20VAC5-314 Regulations Governing Interconnection of Small Electrical Generators  

  • REGULATIONS
    Vol. 25 Iss. 8 - December 22, 2008

    TITLE 20. PUBLIC UTILITIES AND TELECOMMUNICATIONS
    STATE CORPORATION COMMISSION
    Chapter 314
    Reproposed Regulation

    REGISTRAR'S NOTICE: The State Corporation Commission is exempt from the Administrative Process Act in accordance with § 2.2-4002 A 2 of the Code of Virginia, which exempts courts, any agency of the Supreme Court, and any agency that by the Constitution is expressly granted any of the powers of a court of record.

    Title of Regulation: 20VAC5-314. Regulations Governing Interconnection of Small Electrical Generators (adding 20VAC5-314-10 through 20VAC5-314-170).

    Statutory Authority: §§ 12.1-13 and 56-578 of the Code of Virginia.

    Public Hearing Information: Public hearing will be held upon request.

    Public Comments: Public comments may be submitted until 5 p.m. on January 15, 2009.

    Agency Contact: Michael Martin, Senior Utilities Engineer, State Corporation Commission, P.O. Box 1197, Richmond, VA 23218, telephone (804) 371-9336, FAX (804) 371-9350, or email mike.martin@scc.virginia.gov.

    Summary:

    Pursuant to § 56-578 A of the Virginia Electric Utility Restructuring Act, Chapter 23 (§ 56 576 et seq.) of Title 56 of the Code of Virginia (Restructuring Act), all electric energy distributors have the obligation to connect any retail customer, including those using distributed generation, located within its service territory to the distributor's facilities used for delivery of retail electric energy, subject to State Corporation Commission (commission) rules and regulations and approved tariff provisions relating to connection of service. In accordance with § 56-578 C of the Restructuring Act, the commission proposed interconnection standards, not inconsistent with nationally recognized standards, to ensure transmission and distribution safety and reliability. Based upon comments received on the proposed interconnection standards published in the Virginia Register, the commission now directs that revisions to the proposed interconnection standards be made available for comment. These interconnection standards are now republished as reproposed regulations for further comment.

    The interconnection regulations establish standardized interconnection and operating requirements for the safe operation of electric generating facilities with a rated capacity of 20 MW or less connected to the distribution systems of electric utilities under the jurisdiction of the Virginia State Corporation Commission. These requirements apply to retail electric customers, independently owned generators or any other parties operating or intending to operate a distributed generation facility. The regulations establish three interconnection review paths for interconnection of customer-sited generation in Virginia - Level 1, Level 2 and Level 3. Level 1 interconnections must include a request to interconnect a certified inverter-based generating facility no larger than 500 kW. To qualify for a Level 2 interconnection request, the generating facility can be no larger than 2 MW and the proposed generator must meet certain specified codes, standards, and certification requirements. Level 3 interconnection requests apply to generating facilities larger than 2 MW but no larger than 20 MW or a generating facility that does not pass the Level 1 or Level 2 Process. The revised proposed interconnection regulations for distributed generation are intended to more clearly delineate the responsibility of each party under an interconnection agreement. The revisions also clearly identify the cost responsibility of each party while more clearly identifying what costs can be charged interconnection customers. Moreover, the revisions are intended to make the interconnection regulations more readable.

    AT RICHMOND, NOVEMBER 26, 2008

    COMMONWEALTH OF VIRGINIA, ex rel.

    STATE CORPORATION COMMISSION

    CASE NO. PUE-2008-00004

    Ex Parte: In the matter of establishing
    interconnection standards for distributed
    electric generation

    ORDER

    On February 26, 2008, the State Corporation Commission ("Commission") issued an Order Establishing Proceeding in the above-captioned case to consider interconnection standards for distributed generation for the Commonwealth in accordance with § 56‑578 A of the Virginia Electric Utility Restructuring Act, Chapter 23 (§ 56‑576 et seq.) of Title 56 of the Code of Virginia ("Code"). The Staff of the Commission developed proposed rules to meet the requirement of § 56‑578 C of the Restructuring Act, Chapter 314, Regulations Governing Interconnection of Small Electrical Generators, and the Commission directed that notice be given to the public and invited comments on Staff's proposed rules.

    Following comments filed on Staff's proposed rules,1 the Commission granted Staff leave to file a response to the comments filed.2

    On October 27, 2008, the Staff of the Commission filed its Motion for Leave to File ("Motion") requesting that it be granted leave to file its Staff Report, also filed on October 27, 2008, one business day out of time. The Staff Report includes revised rules in response to the comments filed.

    NOW THE COMMISSION, having considered Staff's Motion, is of the opinion and finds that it should be granted. We further find that notice of Staff's revised rules, attached hereto as Appendix A, should be given to the public and that interested persons should have an opportunity to comment on Staff's revised rules (Appendix A).

    Accordingly, IT IS ORDERED THAT:

    (1) Staff is hereby granted its Motion and the Staff Report filed on October 27, 2008, is hereby received into the record of this case.

    (2) The Commission's Division of Information Resources shall forward a copy of this Order including Appendix A to the Registrar of Regulations for publication in the Virginia Register.

    (3) On or before January 15, 2009, interested persons may file an original and fifteen (15) copies of comments with Joel H. Peck, Clerk, State Corporation Commission, c/o Document Control Center, P.O. Box 2118, Richmond, Virginia 23218. Comments shall refer to Case No. PUE‑2008‑00004 and address Staff's revised rules (Appendix A).

    (4) This matter shall remain open for further order of the Commission.

    Commissioner Dimitri did not participate in this matter.

    AN ATTESTED COPY hereof shall be sent by the Clerk of the Commission to: T. Borden Ellis, Senior Attorney, Legal, NiSource Corporate Services Company, 1809 Coyote Drive, Chester, Virginia 23836; Noelle J. Coates, Esquire, Hunton & Williams LLP, Riverfront Plaza, East Tower, 951 East Byrd Street, Richmond, Virginia 23219-4074; Horace P. Payne, Jr., Esquire, Dominion Resources Services, Inc., 120 Tredegar Street, RS‑2, Richmond, Virginia 23219; John A. Pirko, Esquire, LeClairRyan, P.C., 4201 Dominion Boulevard, Suite 200, Glen Allen, Virginia 23060; Charles E. Bayless, Esquire, Appalachian Power Company, P.O. Box 1986, Charleston, West Virginia 25327; Kevin Fox, Esquire, Keyes & Fox LLP, 5727 Keith Avenue, Oakland, California 94618; C. Meade Browder, Jr., Senior Assistant Attorney General, Division of Consumer Counsel, Office of Attorney General, 900 East Main Street, 2nd Floor, Richmond, Virginia 23219; and the Commission's Office of General Counsel and Divisions of Energy Regulation and Economics and Finance.

    _______________________________________

    1 The Commission granted extensions for comments to be filed on May 15, 2008, and August 28, 2008.

    2 Order issued August 28, 2008. The Staff was granted a filing extension to October 24, 2008, by Order Granting Extension to Staff issued September 24, 2008.

    CHAPTER 314
    REGULATIONS GOVERNING INTERCONNECTION OF SMALL ELECTRICAL GENERATORS

    20VAC5-314-10. Applicability and scope.

    These regulations are promulgated pursuant to § 56-578 of the Virginia Electric Utility Restructuring Act (§ 56-576 et seq. of the Code of Virginia). They establish standardized interconnection and operating requirements for the safe operation of electric generating facilities with a rated capacity of 20 megawatts (MW) or less connected to [ distribution companies' electric utility ] distribution [ (and in certain cases transmission) ] systems in Virginia. These [ requirements regulations ] apply to retail electric customers, independently owned generators [ or and ] any other parties operating [ , ] or intending to operate [ , ] a distributed generation facility [ in parallel with a utility's system and to the utility ]. [ Interconnections These regulations do not apply to customer generators operating pursuant to the commission's Regulations Governing Net Energy Metering (20VAC5-315) or those ] that fall under the jurisdiction of the Federal Energy Regulatory Commission [ are not subject to these regulations ].

    [ If the utility has turned over control of its transmission system to a Regional Transmission Entity (RTE), and if the small generator interconnection process identifies upgrades to the transmission system as necessary to interconnect the small generating facility, then the utility will coordinate with the RTE, and the procedures herein will be adjusted as necessary to satisfy the RTE's requirements with respect to such upgrades. ]

    There are three [ interconnection ] review paths for [ the ] interconnection of [ customer-sited ] generation in Virginia [ having an output of not more than 20 MW ]:

    Level 1 - A request to interconnect a [ certified inverter-based ] small generating facility [ (SGF) ] no larger than 500 kilowatts (kW) shall be evaluated under the Level 1 process.

    Level 2 - A request to interconnect a certified [ small generating facility SGF no ] larger than [ 500 kW but no larger than ] 2 MW [ and not qualifying for the Level 1 process ] shall be evaluated under the Level 2 process.

    Level 3 - A request to interconnect [ a small generating facility larger than 2 MW but an SGF ] no larger than 20 MW [ or a small generating facility that does not pass and not qualifying for ] the Level 1 [ process ] or Level 2 process, shall be evaluated under the Level 3 process.

    [ An SGF proposed to be interconnected to a distribution feeder may be limited to a capacity substantially less than 20 MW, depending upon the characteristics of that feeder and the potential for upgrading it, as well as the nature of the loads and other generation on the feeder relative to the proposed point of interconnection. ]

    The utility shall designate an employee or office from which [ the interconnection customer ("IC") may informally request ] information [ on concerning ] the application process [ can be obtained through informal requests from the interconnection customer presenting a proposed project for a specific site ]. The name, telephone number, and email address of such contact employee or office shall be made available on the utility's Internet web site. Electric system information [ for specific locations, feeders, or small areas relevant to the location of the proposed SGF ] shall be provided to the [ interconnection customer IC ] upon request and may include [ relevant system studies, ] interconnection studies [ , ] and [ any ] other [ relevant ] materials [ useful to an understanding of an interconnection at a particular point on the utility's system ], to the extent such provision does not violate confidentiality provisions of prior agreements or [ release ] critical infrastructure [ requirements information ]. The utility shall comply with reasonable requests for such information unless the information is proprietary or confidential and cannot be provided pursuant to a confidentiality agreement.

    The utility shall make reasonable efforts to meet all time frames provided in these [ procedures regulations ] unless the utility and the [ interconnection customer IC ] agree to a different schedule. If the utility cannot meet a deadline provided herein, it shall notify the [ interconnection customer IC ], explain the reason for the failure to meet the deadline, and provide an estimated time by which it will complete the applicable interconnection procedure in the process.

    20VAC5-314-20. Definitions.

    The following terms when used in this chapter shall have the following meaning unless the context clearly indicates otherwise:

    "Affected system" means an electric [ utility ] system other than [ that of ] the [ utility's distribution system utility ] that may be affected by the proposed interconnection.

    [ "Affected system operator" means an entity that operates an affected system or, if the affected system is under the operational control of an independent system operator or a regional transmission entity, such independent entity.

    "Applicable laws and regulations" means all duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any government authority.

    "Attachment facilities" means the facilities and equipment owned, operated, and maintained by the utility that are built new in order to physically connect the customer's interconnection facilities to the utility system. Attachment facilities shall not include distribution upgrades or previously existing distribution and transmission facilities. ]

    "Business day" means Monday through Friday, excluding federal holidays.

    [ "Certified" has the meaning ascribed to it in Schedule 2 of this chapter.

    "Customer's interconnection facilities" means all of the facilities and equipment owned, operated and maintained by the interconnection customer, between the small generating facility and the point of interconnection necessary to physically and electrically interconnect the small generating facility to the utility system. ]

    "Commission" means the Virginia State Corporation Commission.

    [ "Distribution company" means the utility that owns and/or operates the distribution system located in Virginia to which the small generation facility proposes to interconnect its small generating facility. ]

    [ "Default" means the failure of a breaching party to cure its breach under the small generator interconnection agreement. ]

    "Distribution system" means [ a the ] utility's facilities and equipment generally delivering electricity to ultimate customers from substations supplied by higher voltages (usually at transmission level). For purposes of these [ interconnection rules regulations], all portions of the [ distribution company's utility's ] transmission system regulated by the commission for which interconnections are not within Federal Energy Regulatory Commission (FERC) jurisdiction are considered [ also ] to be [ part of subject to ] these interconnection [ rules regulations ].

    "Distribution upgrades" means the additions, modifications, and upgrades to the utility's distribution system at or beyond the point of interconnection [ to facilitate necessary to abate problems on the utility's distribution system caused by the ] interconnection of the small generating facility [ and to render the service necessary to effect the interconnection customer's operation of on-site generation ]. Distribution upgrades do not include [ customer's ] interconnection facilities [ or attachment facilities ].

    "Energy service provider" means any entity supplying electric energy [ service ] to the [ producer, either as tariffed, competitive, or default service pursuant to § 56-585 of the Code of Virginia interconnection customer ].

    [ "Facilities study" has the meaning ascribed to it in 20VAC5-314-70 E.

    "Feasibility study" has the meaning ascribed to it in 20VAC5-314-70 C.

    "FERC" means the Federal Energy Regulatory Commission.

    "Good Utility Practice" means any of the practices, methods and acts engaged in or approved by a significant portion of the electric industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good Utility Practice is not intended to be limited to the optimum practice, method, or act to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region.

    "Governmental authority" means any federal, state, local or other governmental regulatory or administrative agency, court, commission, department, board, or other governmental subdivision, legislature, rulemaking board, tribunal, or other governmental authority having jurisdiction over the parties, their respective facilities, or the respective services they provide, and exercising or entitled to exercise any administrative, executive, police, or taxing authority or power; provided that such term does not include the interconnection customer, the utility or a utility affiliate. ]

    "Interconnection customer" or "IC" means any entity [ , including the utility, any affiliates or subsidiaries of either, ] proposing to interconnect a new small generating facility with the [ utility's utility ] system [ under this chapter ] .

    [ "Interconnection facilities" means the utility's interconnection facilities and the interconnection customer's interconnection facilities. Collectively, interconnection facilities include all facilities and equipment between the small generating facility and the point of interconnection, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the small generating facility to the utility's distribution system. Interconnection facilities are sole use facilities and shall not include distribution upgrades. ]

    "Interconnection request" means the [ interconnection customer's IC's ] request, in accordance with the tariff, to interconnect a new small generating facility, or to increase the capacity of, or make a material modification to the operating characteristics of, an existing small generating facility that is interconnected with the [ utility's utility ] system.

    "Interconnection [ study studies ] " means the [ study that is undertaken studies conducted ] by the [ company utility ], or a [ mutually agreed upon ] third party agreed to by the [ company utility ] and the [ producer interconnection customer ], in order to determine the interaction of the small generating facility [ and with ] the [ distribution utility ] system [ , ] and [ the affected systems in order ] to specify any [ modification modifications ] to the small generating facility or the [ distribution system needed electric systems studied ] to ensure safe and reliable operation of the small generating facility in parallel with the [ distribution utility ] system.

    [ "Material modification" means a modification that has a material impact on the cost or timing of any interconnection request with a later queue priority date.

    "Operating requirements" means any operating and technical requirements that may be applicable due to regional transmission entity, independent system operator, control area, or the utility's requirements, including those set forth in the Small Generator Interconnection Agreement. ]

    "Party" or "parties" means the utility, interconnection customer, or [ any combination thereof both ].

    "Point of interconnection" means the point where the [ customer's ] interconnection facilities connect [ with to ] the [ utility's utility ] system.

    [ "Producer" means a person operating a small generating facility interconnected to the distribution system of a utility for the purpose of parallel operation.

    "Regional Transmission Entity" or "RTE" means an entity having the management and control of a utility's transmission system as further set forth in § 56-579 of the Code of Virginia. ]

    "Small generating facility" [ or "generator" or "SGF" ] means the interconnection customer's [ device equipment ] for the production of electricity identified in the interconnection request [ , but shall not include the interconnection facilities not owned by the interconnection customer ].

    [ "Study process" means the procedure for evaluating an interconnection request that includes the Level 3 scoping meeting, feasibility study, system impact study, and facilities study.

    "Small Generator Interconnection Agreement" or "SGIA" means the agreement between the utility and the interconnection customer as set forth in Schedule 6 of 20VAC5-314-170.

    "Supplemental review" has the meaning ascribed to it in 20VAC5-314-60 G. ]

    "System" [ or "utility system" ] means the [ distribution and transmission ] facilities owned, controlled, or operated by the utility that are used to [ provide electric service under the tariff deliver electricity ].

    [ "System impact study" has the meaning ascribed to in 20VAC5-314-70 E. ]

    "Tariff" means the rates, terms and conditions filed by the utility with the commission for the purpose of providing commission-regulated electric service to retail customers.

    [ "Transmission system" means the utility's facilities and equipment delivering electric energy to the distribution system, such facilities being operated at voltages above the utility's typical distribution system voltages. ]

    "Utility" means the public utility company subject to regulation by the commission pursuant to Chapter 10 (§ 56-232 et seq.) of Title 56 of the Code of Virginia with regard to rates and/or service quality [ to which the interconnection customer proposes to interconnect a small generating facility ].

    20VAC5-314-30. Siting of distributed generation facilities.

    Prior to installing a small generating facility, the [ IC interconnection customer ] must ensure compliance with local, state and federal laws and regulations, including [ siting. If the producer has satisfied the requirements of this chapter and has submitted a copy of his interconnection notification form to the commission's Division of Energy Regulation, the statutory requirements of § 56-580 D all applicable easements and permits, and §§ 56-265.2 and 56-580 ] of the Code of Virginia [ shall be deemed to have been met, as applicable ].

    20VAC5-314-40. Level 1 interconnection process.

    [ A. ] The Level 1 interconnection [ path process ] is available to any [ IC interconnection customer ] proposing to interconnect a small generating facility with the [ utility's distribution utility ] system if the [ small generating facility SGF ] is no larger than 500 kW. [ In order to interconnect under this path, the small generating facility shall complete the streamlined Interconnection Request Form contained in 20VAC5-314-170 as Schedule 1. The utility shall follow the same time line established by the commission in 20VAC5-315-30 of the Net Metering Regulations.

    B. An IC may begin operation of a small generating facility when:

    1. The IC has completed the Level 1 Interconnection Request Form (Schedule 1 in 20VAC5-314-170) and submitted it to the utility with the required $100 processing fee attached. The utility shall submit a copy of the Interconnection Notification Form to the commission's Division of Energy Regulation. The utility may supply a commission-approved Interconnection Request Form similar to Schedule 1;

    2. If required by the utility's tariff, the IC has installed a lockable, utility-accessible, load breaking manual disconnect switch;

    3. A licensed electrician has certified, by signing the Interconnection Request Form, that any required manual disconnect switch has been installed properly and that the small generating facility has been installed in accordance with the manufacturer's specifications as well as all applicable provisions of the National Electrical Code;

    4. The vendor of the SGF has certified on the Interconnection Request Form that the SGF equipment is in compliance with the requirements established by Underwriters Laboratories or other national testing laboratories in accordance with IEEE Standard 1547, Standard for Interconnecting Distributed Resources with Electric Power Systems;

    5. In the case of a static inverter-connected SGF with an alternating current capacity in excess of 10 kilowatts, the IC has had the inverter settings inspected by the utility. The utility may not impose a charge for the inspection;

    6. In the case of a nonstatic inverter-connected SGF, the IC has interconnected according to the utility's interconnection guidelines, and the utility has inspected all protective equipment settings. The utility may not impose a charge for such inspection.

    7. In the case of an SGF having an alternating current capacity greater than 25 kilowatts, the following requirements shall be met before interconnection may occur:

    a. Distribution facilities and customer impact limitations. An SGF shall not be permitted to interconnect to distribution facilities if the interconnection would reasonably lead to damage to any of the utility's facilities or would reasonably lead to voltage regulation or power quality problems at other customer revenue meters due to the incremental effect of the SGF on the performance of the system, unless the IC reimburses the utility for its cost to modify any facilities needed to accommodate the interconnection.

    b. Secondary, service, and service entrance limitations. The capacity of the SGF shall be less than the capacity of the utility-owned secondary, service, and service entrance cable connected to the point of interconnection, unless the IC reimburses the utility for its cost to modify any facilities needed to accommodate the interconnection.

    c. Transformer loading limitations. The SGF shall not have the ability to overload the utility's distribution transformer, or any distribution transformer winding, beyond manufacturer or nameplate ratings, unless the IC reimburses the utility for its cost to modify any facilities needed to accommodate the interconnection.

    d. Integration with utility's grounding. The grounding scheme of the SGF shall comply with the IEEE 1547, Standard for Interconnecting Distributed Resources with Electric Power Systems, and shall be consistent with the grounding scheme used by the utility. If requested by an IC, the utility shall assist the IC in selecting a grounding scheme that coordinates with its distribution system.

    e. Balance limitation. The SGF shall not create a voltage imbalance of more than 3.0% at any other customer's revenue meter if the utility distribution transformer, with the secondary connected to the point of interconnection, is a three-phase transformer, unless the IC reimburses the utility for its cost to modify any facilities needed to accommodate the interconnection.

    C. Neither the utility nor the energy service provider shall impose any charges upon an IC for any interconnection requirements specified by this chapter, except as may be incurred in providing off-site metering.

    D. The IC shall immediately notify the utility of any changes in the ownership of, operational responsibility for, or contact information for the SGF.

    E. The utility shall not be required to maintain an interconnection with an SGF if the SGF or associated equipment is found to be out of compliance with the codes, standards and certifications applicable to the SGF. ]

    20VAC5-314-50. Levels [ 1 2 ] and [ 2 3 ] interconnection request general requirements.

    A. The interconnection customer shall submit [ it’s a completed Levels 2 and 3 ] Interconnection Request Form [ contained in (Schedule 4 of ] 20VAC5-314-170 [ (Schedule 4 ]) to the utility, with the processing fee or deposit specified in the Interconnection Request Form. [ The utility shall provide a copy of the Interconnection Request Form to the commission's Division of Energy Regulation. ] The Interconnection Request Form shall be date- and time-stamped upon receipt by the utility [ , which. The date- and time-stamp of a completed Interconnection Request Form ] shall be used as the qualifying date- and time-stamp for the purposes of any timetable in these procedures. The interconnection customer shall be notified of receipt by the utility within three business days of receiving the interconnection request, which notification may be [ to an by US mail, ] email address or fax number provided by the IC.

    The utility shall notify the interconnection customer within 10 business days of the receipt of the Interconnection Request Form as to whether the Interconnection Request Form is complete or incomplete. If the Interconnection Request Form is incomplete, the utility shall [ provide, along with the notice that the Interconnection Request Form is incomplete, so notify the IC, including ] a written list detailing all information that must be provided to complete the Interconnection Request Form.

    The interconnection customer [ will shall ] have 10 business days after receipt of the notice [ of incomplete information ] to submit the listed information or to request an extension of time to provide such information. If the [ interconnection customer IC ] does not provide the listed information or a request for an extension of time within the deadline, the Interconnection Request Form will be deemed withdrawn. [ An Interconnection Request Form will be deemed complete upon submission of the listed information to the utility.

    The utility shall provide a copy of the final completed date- and time-stamped Interconnection Request Form to the commission's Division of Energy Regulation. ]

    B. Any [ material ] modification to machine data or equipment configuration or to the interconnection site of the small generating facility as specified in the Interconnection Request Form but not agreed to in writing by the utility and the [ interconnection customer IC ] may be deemed a withdrawal of the Interconnection Request Form and may require submission of a new Interconnection Request Form, unless proper notification of each party by the other and a reasonable time to cure the problems created by the changes are undertaken.

    C. Site control documentation must be submitted with the [ interconnection request Interconnection Request Form ]. [ Any information appearing in public records may not be labeled Confidential. (Confidential information is discussed in 20VAC5-314-110.) ] Site control may be demonstrated through:

    1. Ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the small generating facility;

    2. An option to purchase or acquire a leasehold site for such purpose;

    3. An exclusivity or other business relationship between the interconnection customer and the entity having the right to sell, lease, or grant the [ interconnection customer IC ] the right to possess or occupy a site for such purpose.

    D. The utility shall place interconnection requests [ in into ] a first come, first served [ order per queue that is based on the interconnection's distribution ] feeder and [ per distribution ] substation [ . The queue position shall be ] based upon the date- and time-stamp of the [ completed ] Interconnection Request Form. The [ order of each Interconnection Request Form queue position of an interconnection request ] will be used to determine the cost responsibility for the [ necessary ] upgrades [ necessary to accommodate the interconnection ]. At the utility's option, interconnection requests may be studied serially or in clusters for the purpose of the system impact study.

    [ E. The utility shall not be required to maintain an interconnection with an SGF if the SGF or associated equipment is found to be out of compliance with the codes, standards and certification applicable to the SGF. ]

    20VAC5-314-60. Level 2 interconnection process.

    A. The Level 2 interconnection process is available to an interconnection customer proposing to interconnect a small generating facility with the [ utility's distribution utility ] system if the [ small generating facility SGF ] is no larger than 2 MW and [ if the interconnection customer's proposed small generating facility does not qualify for the Level 1 process, and ] meets the codes, standards, and certification requirements of Schedules 2 and 3 in 20VAC5-314-170.

    B. Within 15 business days after the utility notifies the [ interconnection customer IC ] it has received a complete [ interconnection request Interconnection Request Form ], the utility shall perform an initial review using the screens set forth below and shall notify the [ interconnection customer IC ] of the results including copies of the analysis and data underlying the utility's determinations under the screens.

    [ 1. The proposed small generating facility's point of interconnection must be on a portion of the utility's distribution system that is subject to the tariff. ]

    [ C. Interconnection to radial circuits. ]

    [2. 1. ] For interconnection of a [ proposed ] small generating facility to a radial distribution circuit, the aggregated generation, including the proposed small generating facility, on the circuit shall not exceed 15% of the line section's annual peak load as most recently measured at the substation or calculated for the line [ segment section ]. A line section is that portion of a [ utility's electric system distribution circuit ] connected to a customer [ that is ] bounded by automatic sectionalizing devices or the end of the [ distribution line circuit ].

    [ 3. 2. ] The [ proposed small generating facility SGF ], in aggregation with other generation on the distribution circuit, shall not contribute more than 10% to the [ distribution ] circuit's maximum fault current at the point on the distribution [ feeder feeder's (primary) ] voltage [ (primary) ] level [ that is ] nearest the [ proposed ] point of [ change of ownership interconnection ].

    [ 4. 3. ] The [ proposed small generating facility SGF ], in aggregate with other generation on the distribution circuit, shall not cause any distribution protective devices and equipment (including, but not limited to, substation breakers, [ fuse fused ] cutouts, and line reclosers), or interconnection customer equipment on the system to exceed 87.5% of the short circuit interrupting capability; nor shall the interconnection be [ proposed for permitted on ] a circuit [ that already exceeds where ] 87.5% of the short circuit interrupting capability [ is already exceeded ].

    [ 5. Using 4. For interconnections to the distribution primary voltage, use ] the table below, [ to ] determine the [ acceptable ] type of interconnection to a primary distribution [ line circuit ]. This screen includes a review of the type of electrical service provided to the [ interconnection customer IC ], including line configuration and the transformer connection [ , ] to limit the potential for creating over-voltages on the utility's [ electric power distribution ] system due to a loss of ground during the operating time of any anti-islanding function.

    Primary Distribution Line Type

    Type of Interconnection to Primary Distribution Line

    Result/Criteria

    Three-phase, three wire

    Three-phase [ , ] or single phase, phase-to-phase

    Pass screen

    Three-phase, four wire

    Effectively-grounded three phase [ , ] or single-phase, line-to-neutral

    Pass screen

    [ 6. 5. ] If the [ proposed ] small generating facility is to be interconnected [ on to a ] single-phase shared secondary, the aggregate generation capacity on the shared secondary, including the proposed [ small generating facility SGF ], shall not exceed 20 kW.

    [ 7. 6. ] If the [ proposed small generating facility SGF ] is single-phase and is to be interconnected on a center tap neutral of a 240 volt service, its addition shall not create an imbalance between the two sides of the 240 volt service of more than 20% of the nameplate rating of the service transformer.

    [ 8. 7. ] The [ small generating facility SGF ], in aggregate with [ other ] generation interconnected to the transmission side of [ a the ] substation transformer [ feeding that feeds ] the [ distribution ] circuit where the [ small generating facility SGF ] proposes to interconnect [ , ] shall not exceed 10 MW in an area where there are known, or posted, transient stability limitations to generating units located in the general electrical vicinity (e.g., three or four transmission busses from the point of interconnection).

    [ 9. 8. ] No construction of facilities by the utility on its own system shall be required to accommodate the [ small generating facility SGF, except minor modifications ].

    [ C. D. ] Interconnections to [ distribution systems secondary voltage networks (120 volts to 480 volts) ].

    1. For interconnection of a [ proposed ] small generating facility to the load side of spot network protectors serving more than a single customer, the [ proposed small generating facility SGF ] must utilize an inverter-based equipment package and, together with the aggregated other inverter-based generation, shall not exceed the smaller of 5.0% of a spot network's maximum load or 300 kW. For spot networks serving a single customer, the [ small generating facility SGF ] must use [ an ] inverter-based equipment package and either meet the requirements above [ , ] or [ shall ] use a protection scheme [ , ] or operate the generator so as not to exceed on-site load or otherwise prevent nuisance operation of the spot network protectors.

    2. For interconnection of [ a proposed small generating facility an SGF ] to the load side of area network protectors, the [ proposed small generating facility SGF ] must utilize an inverter-based equipment package and, together with the aggregated other inverter-based generation, shall not exceed the smaller of 10% of an area network's minimum load [ , ] or 500 kW.

    3. [ Notwithstanding subdivision 1 or 2 of this subsection, each utility may incorporate into its interconnection standards any change in interconnection guidelines related to networks pursuant to standards developed under IEEE 1547 for interconnections to networks. ] To the extent [ the any ] new IEEE standards conflict with this chapter, [ in particular IEEE 1547, ] the new standards shall apply. In addition, [ and with the consent of the ] utility [ , a small generating facility may be interconnected consent shall not be unreasonably withheld from an SGF interconnecting ] to a spot or area network provided the [ facility SGF ] utilizes a protection scheme that will prevent any power export from the [ customer's IC's ] site including inadvertent export under fault conditions [ or, and ] otherwise prevent nuisance operation of the network protectors.

    [ D. E. ] If the [ proposed ] interconnection passes the screens, the interconnection request shall be approved and the utility will provide the interconnection customer an executable interconnection agreement within [ 10 five ] business days after the determination.

    [ E. F. ] If the [ proposed ] interconnection fails any screens, but the utility determines that the small generating facility may nevertheless be interconnected consistent with safety, reliability, and power quality standards, the utility shall provide the [ interconnection customer IC ] an executable interconnection agreement within five business days after the determination.

    [ F. G. ] If the [ proposed ] interconnection fails [ the any ] screens, but the utility does not or cannot determine from the initial review that the [ small generating facility SGF ] may nevertheless be interconnected consistent with safety, reliability, and power quality standards [ , ] unless the [ interconnection customer IC ] is willing to consider minor modifications or further study, the utility shall provide the [ interconnection customer IC ] with the opportunity to attend a customer options meeting.

    [ G. H. ] If the utility determines the [ Interconnection Request Form interconnection ] cannot be approved without minor modifications at minimal cost; a supplemental study or other additional studies or actions; or at significant cost to address safety, reliability, or power quality problems, [ within the five business day period after the determination, ] the utility shall notify the [ interconnection customer IC ] and provide copies of the data and analyses underlying its conclusion [ within five business days after determination ]. Within 10 business days of the [ utility's ] determination, the utility shall offer to convene a customer options meeting [ with the utility ] to review possible [ interconnection customer IC ] facility modifications [ , ] or the screen analysis and related results, to determine what further steps are needed to permit the [ small generating facility SGF ] to be connected safely and reliably. At the time of notification of the utility's determination, or at the customer options meeting, the utility shall:

    1. Offer to perform facility modifications or minor modifications to the utility's electric system (e.g., changing meters, fuses, relay settings) and provide [ a nonbinding good faith an ] estimate of the [ limited ] cost to make such modifications to the utility's electric system;

    2. Offer to perform a supplemental review if the utility concludes that the supplemental review might determine that the [ small generating facility SGF ] could continue to qualify for interconnection pursuant to the [ fast track Level 2 ] process, and provide [ a nonbinding good faith an ] estimate of the costs and time of such review; or

    3. [ Obtain the interconnection customer's agreement Offer ] to continue evaluating the interconnection request [ , but ] under the Level 3 [ study interconnection ] process.

    [ H. I. ] Supplemental review.

    If [ the interconnection customer agrees to ] a supplemental review [ , is offered to ] the interconnection customer [ shall agree in writing within 15 business days of the offer and submit a deposit for the estimated costs provided in subdivision G 2 of this section and the IC agrees to the supplemental review, the utility shall, within 10 business days of the request, provide to the IC an appropriate supplemental review agreement. To maintain its position in the utility’s interconnection queue, the IC must execute the supplemental review agreement and return it to the utility, along with a deposit for the estimated cost of the supplemental review, within 15 business days after receipt of the agreement. If the IC fails to return the executed supplemental review agreement along with the deposit within 15 business days after receipt, the interconnection request shall be deemed withdrawn and shall lose its place in the utility’s interconnection queue ].

    The [ interconnection customer IC ] shall be responsible for the utility's actual costs [ for of ] conducting the supplemental review. The [ interconnection customer IC ] shall pay any review costs that exceed the deposit within [ 20 30 ] business days of receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced costs, the utility will return such excess within [ 20 30 ] business days of the invoice without interest.

    Within 10 business days following receipt of the [ supplemental review agreement and ] deposit [ for a supplemental review ], the utility will determine if the [ small generating facility SGF ] can be interconnected safely and reliably.

    1. If so, [ and if the supplemental review reveals that no modification are required to the customer’s interconnection facilities, or to the system, or to an affected system, ] the utility shall forward an executable interconnection agreement to the interconnection customer within five business days [ after the determination ].

    2. If so, and [ interconnection customer facility the customer’s interconnection facilities ] modifications are required to allow the [ small generating facility SGF ] to be interconnected consistent with safety, reliability, and power quality standards under these procedures, the utility shall forward an executable interconnection agreement to the [ interconnection customer IC ] within five business days after confirmation that the [ interconnection customer IC ] has agreed to make the necessary changes at the [ interconnection customer's IC’s ] cost.

    3. If so, and minor modifications to the utility's electric system are required to allow the [ small generating facility SGF ] to be interconnected consistent with safety, reliability, and power quality standards under the Level 2 process, the utility shall forward an executable interconnection agreement to the [ interconnection customer IC ] within 10 business days [ after the determination ] that requires the [ interconnection customer IC ] to pay the costs of such system modifications prior to interconnection.

    4. If not, the interconnection request will [ continue to ] be [ evaluated under elevated to ] the Level 3 [ study interconnection ] process.

    20VAC5-314-70. Level 3 interconnection process.

    A. The Level 3 interconnection process shall be used by an [ IC interconnection customer ] proposing to interconnect a small generating facility with the [ utility's distribution utility ] system if the [ small generating facility SGF ] is [ (i) larger than 2 MW but ] no larger than 20 MW [ , (ii) not certified, or (iii) certified but did and does ] not pass [ or qualify for ] the Level 1 or Level 2 interconnection [ process processes ]. [ A study process consisting of As needed, a ] scoping [ meeting ], feasibility [ study ], system impact [ study ], and facilities [ study ] shall precede the preparation of [ an interconnection agreement a Small Generator Interconnection Agreement (Schedule 6 of 20VAC5-314-170) ]. [ Feasibility studies, scoping studies, and facility Any of the ] studies may be combined [ for simpler projects ] by mutual agreement of the [ utility and the ] parties.

    B. Scoping [ study meeting ].

    1. A scoping meeting will be held within 10 business days after the [ interconnection request Interconnection Request Form ] is deemed complete, or as otherwise mutually agreed to by the parties. The utility and the [ interconnection customer IC ] shall bring to the meeting personnel, including system engineers and other resources as may be reasonably required to accomplish the purpose of the meeting.

    2. The purpose of the scoping meeting is to discuss the interconnection request. The parties shall [ further ] discuss [ whether the utility should perform a feasibility study or proceed directly to a system impact study, or a facilities study, or an interconnection agreement the studies and the cost responsibilities for the studies ]. [ If the parties agree that a feasibility study should be performed, the utility shall provide the interconnection customer, as soon as possible, but not later than five business days after the scoping meeting, a feasibility study agreement including an outline of the scope of the study and a nonbinding good faith estimate of the cost to perform the study. ]

    3. The scoping meeting may be omitted by mutual agreement. [ In order to remain in consideration for interconnection, an interconnection customer who has requested a feasibility study must return the executed feasibility study agreement within 15 business days. If the parties agree not to perform a feasibility study, the utility shall provide the interconnection customer, no later than five business days after the scoping meeting, a system impact study agreement including an outline of the scope of the study and a nonbinding good faith estimate of the cost to perform the study. ]

    C. Feasibility study.

    [ 1. If the parties agree that a feasibility study should be performed, the utility shall provide the IC with a feasibility study agreement, including an outline of the scope of the feasibility study and an estimate of the cost to perform the study no later than five business days after the scoping meeting or five business days after the decision is made to not have a scoping meeting.

    If the parties agree to not perform a feasibility study, the utility shall provide the IC a system impact study agreement including an outline of the scope of the study and an estimate of the cost to perform the study no later than five business days after the scoping meeting, or five business days after the decision is made to not have a scoping meeting.

    2. To maintain its position in the utility’s interconnection queue, the IC must execute the feasibility study agreement and return it to the utility along with the deposit for the feasibility study within 15 business days after receipt of the agreement. If the IC fails to return the executed feasibility study agreement along with the deposit within 15 business days after receipt of the agreement, the interconnection request shall be deemed withdrawn and the interconnection request shall lose its place in the utility’s interconnection queue. ]

    [ 1. 3. ] A feasibility study shall identify any potential adverse system impacts that would result from the interconnection of the [ small generating facility SGF ].

    [ 2. 4. ] A deposit of [ the lesser of no more than ] 50% of the [ good faith ] estimated feasibility study costs or earnest money of $1,000 may be required from the interconnection customer.

    a. [ Any study fees Study costs ] shall be [ based on ] the [ distribution company's utility’s ] actual [ incremental ] costs and will be invoiced to the [ interconnection customer IC ] after the study is completed and delivered and will include a summary of professional time.

    b. The [ interconnection customer must IC shall ] pay any study costs that exceed the deposit without interest within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the [ distribution company utility ] shall refund such excess within 30 calendar days of the invoice without interest.

    [ 3. 5. ] The feasibility study shall be based on the technical information provided by the [ interconnection customer IC ] in the [ interconnection request Interconnection Request Form ], as may be modified as the result of the scoping meeting. The [ distribution company utility ] reserves the right to request additional technical information from the [ interconnection customer IC ] as may reasonably become necessary consistent with [ Good Utility Practice ] during the course of the feasibility study and as designated in accordance with the standard small generator interconnection procedures. [ All modification made to the interconnection request shall be made in writing to the utility. ] If the interconnection customer modifies its interconnection request, the time to complete the feasibility study may be extended by agreement of the parties.

    [ 4. 6. ] In performing the [ feasibility ] study, the [ distribution company utility ] shall rely, to the extent reasonably practicable, on recent studies. The [ interconnection customer IC ] shall not be charged for such existing studies; however, the [ interconnection customer IC ] shall be responsible for charges associated with any new study or modifications to existing studies that are reasonably necessary to perform the feasibility study.

    [ 5. 7. ] The feasibility study report shall provide the following analyses for the purpose of identifying any potential adverse system impacts that would result from the interconnection of the [ small generating facility as proposed SGF ]:

    a. Initial identification of any circuit breaker short circuit capability limits exceeded [ as a result of the interconnection ];

    b. Initial identification of any thermal overload or voltage limit violations [ resulting from the interconnection ];

    c. Initial review of grounding requirements and electric system protection; and

    d. Description and [ nonbonding ] estimated cost of facilities [ and estimated construction time ] required to interconnect the [ proposed small generating facility SGF ] and to address the identified short circuit and power flow issues.

    [ 6. 8. ] The feasibility study shall model the impact of the [ small generating facility regardless of purpose SGF for all purposes identified in the Interconnection Request Form ] in order to avoid the further expense and interruption of operation for reexamination of feasibility and impacts if the [ interconnection customer IC ] later changes the purpose for which the [ small generating facility SGF ] is being installed.

    [ 7. 9. ] The [ feasibility ] study shall include the feasibility of [ any interconnection at a proposed project site where there could be multiple all ] potential points of interconnection, as requested by the [ interconnection customer IC ] and at the [ interconnection customer's IC’s ] cost.

    [ 8. Once the feasibility study is completed, a 10. A ] feasibility study report shall be prepared and transmitted to the [ interconnection customer. Barring unusual circumstances, the feasibility study must be completed and the feasibility study report transmitted IC ] within 30 business days of the [ interconnection customer's agreement to conduct a feasibility study utility’s receipt of the complete executed feasibility study agreement and required deposit ].

    [ 9. 11. ] If the feasibility study shows no potential for adverse system impacts, [ then within five business days ] the utility shall send the [ interconnection customer IC either an executable Small Generator Interconnection Agreement (Schedule 5, 20VAC5-314-170) or ] a facilities study agreement, including an outline of the scope of the study and [ a nonbinding good faith an ] estimate of the cost to perform the study.

    [ 10. 12. ] If the feasibility study shows [ the ] potential for adverse system impacts, the review process shall proceed to the [ appropriate ] system impact study [ or studies ].

    D. System impact study.

    [ 1. No later than five business days after the parties agree that a system impact study should be performed, the utility shall provide the IC a system impact study agreement including an outline of the scope of the system impact study and an estimate of the cost to perform the study.

    2. To maintain its position in the utility’s interconnection queue, the IC must execute the system impact study agreement and return it to the utility along with the deposit for the system impact study within 15 business days after receipt of the agreement. If the IC fails to return the executed system impact study agreement along with the deposit within 15 business days after receipt of the agreement, the interconnection request shall be deemed withdrawn and the interconnection request shall lose its place in the utility’s interconnection queue.

    3. A deposit equal to the estimated cost of a system impact study may be required from the IC.

    a. Study cost shall be the utility’s actual incremental costs and will be invoiced to the IC after the study is completed and delivered and will include a summary of professional time.

    b. The IC shall pay any study costs that exceed the deposit within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the utility shall refund the excess within 30 calendar days of the invoice without interest. ]

    [ 1. 4. ] A system impact study shall identify and detail the electric system impacts that would result if the [ proposed small generating facility SGF ] were interconnected without project modifications or electric system modifications, focusing on the adverse [ electric ] system impacts identified in the feasibility study, or [ to study potential impacts, including but not limited to those identified ] in the scoping meeting. A system impact study shall evaluate the impact of the proposed interconnection on the reliability of the electric system.

    [ 2. 5. ] A system impact study will be based upon the results of the feasibility study and the technical information provided by the interconnection customer in the interconnection request. The [ distribution company utility ] reserves the right to request additional technical information from the [ interconnection customer IC ] as may reasonably become necessary consistent with [ Good Utility Practice ] during the course of the system impact study. If the [ interconnection customer IC ] modifies its designated point of interconnection, [ or ] interconnection request, or the technical information provided therein [ is modified ], the time to complete the system impact study may be extended.

    [ 3. 6. ] A system impact study shall consist of a [ study of the potentially impacted transmission and distribution systems, a ] short circuit analysis, a stability analysis, a power flow analysis, voltage drop and flicker studies, [ protection and set point coordination studies, and ] grounding reviews, [ distribution load flow study, analysis of equipment interrupting ratings, protection coordination study, and impacts on electric system operation, ] as necessary. A system impact study shall state the assumptions upon which it is based, state the results of the analyses, and provide the requirement or potential impediments to providing the requested interconnection service, including a preliminary indication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the interconnection. A system impact study shall provide a list of facilities [ and modifications ] that [ are would be ] required as a result of the interconnection [ request and nonbinding good faith along with ] estimates of cost responsibility and time to construct. [ If arranged with the utility prior to the utility preparing the system impact study agreement, the system impact study may, at the IC’s cost, include one or more alternatives to the point of interconnection; however, such alternative points must be on the same distribution circuit as the point of interconnection the IC specified as the proposed point of interconnection. ]

    [ 4. A distribution system impact study shall incorporate a distribution load flow study, an analysis of equipment interrupting ratings, protection coordination study, voltage drop and flicker studies, protection and set point coordination studies, grounding reviews, and the impact on electric system operation, as necessary.

    5. 7. ] Affected systems may participate in the preparation of a system impact study, with a division of costs among such entities as they may agree. All affected systems shall be afforded an opportunity to review and comment upon a system impact study that covers potential adverse system impacts on their electric systems, and the [ distribution company utility ] has 20 additional business days to complete a system impact study requiring review by affected systems.

    [ 6. 8. ] If the utility uses a queuing procedure for sorting or prioritizing projects and their associated cost responsibilities for any required network upgrades, the system impact study shall consider all generating facilities (and with respect to clause iii below, any identified upgrades associated with such higher queued interconnection) that, on the date the system impact study is commenced are: (i) directly interconnected with the [ distribution company's electric utility ] system; or (ii) interconnected with affected systems and may have an impact on the proposed interconnection; and (iii) have a pending higher queued interconnection request to interconnect with the [ utility's electric utility ] system.

    [ 7. 9. ] A [ distribution ] system impact study, if required, shall be completed and the results transmitted to the [ interconnection customer IC ] within [ 30 45 ] business days after an agreement is signed by the parties [ . A transmission system impact study, if required, shall be completed and the results transmitted to the interconnection customer within 45 business days after an agreement is signed by the parties ], or in accordance with the utility's queuing procedures.

    [ 8. A deposit of the equivalent of the good faith estimated cost of a distribution system impact study and one-half of the good faith estimated cost of a transmission system impact study may be required from the interconnection customer.

    9. Any study fees shall be based on the utility's actual costs and will be invoiced to the interconnection customer after the study is completed and delivered and will include a summary of professional time.

    10. The interconnection customer shall pay any study costs that exceed the deposit within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the utility shall refund such excess within 30 calendar days of the invoice. Interest shall not apply.

    11. If no transmission system impact study is required, adverse distribution system impacts are identified in the scoping meeting or shown in the feasibility study, a distribution system impact study shall be performed. The utility shall send the interconnection customer a distribution system impact study agreement within 15 business days of transmittal of the feasibility study report, including an outline of the scope of the study and a nonbinding good faith estimate of the cost to perform the study, or following the scoping meeting if no feasibility study is to be performed.

    12. In instances where the feasibility study or the distribution system impact study shows potential for transmission system adverse system impacts, within five business days following transmittal of the feasibility study report, the utility shall send the interconnection customer a transmission system impact study agreement, including an outline of the scope of the study and a nonbinding good faith estimate of the cost to perform the study, if such a study is required.

    13. If a transmission system impact study is not required, but adverse distribution system impacts are shown by the feasibility study to be possible and no distribution system impact study has been conducted, the utility shall send the interconnection customer a distribution system impact study agreement.

    14. If the feasibility study shows no potential for transmission system or distribution system adverse impacts, the utility shall send the interconnection customer either an executable Small Generator Interconnection Agreement (SGIA) included in this chapter as Schedule 5 in 20VAC5-314-170, or a facilities study agreement, including an outline of the scope of the study and a nonbinding good faith estimate of the cost to perform the study, as applicable.

    15. In order to remain under consideration for interconnection, the interconnection customer shall return executed system impact study agreements, if applicable, within 30 business days.

    10. If the system impact study shows that facility modifications are needed to accommodate the SGF, then within five business days following transmittal of the system impact study report, the utility shall send the IC a facilities study agreement, including an outline of the scope of the study and an estimate of the cost to perform the study.]

    E. Facilities study.

    1. [ Once the required system impact study (or studies) is completed, a system impact study report shall be prepared and transmitted to the interconnection customer along with a facilities study agreement within five business days, including an outline of the scope of the study and a nonbinding good faith estimate of the cost to perform the facilities study. In the case where one or both impact studies are determined to be unnecessary, a notice of the fact shall be transmitted to the interconnection customer within the same timeframe. The facilities study shall specify and estimate the cost of the equipment, engineering, procurement, and construction work needed to implement the conclusion of the feasibility and/or system impact study and to allow SGF to be interconnected and operate safely and reliably. ]

    [ 2. In order to remain under consideration for interconnection, or, as appropriate, in the utility's interconnection queue, the interconnection customer shall provide the following information, or a request for an extension of time within 30 business days, and the facilities study shall be based on the responses of the IC to the following queries:

    a. Provide a location plan and simplified one-line diagram of the plant and station facilities. For staged projects, please indicate future generation, transmission circuits, etc. On the one-line diagram, indicate the generation capacity attached at each metering location. (Maximum load on CT (current transformer)/PT (partial transformer) On the one-line diagram, indicate the location of auxiliary power. (Minimum load on CT/PT) Amps

    b. One set of metering is required for each generation connection to the new ring bus or existing distribution company station.

    Number of generation connections: _____________________

    c. Will an alternate source of auxiliary power be available during CT/PT maintenance?

    Yes ___________ No ___________

    d. Will a transfer bus on the generation side of the metering require that each meter set be designed for the total plant generation?

    Yes ___________ No ___________ (Please indicate on the one-line diagram).

    e. What type of control system or Programmable Logic Controller (PLC) will be located at the small generating facility?

    ______________________________________________

    f. What protocol does the control system or PLC use?

    ______________________________________________

    g. Provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines.

    h. Physical dimensions of the proposed interconnection station: ______________________________________________

    i. Bus length from generation to interconnection station: ______________________________

    j. Line length from interconnection station to utility's transmission system. ________________________________________

    k. Tower number observed in the field. (Painted on tower leg)*: ______________________________________________

    l. Number of third party easements required for transmission lines*: ______________________________________________

    *To be completed in coordination with distribution company.

    m. Is the small generating facility located in utility's service area? Yes ___________ No___________;

    If No, please provide name of local provider:

    ______________________________________________

    n. Please provide the following proposed schedule dates:

    Begin Construction Date:____________________________

    Generator step-up transformers receive back feed power date: ___________________

    Generation Testing Date:____________________________

    Commercial Operation Date:____________________________

    3. The facilities study shall specify and estimate the cost of the equipment, engineering, procurement, and construction work (including overheads) needed to implement the conclusions of the system impact study or studies.

    4. A deposit of the good faith estimated facilities study costs may be required from the interconnection customer.

    5. Any study fees shall be based on the distribution company's actual costs and will be invoiced to the interconnection customer after the study is completed and delivered and will include a summary of professional time.

    6. The interconnection customer shall pay any study costs that exceed the deposit within 30 calendar days on receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the distribution company shall refund such excess within 30 calendar days of the invoice. Interest shall not apply.

    2. To maintain its position in the utility’s interconnection queue, the IC must execute the facilities study agreement and return it to the utility along with a completed Facilities Study Information Form (Schedule 5, 20VAC5-314-170) and deposit for the facilities study within 30 business days after receipt of the agreement, unless an extension has been agreed to with the utility. Otherwise, the interconnection request shall be deemed withdrawn and the interconnection request shall lose its place in the utility’s interconnection queue.

    3. A deposit equal to the estimated cost of a facilities study may be required from the IC.

    a. Study cost shall be the utility’s actual incremental costs and will be invoiced to the IC after the study is completed and delivered and will include a summary of professional time.

    b. The IC shall pay any study costs that exceed the deposit within 30 calendar days after receipt of the invoice or resolution of any dispute. If the deposit exceeds the invoiced fees, the utility shall refund the excess within 30 calendar days of the invoice without interest. ]

    [ 7. 4. ] Design for any required [ customer’s ] interconnection facilities [ , attachment facilities, ] and/or upgrades shall be performed under the facilities study [ agreement ]. The utility may contract with consultants to perform activities required under the facilities study [ agreement ]. The [ interconnection customer IC ] and the utility may agree to allow the [ interconnection customer IC ] to separately arrange for the design of some of the [ customer’s ] interconnection facilities. In such cases, facilities design will be reviewed and/or modified prior to acceptance by the utility, under the provisions of the facilities study [ agreement ]. If the parties agree to separately arrange for design and construction, and provided security and confidentiality requirements can be met, the utility shall make sufficient information available to the [ interconnection customer IC ] in accordance with confidentiality and critical infrastructure requirements [ , ] to permit the [ interconnection customer IC ] to obtain an independent design and cost estimate for any necessary facilities.

    [ 8. 5. ] The facilities study shall [ specify and estimate the cost of the equipment, engineering, procurement and construction work (including overheads) needed to implement the conclusions of the system impact study or studies. The facilities study shall also ] identify (i) the electrical switching configuration of the equipment, including, without limitation, transformer, switchgear, meters, and other station equipment, (ii) the nature and estimated cost of the [ utility's interconnection attachment ] facilities and [ distribution ] upgrades necessary to accomplish the interconnection, and (iii) an estimate of the time required to complete the construction and installation of such facilities.

    [ 9. 6. ] The utility may propose to group facilities required for more than one [ interconnection customer IC ] in order to minimize facilities costs through economies of scale, but any [ interconnection customer IC ] may require the installation of facilities required for its own small generating facility if it [ is willing to pay pays ] the costs of those facilities.

    [ 10. Once the facilities study is completed, a facilities study report shall be prepared and transmitted to the interconnection customer. Barring unusual circumstances, the facilities study must be completed and the facilities study report transmitted within 30 business days of the interconnection customer's agreement to conduct a facilities study 11. In cases where upgrades are required, the facilities study must be completed within 45 business days of the receipt of this facilities study agreement. In cases where no upgrades are necessary, and the required facilities are limited to interconnection facilities, the facilities study must be completed within 30 business days.

    7. In cases where system upgrades are required, the utility shall transmit the facilities study report within 45 business days after receipt of the complete facilities study agreement, Facilities Study Information Form, and the deposit. In cases where no system upgrades are necessary, and the required facilities are limited to customer’s interconnection facilities and attachment facilities only, the utility shall transmit the facilities study report within 30 business days after receipt of the complete facilities study agreement, Facilities Study Information Form and the deposit. ]

    F. [ Interconnection agreement Small Generator Interconnection Agreement ].

    1. [ Upon completion of the facilities study, and with the agreement of the interconnection customer to pay for interconnection facilities and upgrades identified in the facilities study, the utility shall provide the interconnection customer an executable SGIA within five business days Within five business days after transmittal of the final study (i.e. the facilities study, or if applicable, a combined study that satisfies all study requirements), the utility shall provide the interconnection customer an executable SGIA (Schedule 6, 20VAC5-314-170) ].

    2. After receiving [ an interconnection agreement the SGIA ] from the utility, the [ interconnection customer IC ] shall have 30 business days or another mutually agreeable [ time frame deadline, ] to sign and return the [ interconnection agreement, or request that the utility file an unexecuted interconnection agreement with the commission SGIA ]. If the [ interconnection customer IC ] does not [ sign return ] the [ interconnection agreement, or ask that it be filed unexecuted by the utility within 30 business days SGIA within the deadline ], the interconnection request shall be deemed withdrawn [ and the IC shall lose its place in the utility’s queue ]. After the [ interconnection agreement SGIA ] is signed by the parties, the interconnection of the [ small generating facility SGF ] shall proceed under the provisions of the SGIA.

    20VAC5-314-80. Interconnection metering.

    Any metering necessitated by the use of the small generating facility shall be installed at the interconnection customer's expense in accordance with commission requirements or the utility's specifications.

    20VAC5-314-90. Commissioning tests.

    Commissioning tests of the interconnection customer's installed equipment shall be performed pursuant to applicable codes and standards, including IEEE 1547.1 2005 "IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems." The utility shall be given at least five business days written notice, or notice as otherwise mutually agreed to by the parties, of the tests and [ may the utility shall ] be [ allowed to be ] present to witness the commissioning tests. The utility shall [ not ] be compensated by the [ interconnection customer IC ] for [ its expense in ] witnessing [ Level 2 and Level 3 ] commissioning tests.

    20VAC5-314-100. Disputes.

    A. The parties agree to attempt to resolve all disputes arising out of the interconnection process according to the provisions of this section.

    B. In the event of a dispute, either party shall provide the other party with a written notice of dispute. The notice shall describe in detail the nature of the dispute. [ If the dispute has not been resolved within five business days after receipt of the notice, either party may contact a mutually agreed upon third party dispute resolution service for assistance in resolving the dispute The parties shall make a good faith effort to resolve the dispute informally within 10 business days ].

    C. [ If the dispute has not been resolved within 10 business days after receipt of the notice, either party may seek resolution assistance from the commission’s Division of Energy Regulation where the matter will be handled as an informal complaint. If that process is unsatisfactory, either party may petition the commission to handle the dispute as a formal complaint.

    Alternatively, the parties may seek resolution through the assistance of a dispute resolution service. ] The dispute resolution service will assist the parties in either resolving the dispute or in selecting an appropriate dispute resolution venue (e.g., mediation, settlement judge, early neutral evaluation, or technical expert) to assist the parties in resolving their dispute. [ Each party agrees to conduct all negotiations in good faith and will be responsible for one half of any costs paid to neutral third parties. ]

    [ D. Each party agrees to conduct all negotiations in good faith and will be responsible for 1/2 of any costs paid to neutral third parties.

    E. D. ] If [ neither party elects to seek assistance from the dispute resolution service, or if the ] attempted dispute resolution fails [ to satisfy one or both of the parties ] , then either party may exercise whatever rights and remedies it may have in equity or law consistent with the terms of the [ agreements between the parties or it may seek resolution at the commission agreement ].

    20VAC5-314-110. Confidential information.

    A. Confidential information shall mean any confidential and/or proprietary information provided by one party to the other party that is clearly marked or otherwise designated "Confidential." All design, operating specifications, and metering data provided by the [ interconnection customer IC ] shall be deemed confidential information regardless of whether it is clearly marked or otherwise designated as such.

    B. Confidential information does not include information previously in the public domain, required to be publicly submitted or divulged by governmental authorities (after notice to the other party and after exhausting any opportunity to oppose such publication or release), or necessary to be divulged in an action to enforce an agreement between the parties. Each party receiving confidential information shall hold such information in confidence and shall not disclose it to any third party nor to the public without the prior written authorization from the party providing that information, except to fulfill obligations under agreements between the parties, or to fulfill legal or regulatory requirements.

    1. Each party shall employ at least the same standard of care to protect confidential information obtained from the other party as it employs to protect its own confidential information.

    2. Each party is entitled to equitable relief, by injunction or otherwise, to enforce its rights under this section to prevent the release of confidential information without bond or proof of damages, and may seek other remedies available at law or in equity for breach of this provision.

    C. Notwithstanding anything in this chapter to the contrary, if the commission, during the course of an investigation or otherwise, requests information from one of the parties that is otherwise required to be maintained in confidence, the party shall provide the requested information to the commission, within the time provided for in the request for information. In providing the information to the commission, the party may request that the information be treated as confidential and nonpublic by the commission and that the information be withheld from public disclosure. Parties are prohibited from notifying the other party prior to the release of the confidential information to the commission. [ The party shall notify the other party when it is notified by the commission that a request to release confidential information has been received by the commission, at which time either of the parties may respond before such information would be made public. ]

    20VAC5-314-120. [ Comparability Equal treatment ].

    The utility shall receive, process, and analyze all interconnection requests in a timely manner as set forth in this chapter. The utility shall use the same reasonable efforts in processing and analyzing interconnection requests from all Interconnection customers, whether the [ small generating facility SGF ] is owned or operated by the utility, its subsidiaries or affiliates, or others.

    20VAC5-314-130. Record retention.

    The utility shall maintain, subject to audit, records for three years of (i) all interconnection requests received pursuant to this chapter, (ii) the times required to complete interconnection request approvals and disapprovals, and (iii) justification for the actions taken on the interconnection requests.

    20VAC5-314-140. Coordination with affected systems.

    The utility shall coordinate the conduct of any studies required to determine the impact of the [ interconnection request small generating facility ] on affected systems with affected system operators and, if possible, include those results (if available) in its applicable interconnection [ study studies ] within the time frame specified in this chapter. The utility will include such affected system operators in all meetings held with the [ interconnection customer IC ] as required by this chapter. The [ interconnection customer IC ] shall cooperate with the utility in all matters related to the conduct of studies and the determination of modifications to affected systems. A utility [ which that ] may be an affected system shall cooperate with the utility with [ whom which ] interconnection has been requested in all matters related to the conduct of studies and the determination of modifications to affected systems. [ The utility owning or operating the system to which the IC desires to interconnect shall not be held responsible or liable for any delays in the interconnection process attributable to the lack of information or cooperation from the owners or operators of affected systems. ]

    20VAC5-314-150. Capacity of the small generating facility.

    A. If the interconnection request is for an increase in capacity for an existing small generating facility, the interconnection request shall be evaluated on the basis of the new total capacity of the [ small generating facility SGF ].

    B. If the interconnection request is for a [ small generating facility SGF ] that includes multiple energy production devices at a site for which the interconnection customer seeks a single point of interconnection, the interconnection request shall be evaluated on the basis of the aggregate capacity of the multiple devices.

    C. The interconnection request shall be evaluated using the maximum rated capacity of the [ small generating facility SGF ].

    20VAC5-314-160. Insurance.

    A. For [ systems of 500 kW or less a small generating facility with a rated capacity not exceeding 10 kW ], the IC, at its own expense, shall secure and maintain in effect during the term of the agreement liability insurance with a combined single limit for bodily injury and property damage of not less than [ $300,000 $100,000 ] for each occurrence.

    [ For an SGF with a rated capacity exceeding 10 kW but not exceeding 500 kW, the IC, at its own expense, shall secure and maintain in effect during the term of the agreement liability insurance with a combined single limit for bodily injury and property damage of not less than $300,000 for each occurrence. ]

    For [ systems greater than an SGF with a rated capacity exceeding ] 500 kW but [ smaller than not exceeding ] 2 MW, the IC, at its own expense, shall secure and maintain in effect during the term of the agreement liability insurance with a combined single limit for bodily injury and property damage of not less than $2 million for each occurrence. Insurance coverage for [ systems greater than an SGF with a rated capacity exceeding ] 2 MW shall be determined on a case-by-case basis [ by the utility ] and shall reflect the size of the installation and the potential for system damage.

    B. Except for those [ photovoltaic inverter-based ] systems [ installed on a residential premise ] that have a [ design rated ] capacity of 500 kW or less, the utility shall be named as an additional insured by endorsement to the insurance policy and the policy shall provide that written notice be given to the utility at least 30 days prior to any cancellation or reduction of any coverage. Such liability insurance shall provide, by endorsement to the policy, that the utility shall not by reason of its inclusion as an additional insured incur liability to the insurance carrier for the payment of premium of such insurance. For all [ photovoltaic inverter-based ] systems, the liability insurance shall not exclude coverage for any incident related to the subject generator or its operation.

    C. Certificates of insurance evidencing the requisite coverage and provision shall be furnished to [ a the ] utility prior to the date of interconnection of the [ small generating facility SGF ]. [ Utilities The utility ] shall be permitted to periodically obtain proof of current insurance coverage form the [ producer IC ] in order to verify [ continuing ] proper liability insurance coverage. [ The ] IC will not be allowed to commence or continue interconnected operations unless evidence is provided that [ satisfactory required ] insurance coverage is in effect at all times.

    20VAC5-314-170. Schedules for Chapter 314.

    The following schedules shall be used in the administration of this chapter.

    Schedule 1

    LEVEL 1 INTERCONNECTION REQUEST FORM FOR SMALL GENERATING FACILITY [ LESS THAN NOT EXCEEDING ] 500 kW

    PURSUANT TO 20VAC5-314-40 OF THE COMMISSION'S REGULATIONS GOVERNING INTERCONNECTION OF SMALL ELECTRIC GENERATORS, APPLICANT HEREBY GIVES NOTICE OF INTENT TO OPERATE A GENERATING FACILITY.

    Section 1. [ Applicant Interconnection Customer ] Information

    Name:____________________________________________________________

    Mailing Address:____________________________________________________

    [ City: ______________________________State: _____________ Zip Code:_____

    City, State, Zip: _________________________________________________]

    Street Address: __________________________________________________

    [ City: ______________________________State: _____________ Zip Code: _____

    City, State, Zip: _________________________________________________]

    Phone Number(s): ___________________________________________________

    Fax Number: _____________________________ Email [ Address ]: _____________

    [ Facility location (if different from above): __________________________________

    Distribution Company Utility ]: ________________________________________________

    [ Distribution Company Utility ] Account Number: ___________________________________

    Energy Service Provider [ (ESP) (if different than electric distribution company)]:________________________________

    [ ESP ] Account Number [ (if applicable) ]: _____________________________________

    Proposed Interconnection Date:_________________________________________

    [ Section 2. Processing Fee or Deposit

    The nonrefundable processing fee payable to the utility is $100. ]

    Section [ 2. 3. Small ] Generating Facility Information

    [ Facility owner and/or Operator name (if different from Applicant): ________________

    SGF owner: _____________________________________________________

    SGF operator: ___________________________________________________ ]

    Business relationship to applicant: _______________________________________

    Mailing address: ______________________________________________________

    [ City: ________________________________State: ____________ Zip Code: ______

    City, State, Zip:__________________________________________________ ]

    [ Street SGF ] Address: _______________________________________________________

    [ City: ________________________________State: ____________ Zip Code: ______

    City, State, Zip: _________________________________________________ ]

    Phone Number(s): ____________________________________________________

    Fax Number: ______________________________ Email [ Address ]: _____________

    Fuel Type:____________________________________________________________

    Generator Manufacturer and Model: ______________________________________

    Rated Capacity in kilowatts: AC: _________________________ DC: ____________

    Inverter Manufacturer and Model:_________________________________________

    Battery Backup [ (circle one) ]: Yes_____ No_____

    Section [ 3 4 ]. Information for Generators with an AC capacity in excess of 25 [ kilowatts kW ]

    Is the proposed generator inverter based? Yes ____ No ____

    Generator Type [ (circle one) ]: Inverter [ ] Induction [ ] Synchronous [ ]

    Frequency: ____________ Hz; Number of phases [ (circle one) ] : One [ ] Three [ ]

    Rated Capacity: DC _________KW; AC apparent ___________ KVA; AC real _________ KW;

    Power factor ____________%; AC voltage _________; AC amperage___________

    Facility schematic and equipment layout must be attached to this form.

    Section [ 4. 5. ] Vendor Certification

    The [ system hardware SGF equipment ] is listed by Underwriters Laboratories to be in compliance with UL [ - ] 1741.

    Signed (Vendor): ______________________________________________ Date: __________

    Name (printed): _______________________________________________________________

    Company: ___________________________________________________________________

    Phone Number: _______________________________

    Mailing Address:_______________________________________________________________

    [ City: _______________________________ State: _____________ Zip Code: _____________

    City, State, Zip: _________________________________________________ ]

    Section [ 5. 6. ] Electrician Certification

    The [ system generator equipment ] has been installed in accordance with the manufacturer's specifications as well as all applicable provisions of the National Electrical Code.

    Signed (Licensed Electrician): ___________________________ Date: ______

    Name (printed): ___________________________________________________

    License Number: __________________________ Phone Number: ___________

    Mailing Address: ____________________________________________________

    [ City: ___________________________ State: _____________ Zip Code: _______

    City, State, Zip:__________________________________________________ ]

    [ Utility signature signifies only receipt of this form, in compliance with the State Corporation Commission's net energy metering regulations, 20 VAC 5-315-30.

    Signed (Utility Representative): ___________________________ Date: _______ ]

    [ Section 7. Applicant Signature ]

    I hereby certify that, to the best of my knowledge, all of the information provided in this Request Form is true and correct.

    Signature of Applicant: _____________________________________________

    Date:________________________

    [ Section 8. Utility Acknowledgement of Receipt

    Signed: _______________________________________________________

    Title:__________________________________________________________

    Utility: ________________________________________________________

    Date:______________________________

    Utility signature signifies only receipt of this form, in compliance with 20VAC5-314-40, the State Corporation Commission's Regulations Governing Interconnection of Small Electrical Generators. ]

    Schedule 2

    Certification of Small Generator Equipment Packages

    Small generating facility equipment proposed for use separately or packaged with other equipment in an interconnection system shall be considered certified for interconnected operation if (i) it has been tested in accordance with industry standards for continuous utility interactive operation in compliance with the appropriate codes and standards referenced below by any Nationally Recognized Testing Laboratory (NRTL) recognized by the United States Occupational Safety and Health Administration to test and certify interconnection equipment pursuant to the relevant codes and standards listed in SGIP Schedule 3, (ii) it has been labeled and is publicly listed by such NRTL at the time of the interconnection application, and (iii) such NRTL makes readily available for verification all test standards and procedures it utilized in performing such equipment certification, and, with consumer approval, the test data itself. The NRTL may make such information available on its website and by encouraging such information to be included in the manufacturer's literature accompanying the equipment.

    The interconnection customer must verify that the intended use of the equipment falls within the use or uses for which the equipment was tested, labeled, and listed by the NRTL.

    Certified equipment shall not require further type-test review, testing, or additional equipment to meet the requirements of this interconnection procedure; however, nothing herein shall preclude the need for an on-site commissioning test by the parties to the interconnection nor follow up production testing by the NRTL.

    If the certified equipment package includes only interface components (switchgear, inverters, or other interface devices), then an [ interconnection customer IC ] must show that the generator or other electric source being utilized with the equipment package is compatible with the equipment package and is consistent with the testing and listing specified for this type of interconnection equipment.

    Provided the generator or electric source, when combined with the equipment package, is within the range of capabilities for which it was tested by the NRTL, and does not violate the interface components' labeling and listing performed by the NRTL, no further design review, testing or additional equipment on the customer side of the point of [ common coupling interconnection ] shall be required to meet the requirements of this interconnection procedure.

    An equipment package does not include equipment provided by the utility.

    Schedule 3

    Certification Codes and Standards

    IEEE1547 Standard for Interconnecting Distributed Resources with Electric Power Systems (including use of IEEE 1547.1 testing protocols to establish conformity)

    UL 1741 Inverters, Converters, and Controllers for Use in Independent Power Systems

    IEEE Std 929-2000 IEEE Recommended Practice for Utility Interface of Photovoltaic (PV) Systems

    NFPA 70 (2005), National Electrical Code

    IEEE Std C37.90.1-1989 (R1994), IEEE Standard Surge Withstand Capability (SWC) Tests for Protective Relays and Relay Systems

    IEEE Std C37.90.2 (1995), IEEE Standard Withstand Capability of Relay Systems to Radiated Electromagnetic Interference from Transceivers

    IEEE Std C37.108-1989 (R2002), IEEE Guide for the Protection of Network Transformers

    IEEE Std C57.12.44-2000, IEEE Standard Requirements for Secondary Network Protectors

    IEEE Std C62.41.2-2002, IEEE Recommended Practice on Characterization of Surges in Low Voltage (1000V and Less) AC Power Circuits

    IEEE Std C62.45-1992 (R2002), IEEE Recommended Practice on Surge Testing for Equipment Connected to Low-Voltage (1000V and Less) AC Power Circuits

    ANSI C84.1-1995 Electric Power Systems and Equipment – Voltage Ratings (60 Hertz)

    IEEE Std 100-2000, IEEE Standard Dictionary of Electrical and Electronic Terms

    NEMA MG 1-1998, Motors and Small Resources, Revision 3

    IEEE Std 519-1992, IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems

    NEMA MG 1-2003 (Rev 2004), Motors and Generators, Revision 1

    Schedule 4

    [ LEVEL LEVELS ] 2 AND 3 INTERCONNECTION REQUEST FORM [ FOR ] SMALL GENERATING [ FACILITIES FACILITY ] LESS THAN 20 MW

    [ Distribution Company:________________________________________

    Designated Contact Person: ________________________________________

    Address: ________________________________________________

    Telephone Number: ____________________

    Fax:________________________________

    E-Mail Address: ________________________________________________

    An Interconnection Request is considered complete when it provides all applicable and correct information required below.

    Processing Fee or Deposit

    If the Interconnection Request is submitted as Level 2, the nonrefundable processing fee payable to the distribution company is $500.

    If the interconnection request is submitted as Level 3, the interconnection customer shall submit to the distribution company a deposit not to exceed $1,000 towards the cost of the feasibility study.

    Interconnection Customer Information

    Legal Name of the Interconnection Customer (or, if an individual, individual's name)

    Name:___________________________________________

    Account Number: ________________________________________________

    Contact person:__________________________________________

    Mailing Address:_________________________________________

    City: State: Zip:_____________________________________________

    Facility location (if different from above):_______________________________

    Telephone (Day): __________________ Telephone (Evening): _____________

    Fax: _________________________ E-Mail Address:_____________________

    Alternative contact information (if different from the interconnection customer)

    Contact Name: ________________________________________________

    Title: ________________________________________________

    Address:_________________________________________

    ________________________________________________

    Telephone (Day): ________________ Telephone (Evening): ________________

    Fax: __________________________ E-Mail Address: ____________________

    Application is for:

    New Small Generating Facility

    Capacity addition to Existing Small Generating Facility

    If capacity addition to existing facility, please describe: _____________________________________________

    Will the Small Generating Facility be used for any of the following?

    To supply power to the interconnection customer? Yes ___No ___

    To supply power to others? Yes ___ No ___

    Contact Name: ________________________________________________

    Title: ________________________________________________

    Address: ________________________________________________

    Telephone (Day): _________________ Telephone (Evening): ______________

    Fax: ________________ E-Mail Address: _____________

    Requested point of interconnection: ____________________________________

    Interconnection customer's requested in-service date: ______________________

    Section 1. Interconnection Customer Information

    Name:

    Contact person:

    Mailing address:

    City: State: Zip:

    Utility and account number:

    Energy Service Provider and account number:

    Facility address:

    Telephone (Day): ___________ (Evening):

    Fax: _______________ E-Mail:

    Alternative contact information

    Contact Name:

    Title:

    Mailing Address: ________________________________________________

    City: State: Zip:

    Telephone (Day): __________ (Evening):

    Fax: __________________ E-Mail:

    Application is for: New Small Generating Facility ______ Capacity addition ______

    If capacity addition to existing facility, please describe:

    The Small Generating Facility will supply: Interconnection Customer ___ others ____

    Point of Interconnection:

    Interconnection Customer's requested in-service date:

    Section 2. Processing Fee or Deposit

    If the Interconnection Request is submitted as Level 2, the nonrefundable processing fee payable to the utility is $500.

    If the Interconnection Request is submitted as Level 3, the Interconnection Customer shall submit to the Utility the deposit is $1,000, or 50% of the estimated cost of the Feasibility Study, whichever is less.

    Section 3. ] Small Generating Facility Information

    Data apply only to the small generating facility, not the interconnection facilities.

    Energy Source: ___ Solar ___ Wind ___ Hydro ___ Hydro Type [ (e.g. Run-of-River) ]:_________

    Diesel ___ Natural Gas ___ Fuel Oil ___ Other ([ state type describe ]) ______________________________

    Prime Mover: Fuel Cell__ Recip Engine__ Gas Turb__ Steam Turb__ Microturbine__ PV__ Other [ (describe) ]

    Type of Generator: [ ____ ] Synchronous ____Induction ____ Inverter [ ]

    Generator Nameplate Rating: ________kW [ (Typical) ] Generator Nameplate kVAR: ______

    Interconnection customer or customer-site load: _________________kW [ (if none, so state) ]

    Typical reactive load [ (if known) ]: _________________

    Maximum physical export capability requested: ______________ kW

    List components of the small generating facility equipment package that are currently certified:

    Equipment [ Type ]

    Certifying Entity

    1.________________

    1.___________________

    2.________________

    2.___________________

    3.________________

    3.___________________

    4.________________

    4.___________________

    5.________________

    5.___________________

    Is the prime mover compatible with the certified protective relay package? [ ____]Yes ____No [ ____ ]

    Generator (or solar collector)

    Manufacturer, model name & number:_____________________________________

    Version Number:_________________________________________

    Nameplate Output Power Rating in kW: (Summer) _________ (Winter) ______

    Nameplate Output Power Rating in kVA: (Summer) ________ (Winter) _______

    Individual Generator Power Factor

    Rated Power Factor: Leading: _____________Lagging: _______________

    Total number of generators in wind farm to be interconnected pursuant to this

    Interconnection Request: [ _______ ] Elevation: ____ ___Single phase ___Three phase [ ____________ ]

    Inverter manufacturer, model name & number [ (if used) ]:___________________

    List of adjustable set points for the protective equipment or software:_________

    Note: A completed power systems load flow data sheet must be supplied with the Interconnection Request.

    Small Generating Facility Characteristic Data (for inverter-based machines)

    Max design fault contribution current:________ Instantaneous_____ or RMS [ ? ] _________

    Harmonics characteristics: __________________________________________

    Start-up requirements: _____________________________________________

    Small Generating Facility Characteristic Data (for rotating machines)

    RPM Frequency: _______________________________________________

    [ (*) ] Neutral Grounding Resistor (If Applicable): ____________

    Synchronous Generators:

    Direct Axis Synchronous Reactance, Xd: _______ P.U.

    Direct Axis Transient Reactance, X'd: ___________ P.U.

    Direct Axis Subtransient Reactance, X"d: ______________P.U.

    Negative Sequence Reactance, X2: _________ P.U.

    Zero Sequence Reactance, X0: ____________ P.U.

    KVA Base: __________________________

    Field Volts: ______________

    Field Amperes: ______________

    Induction Generators:

    Motoring Power (kW): ______________

    [ I2 2t I2t ] or K (Heating Time Constant): ______________

    Rotor Resistance, Rr: ______________

    Stator Resistance, Rs: ______________

    Stator Reactance, Xs: ______________

    Rotor Reactance, Xr: ______________

    Magnetizing Reactance, Xm: ______________

    Short Circuit Reactance, Xd'': ______________

    Exciting Current: ______________

    Temperature Rise: ______________

    Frame Size: ______________

    Design Letter: ______________

    Reactive Power Required In Vars (No Load): ______________

    Reactive Power Required In Vars (Full Load): ______________

    Total Rotating Inertia, H: _____________ Per Unit on kVA [ Base base ]

    Excitation and Governor System Data for Synchronous Generators Only

    Provide appropriate IEEE model block diagram of excitation system, governor system and power system stabilizer (PSS) in accordance with the regional reliability council criteria. A PSS may be determined to be required by applicable studies. A copy of the manufacturer's block diagram may not be substituted.

    [ Section 4. Customer's ] Interconnection Facilities Information

    Will a transformer be used between the generator and the point of [ common coupling interconnection ] ? [ ___ ] Yes ____No [ ____ ]

    Will the transformer be provided by the interconnection customer? [ ____ ] Yes ____No [ ____ ]

    Transformer Data (If applicable, for interconnection customer-owned transformer):

    Is the transformer: [ ____ ] single phase _____three phase [ ? ___ ] Size: [ ___________ ] kVA [ _____ ]

    Transformer Impedance: _______% on __________kVA [ Base base]

    If Three Phase:

    Transformer Primary:_____ Volts _____ Delta _____Wye _____ Wye Grounded

    Transformer Secondary: _____Volts _____ Delta _____Wye _____ Wye Grounded

    Transformer Tertiary:_____ Volts _____ Delta _____Wye _____ Wye Grounded

    Transformer Fuse Data (If applicable, for interconnection customer-owned fuse):

    (Attach copy of fuse manufacturer's minimum melt and total clearing time-current curves)

    Manufacturer: ____________ Type: __________ Size: ______Speed: _______

    Interconnecting Circuit Breaker (if applicable):

    Manufacturer: ___________________ Type: __________

    Load Rating (Amps): ______ Interrupting Rating (Amps): _______ Trip Speed (Cycles): ______

    Interconnection Protective Relays (If Applicable):

    If microprocessor-controlled:

    Manufacturer: _________________________ Type: _____________________ Model No. ___________ Firmware ID: _____________ Instruction Book No. ______________

    List of functions and adjustable setpoints for the protective equipment or software:

    Setpoint Function

    Minimum

    Maximum

    1.________________

    ____________

    __________

    2.________________

    ____________

    __________

    3.________________

    ____________

    __________

    4.________________

    ____________

    __________

    5.________________

    ____________

    __________

    6.________________

    ____________

    __________

    If Discrete Components:

    (Enclose copy of any proposed time-overcurrent coordination curves)

    Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______

    Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______

    Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______

    Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______

    Manufacturer: ___________Type: _______ Style/Catalog No.: ______ Proposed Setting: ______

    Current Transformer Data (If applicable):

    (Enclose copy of manufacturer's excitation and ratio correction curves)

    Manufacturer:____________________________________

    Type: _______ Accuracy Class: ________Proposed Ratio Connection: ____

    Manufacturer:____________________________________

    Type: _______ Accuracy Class: ________Proposed Ratio Connection: ____

    Potential Transformer Data (If applicable):

    Manufacturer:____________________________________

    Type: __________ Accuracy Class: _______Proposed Ratio Connection: ____

    Manufacturer:____________________________________

    Type: ________ Accuracy Class: _________Proposed Ratio Connection: ____

    [ Section 5. ] General Information

    Enclose [ a ] copy of [ the ] site electrical one-line diagram showing the configuration of [ all the ] small generating facility equipment, current and potential circuits, and protection and control schemes.

    Enclose [ a ] copy of any site documentation that indicates the precise physical location of the proposed [ small generating facility SGF ] (e.g., United States Geological Survey [ (USGS) ] topographic map or other diagram or documentation).

    [ Proposed Describe the proposed ] location of [ the ] protective interface equipment on [ the ] property [ (include address if different from the interconnection customer's address) ] ________________________________________________

    Enclose [ a ] copy of any site documentation that describes and details the operation of the protection and control schemes. Is available documentation enclosed? [ ___ ] Yes ____No [ ____ ]

    Enclose copies of schematic drawings for all protection and control circuits, relay current circuits, relay potential circuits, and alarm/monitoring circuits (if applicable).

    Are schematic drawings enclosed? [ ___ ] Yes ____No [ ____ ]

    [ Applicant Section 6. Interconnection Customer ] Signature

    I hereby certify that, to the best of my knowledge, all the information provided in this Interconnection Request is true and correct.

    [ For Interconnection Customer Signature ] : _________________________ Date: ___________________________________

    [ Section 7. Utility Acknowledgement of Receipt

    Signed:

    Title:

    Utility:

    Date:

    Utility signature signifies only receipt of this form, in compliance with 20VAC5-314-50 of the State Corporation Commission's Regulations Governing Interconnection of Small Electrical Generators. ]

    [ Schedule 5

    LEVELS 2 AND 3 FACILITIES STUDY INFORMATION FORM FOR SMALL GENERATING FACILITIES LESS THAN 20 MW

    1. Provide a location plan and simplified one-line diagram of the plant and station facilities. For staged projects, indicate future generation, future transmission circuits, and other major future facilities. On the one-line diagram, show (i) each generator, its electric connection configuration, and its generation capacity, (ii) the location and capacity of auxiliary power, and (iii) minimum load on CT/PT.

    2. One set of metering is required for each generation connection to the new ring bus or existing utility station. Indicate the number of generation connections requiring a metering set: _____________________

    3. Indicate whether an alternate source of auxiliary power will be available during CT/PT maintenance. Yes ___________ No ________________

    4. Indicate whether a transfer bus on the generation side of the metering will require that each meter set be designed for the total plant generation. Indicate such on the one-line diagram. Yes ________ No _____

    5. State the type of control system or Programmable Logic Controller (PLC) that will be located at the small generating facility.

    __________________________________________________________________________________________________

    6. State the protocol used by the control system or PLC. _____________________________________________________________________

    7. Provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines.

    8. State the physical dimensions of the proposed interconnection station.

    ________________________________________________________________________________________________________________

    9. State the bus length from generation to interconnection station.

    ________________________________________________________________________________________________________________

    10. Provide a diagram or description of the point of interconnection desired by the IC that is to be the point of interconnection in the system impact study report.

    11. State the line length from interconnection station to utility system.

    ________________________________________________________________________________________________________________

    12. State the pole or tower number observed in the field affixed to the pole or tower leg. _____________________________________________

    13. State the number of third party easements required for distribution or transmission lines.

    ________________________________________________________________________________________________________________

    14. Provide the following proposed schedule dates:

    a. Date IC to begin construction: ______________________________________________

    b. Date generator step-up transformers to receive back feed power: ______________________

    c. Date IC will test SGF: ______________________________________________

    d. Date IC will place SGF into commercial operation: _________________________________ ]

    Schedule [ 5 6 ]

    [ LEVEL 3 ] SMALL GENERATOR INTERCONNECTION AGREEMENT (SGIA)
    [ (For Small Generating Facilities Subject to the Level 3 Process) ]

    This [ Small Generator ] Interconnection Agreement ("Agreement") is made and entered into this ______ day of ____________, 20__, by __________________

    [ ("Distribution Company Utility ]"), and _________________________________

    ("Interconnection Customer") each hereinafter sometimes referred to individually as "Party" or both referred to collectively as the "Parties."

    [ Distribution Company Utility ] Information

    [ Distribution Company Utility ]: _____________________________________________

    Attention: ________________________________________________

    Address: ________________________________________________________

    [ City: ________________________ State: ________________ Zip: _________

    City, State, Zip:___________________________________________ ]

    Phone: _____________ Fax: _______________________

    Interconnection Customer Information

    Interconnection Customer: __________________________________________

    Attention: ________________________________________________

    Address: ________________________________________________

    [ City: _________________________ State: _______________ Zip: _________

    City, State, Zip:___________________________________________ ]

    Phone: _______________________ Fax: _____________________________

    Interconnection Customer Application No: _____________

    In consideration of the mutual covenants set forth herein, the Parties agree as follows:

    Article 1. Scope and Limitations of Agreement

    1.1 This Agreement shall be used for all Interconnection Requests submitted under the [ Small Generator Interconnection Procedures (SGIP) Level 3 interconnections pursuant to the Commission's Regulations Governing Interconnection of Small Electrical Generators, Chapter 314 of the Virginia Administrative Code ].

    1.2 This Agreement governs the terms and conditions under which the Interconnection Customer's [ ("IC") ] Small Generating Facility [ ("SGF") ] will interconnect with, and operate in parallel with, the [ utility's distribution utility ] system.

    1.3 This Agreement does not constitute an agreement to purchase or deliver the Interconnection Customer's power. The purchase or delivery of power and other services [ , including station service or backup power, ] that the [ Interconnection Customer IC ] may require will be covered under separate agreements [ , possibly with other parties ]. The [ Interconnection Customer IC ] will be responsible for separately making all necessary arrangements (including scheduling) for delivery of electricity with the applicable [ Distribution Company utility and provider of transmission service ].

    1.4 Nothing in this Agreement is intended to affect any other agreement between the [ Distribution Company utility ] and the [ Interconnection Customer IC ].

    1.5 Responsibilities of the Parties

    1.5.1 The Parties shall perform all obligations of this Agreement in accordance with all applicable laws and regulations, operating requirements, and Good [ Distribution Company Utility ] Practice.

    1.5.2 The [ Interconnection Customer IC ] shall construct, interconnect, operate and maintain its [ Small Generating Facility SGF ] and construct, operate, and maintain its [ Customer's ] Interconnection Facilities in accordance with the applicable manufacturer's recommended maintenance schedule, in accordance with this Agreement, and with Good [ Distribution Company Utility ] Practice.

    1.5.3 The [ Distribution Company utility ] shall construct, operate, and maintain its distribution and transmission system and [ interconnection attachment ] facilities in accordance with this Agreement, and with Good [ Distribution Company Utility ] Practice.

    1.5.4 The [ Interconnection Customer IC ] agrees to construct its facilities [ or systems ] in accordance with applicable specifications that meet or exceed those provided by the National Electrical Safety Code, the American National Standards Institute, IEEE, Underwriter's Laboratory, and operating requirements in effect at the time of construction and other applicable national and state codes and standards. The [ Interconnection Customer IC ] agrees to design, install, maintain, and operate its [ small generating facility SGF ] so as to reasonably minimize the likelihood of a disturbance adversely affecting or impairing the system or equipment of the [ Distribution Company utility ] or affected systems [ and to otherwise maintain and operate its SGF in accordance with the specifications and certifications under which the SGF was initially installed and interconnected ].

    1.5.5 Each Party shall operate, maintain, repair, and inspect, and shall be fully responsible for the facilities that it now or subsequently may own unless otherwise specified in the Attachments to this Agreement. Each Party shall be responsible for the safe installation, maintenance, repair and condition of their respective lines and appurtenances on their respective sides of the point of change of ownership. The [ Distribution Company utility ] and the [ Interconnection Customer IC ], as appropriate, shall provide [ Interconnection Attachment ] Facilities [ and Customer's Interconnection Facilities ] that adequately protect the [ Distribution Company's Transmission System, utility's ] personnel, and other persons from damage and injury. The allocation of responsibility for the design, installation, operation, maintenance and ownership of [ Interconnection Attachment ] Facilities [ and Customer's Interconnection Facilities ] shall be delineated in the Attachments to this Agreement. [ The design, installation, operation, and maintenance of such facilities shall be the responsibility of the owner except as otherwise provided for in this Agreement. ]

    1.5.6 The [ Distribution Company utility ] shall coordinate with all affected systems to support the interconnection.

    1.6 Parallel operation obligations

    Once the [ small generating facility SGF ] has been authorized to commence parallel operation, the [ Interconnection Customer IC ] shall abide by all rules and procedures pertaining to the parallel operation of the [ small generating facility SGF ] including, but not limited to the rules and procedures concerning the operation of generation set forth in the tariff.

    1.7 Metering

    The [ Interconnection Customer IC ] shall be responsible for the [ Distribution Company's utility's ] reasonable and necessary cost for the purchase, installation, operation, maintenance, testing, repair, and replacement of metering and data acquisition equipment specified in Attachments 2 and 3 of this Agreement. The [ Interconnection Customer's IC's ] metering (and data acquisition, as required) equipment shall conform to applicable industry rules and operating requirements.

    1.8 Reactive power

    1.8.1 The [ Interconnection Customer IC ] shall design its [ small generating facility SGF ] to maintain a composite power delivery at continuous rated power output at the point of interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless the [ Distribution Company utility ] has established different requirements that apply to all similarly situated generators in the control area on a comparable basis. The requirements of this paragraph shall not apply to wind generators.

    1.8.2 The [ Distribution Company utility ] is required to pay the Interconnection Customer for reactive power that the [ Interconnection Customer IC ] provides or absorbs from the [ small generating facility SGF ] when the [ Distribution Company utility ] requests the [ Interconnection Customer IC ] to operate its [ small generating facility SGF ] outside the range specified in article 1.8.1. In addition, if the [ Distribution Company utility ] pays its own or affiliated generators for reactive power service within the specified range, it must [ also similarly ] pay the [ Interconnection Customer IC ].

    1.8.3 Payments shall be in accordance with the [ Interconnection Customer's IC's ] applicable rate schedule [ then as may be ] in effect [ and accepted by the appropriate government authority ]. To the extent that no rate schedule is in effect at the time the Interconnection Customer is required to provide or absorb reactive power under this Agreement, the [ Parties agree to IC may ] expeditiously file such rate schedule [ and agree with the appropriate government authority, and the utility agrees ] to support any request for waiver of [ the State Corporation Commission's any ] prior notice requirement [ of such authority ] in order to [ compensate permit compensation to ] the [ Interconnection Customer IC ] from the time service commenced.

    1.9 Capitalized terms used herein shall have the meanings specified in the [ Glossary of Terms definitions ] in Attachment 1 to Schedule [ 5 6 ] or [ in ] the body of this Agreement.

    Article 2. Inspection, Testing, Authorization, and Right of Access

    2.1 Equipment testing and inspection

    2.1.1 The Interconnection Customer shall test and inspect its small generating facility and interconnection facilities prior to interconnection. The [ Interconnection Customer IC ] shall notify the [ Distribution Company utility ] of such activities no fewer than five business days (or as may be agreed to by the Parties) prior to such testing and inspection. Testing and inspection shall occur on a business day. The [ Distribution Company utility ] may, at its own expense, send qualified personnel to the [ small generating facility SGF ] site to inspect the interconnection and observe the testing. The [ Interconnection Customer IC ] shall provide the [ Distribution Company utility ] a written test report when such testing and inspection is completed.

    2.1.2 The [ Distribution Company utility ] shall provide the [ Interconnection Customer IC ] written acknowledgment that it has received the [ Interconnection Customer's IC's ] written test report. Such written acknowledgment shall not be deemed to be or construed as any representation, assurance, guarantee, or warranty by the [ Distribution Company utility ] of the safety, durability, suitability, or reliability of the [ small generating facility SGF ] or any associated control, protective, and safety devices owned or controlled by the [ Interconnection Customer IC ] or the quality of power produced by the [ small generating facility SGF ].

    2.2 Authorization required prior to parallel operation

    2.2.1 The [ Distribution Company utility ] shall use reasonable efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the [ Distribution Company utility ] shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The [ Distribution Company utility ] shall make reasonable efforts to cooperate with the [ Interconnection Customer IC ] in meeting requirements necessary for the [ Interconnection Customer IC ] to commence parallel operations by the in-service date.

    2.2.2 The [ Interconnection Customer IC ] shall not operate its [ small generating facility SGF ] in parallel with the [ Distribution Company's utility's ] system without prior written authorization of the [ Distribution Company utility]. The [ Distribution Company utility ] will provide such authorization once the [ Distribution Company utility ] receives notification that the [ Interconnection Customer IC ] has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

    2.3 Right of access

    2.3.1 Upon reasonable notice, the [ Distribution Company utility ] may send a qualified person to the premises of the Interconnection Customer at or immediately before the time the [ small generating facility SGF ] first produces energy to inspect the interconnection, and observe the commissioning of the [ small generating facility SGF ] (including any required testing), startup, and operation for a period of up to three business days after initial start-up of the unit. In addition, the [ Interconnection Customer IC ] shall notify the [ Distribution Company utility ] at least five business days prior to conducting any on-site verification testing of the [ small generating facility SGF ].

    2.3.2 Following the initial inspection process described above, at reasonable hours, and upon reasonable notice, or at any time without notice in the event of an emergency or hazardous condition, the [ Distribution Company utility ] shall have access to the Interconnection Customer's premises for any reasonable purpose in connection with the performance of the obligations imposed on it by this Agreement or if necessary to meet its legal obligation to provide service to its customers.

    2.3.3 Each Party shall be responsible for its own costs associated with [ following ] this article.

    Article 3. Effective Date, Term, Termination, and Disconnection

    3.1 Effective date

    This Agreement shall become effective upon execution by the Parties [ subject to acceptance by the State Corporation Commission's Division of Energy Regulation (if applicable), or if filed unexecuted, upon the date specified by the State Corporation Commission's Division of Energy Regulation]. The [ Distribution Company utility ] shall promptly file this Agreement with the [ State Corporation ] Commission's Division of Energy Regulation upon execution [ , if required ].

    3.2 Term of Agreement

    This Agreement [ shall become effective on the effective date and ] shall remain in effect for a period of 10 years from the effective date or such other longer period as the Interconnection Customer may request and shall be automatically renewed for each successive one-year period thereafter, unless terminated earlier in accordance with article 3.3 of this Agreement.

    3.3 Termination

    No termination shall become effective until the Parties have complied with all applicable laws and regulations applicable to such termination, including the filing with the [ State Corporation ] Commission's Division of Energy Regulation of a notice of termination of this Agreement [ (if required), which notice has been accepted for filing by commission's Division of Energy Regulation ].

    3.3.1 The Interconnection Customer may terminate this Agreement at any time by giving the [ Distribution Company utility ] 20 business days written notice.

    3.3.2 Either Party may terminate this Agreement after default pursuant to article 7.6.

    3.3.3 Upon termination of this Agreement, the [ small generating facility Small Generating Facility ] will be disconnected from the [ Distribution Company's utility ] system. The termination of this Agreement shall not relieve either Party of its liabilities and obligations, owed or continuing at the time of the termination.

    [ 3.3.4 This provisions of this article shall survive termination or expiration of this Agreement. ]

    3.4 Temporary disconnection

    Temporary disconnection shall continue only for so long as reasonably necessary under Good [ Distribution Company Utility ] Practice.

    3.4.1 Emergency Conditions -- "Emergency Condition" shall mean a condition or situation: (i) that in the judgment of the Party making the claim is imminently likely to endanger life or property; or (ii) that, in the case of the [ Distribution Company utility ], is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to the [ distribution utility ] system, the [ Distribution Company's Interconnection Attachment ] Facilities or the electrical facilities of others to which the [ Distribution Company's distribution utility ] system is directly connected; or (iii) that, in the case of the Interconnection Customer, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to, the [ small generating facility Small Generating Facility ] or the [ Interconnection ] Customer's [ interconnection facilities Interconnection Facilities ]. Under emergency conditions, the [ Distribution Company utility ] may immediately suspend interconnection service and temporarily disconnect the [ small generating facility SGF ]. The [ Distribution Company utility ] shall notify the [ Interconnection Customer IC ] promptly when it becomes aware of an emergency condition that may reasonably be expected to affect the [ Interconnection Customer's IC's ] operation of the [ small generating facility SGF ]. The [ Interconnection Customer IC ] shall notify the [ Distribution Company utility ] promptly when it becomes aware of an emergency condition that may reasonably be expected to affect the [ Distribution Company's utility ] system or other affected systems. To the extent information is known, the notification shall describe the emergency condition, the extent of the damage or deficiency, the expected effect on the operation of both Parties' facilities and operations, its anticipated duration, and the necessary corrective action.

    3.4.2 Routine maintenance, construction, and repair

    The [ Distribution Company utility ] may interrupt interconnection service or curtail the output of the [ small generating facility SGF ] and temporarily disconnect the [ small generating facility SGF ] from the [ Distribution Company's distribution utility's ] system when necessary for routine maintenance, construction, and repairs on the [ Distribution Company's distribution utility ] system. The [ Distribution Company utility ] shall provide the [ Interconnection Customer IC ] with [ at least ] five business days notice prior to such interruption [ unless circumstances require shorter notice ]. The [ Distribution Company utility ] shall use reasonable efforts to coordinate such reduction or temporary disconnection with the [ Interconnection Customer IC ].

    3.4.3 Forced outages

    During any forced outage, the [ Distribution Company utility ] may suspend interconnection service to effect immediate repairs on the [ Distribution Company's distribution utility ] system. The [ Distribution Company utility ] shall use reasonable efforts to provide the [ Interconnection Customer IC ] with prior notice. If prior notice is not given, the [ Distribution Company utility ] shall, upon request, provide the [ Interconnection Customer IC ] written documentation after the fact explaining the circumstances of the disconnection.

    3.4.4 Adverse operating effects

    The [ Distribution Company utility ] shall notify the [ Interconnection Customer IC ] as soon as practicable if, based on Good [ Distribution Company Utility ] Practice, operation of the [ small generating facility SGF ] may cause disruption or deterioration of service to other customers served from the [ same electric utility ] system [ or affected systems], or if operating the [ small generating facility SGF ] could cause damage to the [ Distribution Company's distribution utility ] system or affected systems. Supporting documentation used to reach the decision to disconnect shall be provided to the [ Interconnection Customer IC ] upon request. If, after notice, the [ Interconnection Customer IC ] fails to remedy the adverse operating effect within a reasonable time, the [ Distribution Company utility ] may disconnect the [ small generating facility SGF ]. The [ Distribution Company utility ] shall provide the [ Interconnection Customer IC ] with a five business day notice of such disconnection, unless the provisions of article 3.4.1 apply.

    3.4.5 Modification of the [ small generating facility Small Generating Facility ]

    The Interconnection Customer must receive written authorization from the [ Distribution Company utility ] before making [ any change changes ] to the [ small generating facility SGF or mode of operations ] that may have a material impact on the safety or reliability of the [ Distribution Company's utility ] system [ or affected system ]. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good [ Distribution Company Utility ] Practice. If the [ Interconnection Customer IC ] makes such [ modification modifications ] without the [ Distribution Company's utility's ] prior written authorization, the latter shall have the right to temporarily disconnect the [ small generating facility SGF ].

    3.4.6 Reconnection

    The Parties shall cooperate with each other to restore the [ small generating facility SGF ], interconnection facilities, and the [ Distribution Company's distribution utility ] system to their normal operating state as soon as reasonably practicable following a temporary disconnection.

    Article 4. Cost Responsibility for [ Customer's ] Interconnection Facilities [ , Attachment Facilities, ] and Distribution Upgrades

    4.1 [ Customer's ] Interconnection [ facilities Facilities ]

    [ The IC shall be responsible for the costs associated with owning, operating, maintaining, repairing, and replacing the Customer's Interconnection Facilities. ]

    [ 4.1.1 4.2 Attachment Facilities ]

    The [ Interconnection Customer IC ] shall pay for [ the cost of one-time and ongoing costs of installing, owning, operating, maintaining and replacing ] the [ interconnection attachment ] facilities itemized in Attachment 2 of this Agreement. The [ Distribution Company utility ] shall provide [ a best estimate an estimated ] cost [ , including overheads, ] for the purchase and construction of [ its interconnection the attachment ] facilities and provide a detailed itemization of such costs. Costs associated with [ interconnection attachment ] facilities may be shared with other entities that may benefit from such facilities by agreement of the [ Interconnection Customer IC ], such other entities, and the [ Distribution Company utility ].

    [ 4.1.2 The Interconnection Customer shall be responsible for its share of all reasonable expenses, including overheads, associated with (i) owning, operating, maintaining, repairing, and replacing its own interconnection facilities, and (ii) operating, maintaining, repairing, and replacing the Distribution Company's interconnection facilities.

    4.2 4.3 ] Distribution upgrades

    The [ Distribution Company utility ] shall design, procure, construct, install, and own the distribution upgrades described in Attachment 6 of this Agreement. [ The actual cost of the distribution upgrades shall be directly assigned to the IC. ] If the [ Distribution Company utility ] and the [ Interconnection Customer IC ] agree, the [ Interconnection Customer IC ] may construct distribution upgrades that are located on land owned by the [ Interconnection Customer IC ]. [ The actual cost of the distribution upgrades, including overheads, shall be directly assigned to the Interconnection Customer. ]

    [ Article 5. Cost Responsibility for System Upgrades

    5.1 Applicability

    No portion of this article 5 shall apply unless the interconnection of the small generating facility requires system upgrades.

    5.2 System upgrades

    The Distribution Company shall design, procure, construct, install, and own the system upgrades described in Attachment 3 of this Agreement. If the Distribution Company and the Interconnection Customer agree, the Interconnection Customer may construct system upgrades that are located on land owned by the Interconnection Customer. Unless the Distribution Company elects to pay for system upgrades, the actual cost of the system upgrades, including overheads, shall be borne initially by the Interconnection Customer.

    5.2.1 Repayment of amounts advanced for system upgrades

    The Interconnection Customer shall be entitled to a cash repayment, equal to the total amount paid to the Distribution Company and affected system operator, if any, for system upgrades, including any tax gross-up or other tax-related payments associated with the system upgrades, and not otherwise refunded to the Interconnection Customer, to be paid to the Interconnection Customer on a dollar-for-dollar basis for the nonusage sensitive portion of transmission charges, as payments are made under the Distribution Company's tariff and affected system's tariff for distribution services with respect to the small generating facility. Upgrades through the date on which the Interconnection Customer receives a repayment of such payment pursuant to this subparagraph. The Interconnection Customer may assign such repayment rights to any person.

    5.2.1.1 Notwithstanding the foregoing, the Interconnection Customer, the Distribution Company, and affected system operator may adopt any alternative payment schedule that is mutually agreeable so long as the Distribution Company and affected system operator take one of the following actions no later than five years from the commercial operation date: (i) return to the Interconnection Customer any amounts advanced for system upgrades not previously repaid, or (ii) declare in writing that the Distribution Company or affected system operator will continue to provide payments to the Interconnection Customer on a dollar-for-dollar basis for the nonusage sensitive portion of transmission charges, or develop an alternative schedule that is mutually agreeable and provides for the return of all amounts advanced for system upgrades not previously repaid; however, full reimbursement shall not extend beyond 20 years from the commercial operation date.

    5.2.1.2 If the small generating facility fails to achieve commercial operation, but it or another generating facility is later constructed and requires use of the system upgrades, the Distribution Company and affected system operator shall at that time reimburse the Interconnection Customer for the amounts advanced for the system upgrades. Before any such reimbursement can occur, the Interconnection Customer, or the entity that ultimately constructs the generating facility, if different, is responsible for identifying the entity to which reimbursement must be made.

    5.3 Special provisions for affected systems

    Unless the Distribution Company provides, under this Agreement, for the repayment of amounts advanced to affected system operator for system upgrades, the Interconnection Customer and affected system operator shall enter into an agreement that provides for such repayment. The agreement shall specify the terms governing payments to be made by the Interconnection Customer to affected system operator as well as the repayment by affected system operator.

    Article 5. Transmission System

    5.1 Transmission system upgrades

    5.1.1 No portion of section 5.1 of this article 5 shall apply unless the interconnection of the Small Generating Facility requires transmission system upgrades.

    5.1.2 The utility shall design, procure, construct, install, and own the transmission system upgrades described in Attachment 6 of this Agreement. If the utility and the Interconnection Customer agree, the IC may construct transmission system upgrades that are located on land owned by the IC. The costs of the transmission system upgrades shall be borne by the IC.

    5.1.3 Notwithstanding any other provision of section 5.1 of article 5, in the event and to the extent an RTE has rules, tariffs, agreements, or procedures properly applying to transmission system upgrades, the provisions of section 5.2 of article 5 shall apply to such upgrades.

    5.2 Regional Transmission Entities

    Notwithstanding any other provision of this Agreement, if the utility's transmission system is under the control of an RTE and the RTE has rules, tariffs, agreements or procedures properly governing operation of the SGF, transmission of the output of the SGF, sale of the output of the SGF, system upgrades required for interconnection of the SGF, or other aspects of the interconnection and operation of the SGF, the IC and the utility shall comply with the applicable of such agreements, rules, tariffs, or procedures. ]

    [ 5.4 5.3 ] Rights under other agreements

    Notwithstanding any other provision of this Agreement, nothing herein shall be construed as relinquishing or foreclosing any rights, including but not limited to firm transmission rights, capacity rights, transmission congestion rights, or transmission credits, that the [ Interconnection Customer IC ] shall be entitled to, now or in the future, under any other agreement or tariff as a result of, or otherwise associated with system upgrades, including the right to obtain cash reimbursements or transmission credits for transmission service that is not associated with the [ small generating facility SGF ].

    Article 6. Billing, Payment, Milestones, and Financial Security

    6.1 Billing and payment procedures and final accounting

    6.1.1 The [ Distribution Company utility ] shall bill the [ Interconnection Customer IC ] for the design, engineering, construction, and procurement costs of [ interconnection attachment ] facilities and upgrades contemplated by this Agreement on a monthly basis, or as otherwise agreed by the Parties. The [ Interconnection Customer IC ] shall pay each bill within 30 calendar days of receipt, or as otherwise agreed to by the Parties.

    6.1.2 Within [ three months 120 calendar days ] of completing the construction and installation of the [ Distribution Company's interconnection attachment ] facilities and/or [ distribution ] upgrades described in the Attachments to this Agreement, the [ Distribution Company utility ] shall provide the [ Interconnection Customer IC ] with a final accounting report of any difference between (i) the [ Interconnection Customer's IC's ] cost responsibility for the actual cost of such facilities or upgrades, and (ii) the [ Interconnection Customer's IC's ] previous aggregate payments to the [ Distribution Company utility ] for such facilities or upgrades. If the [ Interconnection Customer's IC's ] cost responsibility exceeds its previous aggregate payments, the [ Distribution Company utility ] shall invoice the [ Interconnection Customer IC ] for the amount due and the [ Interconnection Customer IC ] shall make payment to the [ Distribution Company utility ] within 30 calendar days. If the [ Interconnection Customer's IC's ] previous aggregate payments exceed its cost responsibility under this Agreement, the [ Distribution Company utility ] shall refund to the [ Interconnection Customer IC ] an amount equal to the difference within 30 calendar days of the final accounting report.

    6.2 Milestones

    The Parties shall agree on milestones for which each Party is responsible and [ list them such milestone shall be listed ] in Attachment 4 of this Agreement. A Party's [ milestones ] obligations under this provision may be [ extended modified ] by agreement. If a Party anticipates that it will be unable to meet a milestone for any reason other than a Force Majeure [ Event event], it shall immediately [ (i) ] notify the other Party of the reason(s) for not meeting the milestone [ , ] and [ (i) (ii) ] propose the earliest reasonable alternate date by which it can attain this and future milestones, and [ (ii) requesting (iii) request ] appropriate amendments to Attachment 4. The Party affected by the failure to meet a milestone shall not [ unreasonably ] withhold agreement to such an amendment unless it will suffer [ significant ] uncompensated economic or operational harm from the delay, attainment of the same milestone has previously been delayed, or it has reason to believe that the delay in meeting the milestone is intentional or unwarranted notwithstanding the circumstances explained by the Party proposing the amendment.

    6.3 Financial security arrangements

    At least 20 business days prior to the commencement of the design, procurement, installation, or construction of a discrete portion of the [ Distribution Company's interconnection attachment ] facilities and [ distribution ] upgrades, the Interconnection Customer shall provide the [ Distribution Company utility ], at the [ Interconnection Customer's IC's ] option, a guarantee, a surety bond, letter of credit or other form of security that is reasonably acceptable to the [ Distribution Company utility ] and is consistent with the Uniform Commercial Code of the jurisdiction where the point of interconnection is located. Such security for payment shall be in an amount sufficient to cover the costs for [ constructing, ] designing, procuring, [ and ] installing [ , and constructing ] the applicable portion of the [ Distribution Company's interconnection attachment ] facilities and [ distribution ] upgrades and shall be reduced on a dollar-for-dollar basis for payments made to the [ Distribution Company utility ] under this Agreement during its term. In addition:

    6.3.1 The guarantee must be made by an entity that meets the creditworthiness requirements of the [ Distribution Company utility ], and contain terms and conditions that guarantee payment of any amount that may be due from the [ Interconnection Customer IC ], up to an agreed-to maximum amount.

    6.3.2 The letter of credit or surety bond must be issued by a financial institution or insured reasonably acceptable to the [ Distribution Company utility ] and must specify a reasonable expiration date.

    Article 7. Assignment, Liability, Indemnity, Force Majeure, Consequential Damages, and Default

    7.1 Assignment

    This Agreement may be assigned by either Party upon 15 business days prior written notice and opportunity to object by the other Party; provided that:

    7.1.1 Either Party may assign this Agreement without the consent of the other Party to any affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this Agreement;

    7.1.2 The Interconnection Customer shall have the right to assign this Agreement, without the consent of the [ Distribution Company utility ], for collateral security purposes to aid in providing financing for the [ small generating facility SGF ], provided that the [ Interconnection Customer IC ] will promptly notify the [ Distribution Company utility ] of any such assignment.

    7.1.3 Any attempted assignment that violates this article is void and ineffective.

    Assignment shall not relieve a Party of its obligations, nor shall a Party's obligations be enlarged, in whole or in part, by reason thereof. An assignee is responsible for meeting the same financial, credit, and insurance obligations as the [ Interconnection Customer IC ]. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed.

    7.2 Limitation of liability

    Each Party's liability to the other Party for any loss, cost, claim, injury, liability, or expense, including reasonable attorney's fees, relating to or arising from any act or omission in its performance of this Agreement, shall be limited to the amount of direct damage actually incurred. In no event shall either Party be liable to the other Party for any indirect, special, consequential, or punitive damages, except as authorized by this Agreement.

    7.3 Indemnity

    7.3.1 This provision protects each Party from liability incurred to third parties as a result of carrying out the provisions of this Agreement. Liability under this provision is exempt from the general limitations on liability found in article 7.2.

    7.3.2 The Parties shall at all times indemnify, defend, and hold the other Party harmless from, any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other Party's action or failure to meet its obligations under this Agreement on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnified Party.

    7.3.3 If an indemnified [ person Party ] is entitled to indemnification under this article as a result of a claim by a third party, and the indemnifying Party fails, after notice and reasonable opportunity to proceed under this article, to assume the defense of such claim, such indemnified person may at the expense of the indemnifying Party contest, settle or consent to the entry of any judgment with respect to, or pay in full, such claim.

    7.3.4 If an indemnifying [ party Party ] is obligated to indemnify and hold any indemnified person harmless under this article, the amount owing to the indemnified person shall be the amount of such indemnified person's actual loss, net of any insurance or other recovery.

    7.3.5 Promptly after receipt by an indemnified person of any claim or notice of the commencement of any action or administrative or legal proceeding or small generator investigation as to which the indemnity provided for in this article may apply, the indemnified person shall notify the indemnifying [ party Party ] of such fact. Any failure of or delay in such notification shall not affect a Party's indemnification obligation unless such failure or delay is materially prejudicial to the indemnifying party.

    7.4 Consequential damages

    Other than as expressly provided for in this Agreement, neither Party shall be liable under any provision of this Agreement for any losses, damages, costs or expenses for any special, indirect, incidental, consequential, or punitive damages, including but not limited to loss of profit or revenue, loss of the use of equipment, cost of capital, cost of temporary equipment or services, whether based in whole or in part in contract, in tort, including negligence, strict liability, or any other theory of liability; provided that damages for which a Party may be liable to the other Party under another agreement will not be considered to be special, indirect, incidental, or consequential damages hereunder.

    7.5 Force Majeure

    7.5.1 As used in this article, a Force Majeure [ Event event ] means "any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, any order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities, or any other cause beyond a Party's control. A Force Majeure [ Event event ] does not include an act of negligence or intentional wrongdoing."

    7.5.2 If a Force Majeure [ Event event ] prevents a Party from fulfilling any obligations under this Agreement, the Party affected by the Force Majeure [ Event event ] ([ " ] Affected Party [ " ]) shall promptly notify the other Party, either in writing or via the telephone, of the existence of the Force Majeure [ Event event ]. The notification must specify in reasonable detail the circumstances of the Force Majeure [ Event event ], its expected duration, and the steps that the Affected Party is taking to mitigate the effects of the event on its performance. The Affected Party shall keep the other Party informed on a continuing basis of developments relating to the Force Majeure [ Event event ] until the event ends. The Affected Party will be entitled to suspend or modify its performance of obligations under this Agreement (other than the obligation to make payments) only to the extent that the effect of the Force Majeure [ Event event ] cannot be mitigated by the use of reasonable efforts. The Affected Party will use reasonable efforts to resume its performance as soon as possible.

    7.6 Default

    7.6.1 No default shall exist where such failure to discharge an obligation (other than the payment of money) is the result of a Force Majeure [ Event event ] as defined in this Small Generator Interconnection Agreement or the result of an act or omission of the other Party. Upon a default, the [ nondefaulting Nondefaulting ] Party shall give written notice of such default to the [ defaulting Defaulting ] Party. Except as provided in article 7.6.2, the [ defaulting Defaulting ] Party shall have 60 calendar days from receipt of the default notice within which to cure the default; however, if the default is not capable of cure within 60 calendar days, the [ defaulting Defaulting ] Party shall commence the cure within 20 calendar days after notice and continuously and diligently complete the cure within six months from receipt of the default notice; and, if cured within such time, the default specified in such notice shall cease to exist.

    7.6.2 If a default is not cured as provided in this article, or if a default is not capable of being cured within the period provided for herein, the [ nondefaulting Nondefaulting ] Party shall have the right to terminate this Agreement by written notice at any time until cure occurs, and be relieved of any further obligation hereunder and, whether or not that Party terminates this Agreement, to recover from the [ defaulting Defaulting ] Party all amounts due hereunder, plus all other damages and remedies to which it is entitled at law or in equity. The provisions of this article will survive termination of this Agreement.

    Article 8. Insurance

    8.1 The Interconnection Customer shall, at its own expense, maintain in force general liability insurance without any exclusion for liabilities related to the interconnection undertaken pursuant to this Agreement. The amount of such insurance shall be [ sufficient to insure against all reasonably foreseeable direct liabilities given the size and nature of the generating equipment being interconnected, the interconnection itself, and the characteristics of the system to which the interconnection is made in accordance with 20VAC5-314-160 of the Commission's Regulations Governing the Interconnection of Small Electrical Generators ]. The [ Interconnection Customer IC ] shall obtain additional insurance only if necessary as a function of owning and operating a generating facility. Insurance shall be obtained from an insurance provider authorized to do business in the State [ where the interconnection is located of Virginia ]. Certification that such insurance is in effect shall be provided upon request of the [ Distribution Company utility ], except that the [ Interconnection Customer IC ] shall show proof of insurance to the [ Distribution Company utility ] no later than 10 business days prior to the anticipated commercial operation date [ of the SGF ]. An [ Interconnection Customer IC ] of sufficient creditworthiness may propose to self-insure for such liabilities, and such a proposal shall not be unreasonably rejected.

    8.2 The [ Distribution Company utility ] agrees to maintain general liability insurance or self insurance consistent with the [ Distribution Company's utility's ] commercial practice. Such insurance or self-insurance shall not exclude coverage for the [ Distribution Company's utility's ] liabilities undertaken pursuant to this Agreement.

    8.3 The Parties further agree to notify each other whenever an accident or incident occurs resulting in any injuries or damages that are included within the scope of coverage of such insurance, whether or not such coverage is sought.

    Article 9. Confidentiality

    9.1 Confidential information shall mean any confidential and/or proprietary information provided by one Party to the other Party that is clearly marked or otherwise designated "Confidential." For purposes of this Agreement all design, operating specifications, and metering data provided by the Interconnection Customer shall be deemed confidential information regardless of whether it is clearly marked or otherwise designated as such.

    9.2 Confidential information does not include information previously in the public domain, required to be publicly submitted or divulged by governmental authorities (after notice to the other Party and after exhausting any opportunity to oppose such publication or release), or necessary to be divulged in an action to enforce this Agreement. Each Party receiving confidential information shall hold such information in confidence and shall not disclose it to any third party nor to the public without the prior written authorization from the Party providing that information, except to fulfill obligations under this Agreement, or to fulfill legal or regulatory requirements.

    9.2.1 Each Party shall employ at least the same standard of care to protect confidential information obtained from the other Party as it employs to protect its own confidential information.

    9.2.2 Each Party is entitled to equitable relief, by injunction or otherwise, to enforce its rights under this provision to prevent the release of confidential information without bond or proof of damages, and may seek other remedies available at law or in equity for breach of this provision.

    [ 9.3 Notwithstanding anything in this Agreement to the contrary, if the Virginia State Corporation Commission ("Commission"), during the course of an investigation or otherwise, requests information from one of the Parties that is otherwise required to be maintained in confidence, the Party shall provide the requested information to the Commission, within the time provided for in the request for information. In providing the information to the Commission, the Party may request that the information be treated as confidential and nonpublic by the Commission and that the information be withheld from public disclosure. Parties are prohibited from notifying the other Party prior to the release of the confidential information to the Commission. ]

    Article 10. Disputes

    10.1 The Parties agree to attempt to resolve all disputes arising out of the interconnection process according to the provisions of this article.

    10.2 In the event of a dispute, either Party shall provide the other Party with a written Notice of Dispute. Such Notice shall describe in detail the nature of the dispute. [ The Parties shall make a good faith effort to resolve the dispute informally within 10 business days. ]

    10.3 If the dispute has not been resolved within [ two 10 ] business days after receipt of the Notice, either Party may [ contact seek resolution assistance from ] the [ Commission's ] Division of Energy Regulation [ for assistance in resolving the dispute where the matter will be handled as an informal complaint. If that process is unsatisfactory, either Party may petition the Commission to handle the dispute as a formal complaint ].

    [ Alternatively, either Party may seek resolution through the assistance of a dispute resolution service. The dispute resolution service will assist the Parties in either resolving the dispute or in selecting an appropriate dispute resolution venue (e.g., mediation, settlement judge, early neutral evaluation, or technical expert) to assist the Parties in resolving their dispute. Each Party agrees to conduct all negotiations in good faith and will be responsible for ½ of any costs paid to neutral third parties. ]

    10.4 [ Each Party agrees to conduct all negotiations in good faith and will be responsible for one-half of any costs paid to neutral third-parties If attempted dispute resolutions fail to satisfy one or both of the Parties, then either Party may exercise whatever rights and remedies it may have in equity or law consistent with the terms of this Agreement ].

    [ 10.5 If neither Party elects to seek assistance from the State Corporation Commission's Division of Energy Regulation, or if the attempted dispute resolution fails, then either Party may exercise whatever rights and remedies it may have in equity or law consistent with the terms of this Agreement. ]

    Article 11. Taxes

    11.1 The Parties agree to follow all applicable tax laws and regulations

    11.2 Each Party shall cooperate with the other to maintain the other Party's tax status. Nothing in this Agreement is intended to adversely affect the [ Distribution Company's utility's ] tax exempt status with respect to the issuance of bonds including, but not limited to, local furnishing bonds.

    Article 12. Miscellaneous

    12.1 Governing [ Law, Regulatory Authority, and Rules law, regulatory authority, and rules ]

    The validity, interpretation and enforcement of this Agreement and each of its provisions shall be governed by the laws of the [ state State of ] Virginia without regard to its conflicts of law principles. This Agreement is subject to all applicable laws and regulations. Each Party expressly reserves the right to seek changes in, appeal, or otherwise contest any laws, orders, or regulations of a governmental authority.

    12.2 Amendment

    The Parties may amend this Agreement by a written instrument duly executed by both Parties.

    12.3 No [ Third-Party Beneficiaries third-party beneficiaries ]

    This Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and where permitted, their assigns.

    12.4 Waiver

    12.4.1 The failure of a Party to this Agreement to insist, on any occasion, upon strict performance of any provision of this Agreement will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party.

    12.4.2 Any waiver at any time by either Party of its rights with respect to this Agreement shall not be deemed [ to be ] a continuing waiver or a waiver with respect to any other failure to comply with any other obligation, right, [ or ] duty of this Agreement. Termination or default of this Agreement for any reason by [ the ] Interconnection Customer shall not constitute a waiver of the [ Interconnection Customer's IC's ] legal rights to obtain an interconnection from the [ Distribution Company utility ]. Any waiver of this Agreement shall, if requested, be provided in writing.

    12.5 Entire Agreement

    This Agreement, including all Attachments, constitutes the entire agreement between the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between the Parties with respect to the subject matter of this Agreement. There are no other agreements, representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, either Party's compliance with its obligations under this Agreement.

    12.6 Multiple [ Counterparts counterparts ]

    This Agreement may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument.

    12.7 No [ Partnership partnership ]

    This Agreement shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership between the Parties or to impose any partnership obligation or partnership liability upon either Party. Neither Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, the other Party.

    12.8 Severability

    If any provision or portion of this Agreement shall for any reason be held or adjudged to be invalid or illegal or unenforceable by any court of competent jurisdiction or other governmental authority, (i) such portion or provision shall be deemed separate and independent, (ii) the Parties shall negotiate in good faith to restore insofar as practicable the benefits to each Party that were affected by such ruling, and (iii) the remainder of this Agreement shall remain in full force and effect.

    12.9 Environmental [ Releases releases ]

    Each Party shall notify the other Party, first orally and then in writing, of the release of any hazardous substances, any asbestos or lead abatement activities, or any type of remediation activities related to the [ small generating facility or Small Generating Facility, ] the [ customer's ] interconnection facilities, [ or attachment facilities, ] each of which may reasonably be expected to affect the other Party. The notifying Party shall (i) provide the notice as soon as practicable, provided such Party makes a good faith effort to provide the notice no later than 24 hours after such Party becomes aware of the occurrence, and (ii) promptly furnish to the other Party copies of any publicly available reports filed with any governmental authorities addressing such events.

    12.10 Subcontractors

    Nothing in this Agreement shall prevent a Party from utilizing the services of any subcontractor as it deems appropriate to perform its obligations under this Agreement; however, each Party shall require its subcontractors to comply with all applicable terms and conditions of this Agreement in providing such services and each Party shall remain primarily liable to the other Party for the performance of such subcontractor.

    12.10.1 The creation of any subcontract relationship shall not relieve the hiring Party of any of its obligations under this Agreement. The hiring Party shall be fully responsible to the other Party for the acts or omissions of any subcontractor the hiring Party hires as if no subcontract had been made; however, in no event shall the [ Distribution Company utility ] be liable for the actions or inactions of the [ Interconnection Customer IC ] or its subcontractors with respect to obligations of the [ Interconnection Customer IC ] under this Agreement. Any applicable obligation imposed by this Agreement upon the hiring Party shall be equally binding upon, and shall be construed as having application to, any subcontractor of such Party.

    12.10.2 The obligations under this article will not be limited in any way by any limitation of subcontractor's insurance.

    12.11 Reservation of [ Rights rights ]

    The [ Distribution Company utility ] shall have the right to make a unilateral filing with the Commission to modify this Agreement with respect to any rates, terms and conditions, charges, classifications of service, rule or regulation.

    Article 13. Notices

    13.1 General

    Unless otherwise provided in this Agreement, any written notice, demand, or request required or authorized in connection with this Agreement ("Notice") shall be deemed properly given if delivered in person, delivered by recognized national [ currier courier ] service, or sent by first class mail, postage prepaid, to the person specified below:

    If to the Interconnection Customer:

    Interconnection Customer: ___________________________________________

    Attention: ________________________________________________

    Address: ________________________________________________

    [ City: ______________________________ State:_______________ Zip:_______

    City, State, Zip: ]

    Phone: __________________ Fax: _________________

    If to the [ Distribution Company Utility ]:

    [ Distribution Company Utility ]: _______________________________________________

    Attention: ________________________________________________

    Address:_________________________________________

    [ City: ______________________________ State:_______________ Zip:_______

    City, State, Zip: ]

    Phone: _________________ Fax: ____________________

    13.2 Billing and [ Payment payment ]

    Billings and payments shall be sent to the addresses set out below:

    If to the Interconnection Customer:

    Interconnection Customer: ___________________________________________

    Attention: ________________________________________________

    Address: ________________________________________________

    [ City: ______________________________ State:_______________ Zip:_______

    City, State, Zip: ]

    If to the [ Distribution Company Utility ]:

    [ Distribution Company Utility ]: _______________________________________________

    Attention: ________________________________________________

    Address:_________________________________________

    [ City: ______________________________ State:_______________ Zip:_______

    City, State, Zip: ]

    13.3 Alternative [ Forms forms ] of [ Notice notice ]

    Any notice or request required or permitted to be given by either Party to the other and not required by this Agreement to be given in writing may be so given by telephone, facsimile or e-mail to the telephone numbers and email addresses set out below:

    If to the Interconnection Customer:

    Interconnection Customer: ___________________________________________

    Attention: ________________________________________________

    Address: ________________________________________________

    [ City: ______________________________ State:_______________ Zip:_______

    City, State, Zip: ]

    Phone: ___________________ Fax: __________________

    If to the [ Distribution Company Utility ]:

    [ Distribution Company Utility]: _______________________________________________

    Attention: ________________________________________________

    Address:_________________________________________

    [ City: ______________________________ State:_______________ Zip:_______

    City, State, Zip: ]

    Phone: __________________ Fax: ___________________

    13.4 Designated [ Operating Representative operating representative]

    The Parties may also designate operating representatives to conduct the communications which may be necessary or convenient for the administration of this Agreement. This person will also serve as the point of contact with respect to operations and maintenance of the Party's facilities.

    Interconnection Customer's Operating Representative:

    Interconnection Customer: ___________________________________________

    Attention: ________________________________________________

    Address: ________________________________________________

    [ City: ______________________________ State:_______________ Zip:_______

    City, State, Zip: ]

    Phone: __________________ Fax: ___________________

    [ Distribution Company's Utility's ] Operating Representative:

    [ Distribution Company Utility ]: _______________________________________________

    Attention: ________________________________________________

    Address:________________________________________

    [ City: ______________________________ State:_______________ Zip:_______

    City, State, Zip: ]

    Phone: __________________ Fax: ___________________

    13.5 Changes to the [ Notice Information notice information ]

    Either Party may change this information by giving five business days written notice prior to the effective date of the change.

    Article 14. Signatures

    IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by their respective duly authorized representatives.

    For the [ Distribution Company Utility ]

    Name: ________________________________________________

    Title: ________________________________________________

    Date: ________________________________________________

    For the Interconnection Customer

    Name: ________________________________________________

    Title: ________________________________________________

    Date: ________________________________________________

    Attachment 1 to

    Schedule [ 5 6 ]

    Glossary of Terms

    [ " ] Affected system [ – An " means an ] electric [ utility ] system other than [ that of ] the [ Distribution Company's transmission system utility ] that may be affected by the proposed interconnection.

    [ "Affected system operator" means an entity that operates an affected system or, if the affected system is under the operational control of an independent system operator or a Regional Transmission Entity, such independent entity. ]

    [ " ] Applicable laws and regulations [ – All " means all ] duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any governmental authority.

    [ "Attachment facilities" means the facilities and equipment owned, operated, and maintained by the utility that are built new in order to physically connect the customer’s interconnection facilities to the utility system. Attachment facilities shall not include distribution upgrades or previously existing distribution and transmission facilities. ]

    [ " ] Business Day [ " means ] Monday through Friday, excluding federal holidays.

    [ "Certified" has the meaning ascribed to it in Schedule 2 of Chapter 314 ( 20VAC5-314-10 et seq.) of the Virginia Administrative Code.

    "Customer’s interconnection facilities" means all the facilities and equipment owned, operated and maintained by the Interconnection Customer, between the Small Generating Facility and the point of interconnection necessary to physically and electrically interconnect the Small Generating Facility to the utility system.

    "Commission" means the Virginia State Corporation Commission. ]

    [ " ] Default [ – The " means the ] failure of a breaching Party to cure its breach under the Small Generator Interconnection Agreement.

    [ Distribution Company – The Utility that owns and/or operates the Distribution System located in Virginia to which the small generation facility proposes to interconnect its small generating facility. ]

    [ " ] Distribution system [ – The Distribution Company's " means the utility's ] facilities and equipment [ used to transmit generally delivering ] electricity to ultimate [ usage points such as homes and industries directly from nearby generators or from interchanges with higher voltage transmission systems which transport bulk power over longer distances. The voltage levels at which distribution systems operate differ among areas customers from substations supplied by higher voltages (usually at transmission level). For purposes of this Agreement, all portions of the utility's transmission system regulated by the Commission for which interconnections are not within Federal Energy Regulatory Commission jurisdiction are considered also to be subject to Commission regulations. ]

    [ " ] Distribution upgrades [ – The " means the ] additions, modifications, and upgrades to the [ Distribution Company's utility's ] distribution system at or beyond the point of interconnection [ necessary ] to [ facilitate abate problems on the utility's distribution system caused by the ] interconnection of the [ small generating facility and render the transmission service necessary to effect the Interconnection Customer's wholesale sale of electricity in interstate commerce Small Generating Facility ]. Distribution upgrades do not include [ customer's ] interconnection facilities [ or attachment facilities ].

    [ "Energy service provider" means any entity supplying electric energy service to the Interconnection Customer.

    "Facilities study" has the meaning ascribed to it in the commission’s regulations governing the interconnection of small generating facilities at 20VAC5-314-70 F.

    "Feasibility study" has the meaning ascribed to it in the commission’s regulations governing the interconnection of small generating facilities at 20VAC5-314-70 D.

    "FERC" means the Federal Energy Regulatory Commission.]

    [ " ] Good [ Distribution Company Utility ] Practice [ – Any " means any ] of the practices, methods and acts engaged in or approved by a significant portion of the electric industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good [ Distribution Company Utility ] Practice is not intended to be limited to the optimum practice, method, or act to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region.

    [ " ] Governmental authority [ – Any " means any ] federal, state, local or other governmental regulatory or administrative agency, court, commission, department, board, or other governmental subdivision, legislature, rulemaking board, tribunal, or other governmental authority having jurisdiction over the Parties, their respective facilities, or the respective services they provide, and exercising or entitled to exercise any administrative, executive, police, or taxing authority or power; provided that such term does not include the Interconnection Customer, the [ interconnection provider, or any Affiliate thereof utility, or a utility affiliate ].

    [ " ] Interconnection Customer [ – Any " or "IC" means any ] entity [ , including the Distribution Company, the transmission owner or any of the affiliates or subsidiaries of either, that proposes to interconnect its small generating facility with the Distribution Company's transmission proposing to interconnect a new Small Generating Facility with the utility ] system.

    [ Interconnection facilities – The Distribution Company's interconnection facilities and the Interconnection Customer's interconnection facilities. Collectively, interconnection facilities include all facilities and equipment between the small generating facility and the point of interconnection, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the small generating facility to the Distribution Company's transmission system. Interconnection facilities are sole use facilities and shall not include distribution upgrades or system upgrades.

    " ] Interconnection request [ – The Interconnection Customer's " means the IC's ] request, in accordance with the tariff, to interconnect a new [ small generating facility Small General Facility ], or to increase the capacity of, or make a material modification to the operating characteristics of, an existing [ small generating facility Small Generating Facility ] that is interconnected with the [ Distribution Company's utility ] system.

    [ "Interconnection studies" means the studies conducted by the utility, or a third party agreed to by the utility and the Interconnection Customer, in order to determine the interaction of the Small Generating Facility with the utility system and the affected systems in order to specify any modifications to the Small Generating Facility or the electric systems studied to ensure safe and reliable operation of the Small Generating Facility in parallel with the utility system.

    " ] Material modification [ – A " means a ] modification that has a material impact on the cost or timing of any Interconnection Request with a later queue priority date.

    [ System upgrades – Additions, modifications, and upgrades to the Distribution Company's distribution and transmission system required at or beyond the point at which the small generating facility interconnects with the system to accommodate the interconnection of the small generating facility with the Distribution Company's transmission system.

    " ] Operating requirements [ – Any " means any ] operating and technical requirements that may be applicable due to [ Regional Transmission Organization, Independent System Operator regional transmission entity, independent system operator], control area, or the [ Distribution Company's utility's ] requirements, including those set forth in the Small Generator Interconnection Agreement.

    [ " ] Party [ " ] or [ " ] Parties [ " ] [ – The Distribution Company means the utility ], [ the ] Interconnection Customer or [ any combination of the above both ].

    [ " ] Point of interconnection [ – The " means the ] point where the [ customer's ] interconnection facilities connect [ with to ] the [ Distribution Company's transmission utility ] system.

    [ Reasonable efforts – With respect to an action required to be attempted or taken by a Party under the Small Generator Interconnection Agreement, efforts that are timely and consistent with Good Distribution Company Practice and are otherwise substantially equivalent to those a Party would use to protect its own interests.

    "Regional Transmission Entity" or "RTE" shall refer to an entity having the management and control of a utility’s transmission system as further set forth in § 56-579 of the Code of Virginia.

    " ] Small Generating Facility [ – The " or "generator" or "SGF" means the ] Interconnection Customer's [ device equipment ] for the production of electricity identified in the Interconnection Request [ , but shall not include the Interconnection Customer's interconnection facilities ].

    [ "Small Generator Interconnection Agreement" or "SGIA" means the agreement between the utility and the Interconnection Customer as set forth in Schedule 6 of 20VAC5-314-170 of the Commission’s regulations governing interconnection of small electrical generators.

    "Supplemental review" has the meaning ascribed to it in the Commission’s regulations governing the interconnection of small generating facilities at 20VAC5-314-70 E.

    "System" or "utility system" means the distribution and transmission facilities owned, controlled, or operated by the utility that are used to deliver electricity.

    "System impact study" has the meaning ascribed to it in the Commission’s regulations governing the interconnection of small generating facilities at 20VAC5-314-70 E. ]

    [ " ] Tariff [ – The " means the ] rates, terms and conditions filed by the utility with the [ State Corporation ] Commission for the purpose of providing [ commission-regulated Commission-regulated ] electric service to retail customers.

    [ Upgrades – The required additions and modifications to the Distribution Company's distribution or transmission system at or beyond the point of interconnection. Upgrades do not include interconnection facilities.

    "Transmission system" means the utility’s facilities and equipment delivering electric energy to the distribution system, such facilities usually being operated at voltages above the utility’s typical distribution system voltages.

    "Utility" means the public utility company subject to regulation by the Commission pursuant to Chapter 10 (§ 56-232 et seq.) of Title 56 of the Code of Virginia with regard to rates and/or service quality to which the Interconnection Customer proposes to interconnect a Small Generating Facility. ]

    Attachment 2 to

    Schedule [ 5 6 ]

    Description and Costs of the Small Generating Facility, [ Customer's ] Interconnection Facilities, [ Attachment Facilities ] and Metering Equipment

    [ Equipment, including the small generating facility, interconnection facilities, and metering equipment shall be itemized and identified as being The following shall be provided in this exhibit:

    1. An itemization of the major equipment components ] owned by the Interconnection Customer [ or and ] the [ Distribution Company. The Distribution Company will provide a best estimate itemized cost, including overheads, of its interconnection facilities and metering equipment, and a best estimate itemized cost of the annual operation and maintenance expenses associated with its interconnection facilities and metering equipment utility, including components of the Small Generating Facility, the customer’s interconnection facilities, attachment facilities, and metering equipment. Such itemization shall identify the owner of each item listed.

    2. The utility’s estimated itemized cost of its attachment facilities and its metering equipment.

    3. The utility’s estimated cost of its annual operation and maintenance expenses associated with attachment facilities and metering equipment to be charged to the Interconnection Customer ].

    Attachment 3 to

    Schedule [ 5 6 ]

    [ [ Diagram to be provided by applicant ] ]

    One-line Diagram Depicting the Small Generating Facility, [ Customer's ] Interconnection Facilities, [ Attachment Facilities, ] Metering Equipment, and [ Distribution ] Upgrades

    [ (Diagram and description to be provided by Interconnection Customer) ]

    Attachment 4 to

    Schedule [ 5 6 ]

    Milestones

    In-Service Date: ___________________

    Critical milestones and responsibility as agreed to by the Parties:

    Milestone/Date

    Responsible Party

    (1)____________________

    ____________________

    (2)____________________

    ____________________

    (3)____________________

    ____________________

    (4)____________________

    ____________________

    (5)____________________

    ____________________

    (6)____________________

    ____________________

    (7)____________________

    ____________________

    (8)____________________

    ____________________

    (9)____________________

    ____________________

    (10)___________________

    ____________________

    Agreed to by:

    For the [ Distribution Company Utility ] ____________________ Date__________

    For the Transmission Owner (If Applicable)_____________ Date__________

    For the Interconnection Customer_____________________ Date___________

    Attachment 5 to

    Schedule [ 5 6 ]

    Additional Operating Requirements for the [ Distribution Company's Utility ] System and Affected Systems Needed to Support the Interconnection Customer's Needs

    The [ Distribution Company utility ] shall [ also ] provide requirements that must be met by the Interconnection Customer prior to initiating parallel operation with the [ Distribution Company's utility ] system.

    Attachment 6 to

    Schedule [ 5 6 ]

    [ Distribution Company's Utility's ] Description of its [ Distribution and Transmission ] Upgrades [ And Best and ] Estimate of Upgrade Costs

    The [ Distribution Company shall describe upgrades and provide an itemized estimate of the cost, including overheads, of the upgrades and annual operation and maintenance expenses associated with such upgrades. The Distribution Company shall functionalize upgrade costs and annual expenses as either transmission or distribution related. utility shall provide the following in this attachment:

    1. An itemized list of the upgrades required to be constructed by the utility prior to interconnection of the Small Generating Facility, with transmission and distribution related upgrades shown separately.

    2. An estimate of the cost of each item listed pursuant to item 1.

    3. An estimate of annual operation and maintenance expenses associated with such upgrades that are to be charged to the Interconnection Customer, shown separately for transmission and distribution related items. ]

    Attestation

    VA.R. Doc. No. R08-1147; Filed December 1, 2008, 10:48 a.m.