9VAC25-193 General Virginia Pollutant Discharge Elimination System (VPDES) Permit for Concrete Products Facilities
-
REGULATIONS
Vol. 29 Iss. 5 - November 05, 2012TITLE 9. ENVIRONMENTSTATE WATER CONTROL BOARDChapter 193Proposed RegulationREGISTRAR'S NOTICE: The State Water Control Board is claiming an exemption from the Administrative Process Act in accordance with § 2.2-4006 A 8 of the Code of Virginia, which exempts general permits issued by the State Water Control Board pursuant to the State Water Control Law (§ 62.1-44.2 et seq.), Chapter 24 (§ 62.1-242 et seq.) of Title 62.1, and Chapter 25 (§ 62.1-254 et seq.) of Title 62.1 of the Code of Virginia if the board (i) provides a Notice of Intended Regulatory Action in conformance with the provisions of § 2.2-4007.01; (ii) following the passage of 30 days from the publication of the Notice of Intended Regulatory Action forms a technical advisory committee composed of relevant stakeholders, including potentially affected citizens groups, to assist in the development of the general permit; (iii) provides notice and receives oral and written comment as provided in § 2.2-4007.03; and (iv) conducts at least one public hearing on the proposed general permit.
Title of Regulation: 9VAC25-193. General Virginia Pollutant Discharge Elimination System (VPDES) Permit for Concrete Products Facilities (amending 9VAC25-193-10 through 9VAC25-193-70; adding 9VAC25-193-15).
Statutory Authority: § 62.1-44.15 of the Code of Virginia; § 402 of the federal Clean Water Act; 40 CFR Parts 122, 123, and 124.
Public Hearing Information:
December 5, 2012 - 10 a.m. - Department of Environmental Quality, Piedmont Regional Office, Training Room, 4949 Cox Road, Glen Allen, VA
Public Comment Deadline: January 11, 2013.
Agency Contact: Elleanore M. Daub, Department of Environmental Quality, 629 East Main Street, P.O. Box 1105, Richmond, VA 23218, telephone (804) 698-4111, FAX (804) 698-4032, TTY (804) 698-4021, or email elleanore.daub@deq.virginia.gov.
Summary:
The proposed regulatory action reissues the existing Virginia Pollutant Discharge Elimination System (VPDES) general permit that expires on September 30, 2013. The general permit contains limitations and monitoring requirements for point source discharge of treated wastewaters from concrete products facilities to surface waters.
Substantive proposed changes (i) add two reasons authorization to discharge cannot be granted (if the antidegradation policy is not met or if the discharge is not consistent with a total maximum daily load (TMDL)), (ii) add language to allow for administrative continuances of coverage, (iii) add approval of representative outfalls and closure plans for portable plants as part of the registration, (iv) reduce monitoring requirements from monthly to quarterly, (v) clarify that total petroleum hydrocarbon monitoring was only necessary when vehicle degreasing was occurring on site, (vi) add benchmark monitoring concentrations for storm water, and (vii) remove total petroleum hydrocarbon and iron monitoring from the storm water limits page.
In the special conditions, the proposed changes clarify what information is required for temporary and long-term facility closure plans and add (i) that no oil sheen shall be present and waste water should be reused or recycled when feasible, (iii) that settling basins must be lined if they are expanded, (iv) quantification levels of total suspended solids and total petroleum hydrocarbons, (v) that discharges to TMDL waters must implement measures and controls consistent with the TMDL, (vi) an allowance for deleting or adding outfalls, (vii) procedures for termination of coverage, (viii) instructions for allowing temporary closures for inactive and unstaffed sites, (ix) that discharges must meet water quality standards and (x) that coverage under the permit did not relieve an owner of compliance with any other federal, state, or local statute, ordinance, or regulation.
This action revises Part II (Storm Water Management) to make it more consistent with the 2009 Industrial Storm Water General Permit (9VAC25-151) conditions. Changes make this general permit similar to other general permits issued recently and respond to staff and technical advisory committee members' requests to clarify and update permit limits and conditions.
9VAC25-193-10. Definitions.
The words and terms used in this chapter shall have the meanings defined in § 62.1-44.2 et seq. of the Code of Virginia (State Water Control Law) and 9VAC25-31 (VPDES Permit Regulation), unless the context clearly indicates otherwise, except that for the purposes of this chapter:
"Best management practices" or "BMPs" means schedules of activities, practices and prohibitions of practices, structures, vegetation, maintenance procedures, and other management practices to prevent or reduce the discharge of pollutants to surface waters. BMPs also include treatment requirements, operating procedures, and practices to control plant site runoff, spillage or leaks, sludge or waste disposal, or drainage from raw material storage.
"Department" or "DEQ" means the Virginia Department of Environmental Quality.
"Industrial activity" means facilities or those portions of a facility where the primary purpose is classified as:
1. Standard Industrial Classification (SIC) Code 3271—Concrete Block and Brick (Office of Management and Budget (OMB) SIC Manual, 1987);
2. SIC Code 3272—Concrete Products, Except Block and Brick; or
3. SIC Code 3273—Ready-Mixed Concrete, including both permanent and portable plants.
These facilities are collectively defined as "Concrete Products Facilities".
"Municipal separate storm sewer system" or "MS4" means a conveyance or system of conveyances (including roads with drainage systems, municipal streets, catch basins, curbs, gutters, ditches, man-made channels, or storm drains): (i) owned or operated by a state, city, town, county, district, association, or other public body (created by or pursuant to state law) having jurisdiction over disposal of sewage, industrial wastes, storm water, or other wastes, including special districts under state law such as a sewer district, flood control district or drainage district, or similar entity, or an Indian tribe or an authorized Indian tribal organization, or a designated and approved management agency under § 208 of the Clean Water Act (CWA) (33 USC § 1251 et seq.) that discharges to surface waters of the state; (ii) designed or used for collecting or conveying storm water; (iii) which is not a combined sewer; and (iv) which is not part of a Publicly Owned Treatment Works (POTW).
"Runoff coefficient" means the fraction of total rainfall that will appear at the conveyance as runoff.
"Significant spills" includes, but is not limited to, releases of oil or hazardous substances in excess of reportable quantities under § 311 of the Clean Water Act (see 40 CFR 110.10 and 40 CFR 117.21) or § 102 of the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) (42 USC § 9601 et seq.) (see 40 CFR 302.4).
"Total maximum daily load" or "TMDL" means a calculation of the maximum amount of a pollutant that a waterbody can receive and still meet water quality standards and an allocation of that amount to the pollutant's sources. A TMDL includes wasteload allocations (WLAs) for point source discharges and load allocations (LAs) for nonpoint sources or natural background, or both, and must include a margin of safety (MOS) and account for seasonal variations.
"Vehicle or equipment degreasing" means the washing or steam cleaning of engines or other drive components of a vehicle or piece of equipment in which the purpose is to degrease and clean petroleum products from the equipment for maintenance purposes. Removing sediment and concrete residue is not considered vehicle or equipment degreasing.
9VAC25-193-15. Applicability of incorporated references based on the dates that they became effective.
Except as noted, when a regulation of the U.S. Environmental Protection Agency set forth in Title 40 of the Code of Federal Regulations is referenced or adopted herein and incorporated by reference, that regulation shall be as it exists and has been published as a final regulation in the Federal Register prior to July 1, 2013, with the effective date as published in the Federal Register notice or October 1, 2013, whichever is later.
9VAC25-193-20. Purpose.
This general permit regulation governs the discharge of process waste water, noncontact cooling water, and storm water associated with industrial activity from concrete products facilities classified as Standard Industrial Classification Codes 3271, 3272 and 3273, provided that the discharge is through a point source to surface waters.
9VAC25-193-30. Delegation of authority.
The director of the Department of Environmental Quality, or his designee, may perform any act of the board provided under this chapter, except as limited by § 62.1-44.14 of the Code of Virginia.
9VAC25-193-40. Effective date of the permit.
This general VPDES permit
becamewill become effective onOctober 1, 2008October 1, 2013, and it will expire onSeptember 30, 2013September 30, 2018.With respect to a particular facility, thisThis general permitshall becomeis effective for any covered owner uponthe facility owner'scompliance with all the provisions of 9VAC25-193-50and the receipt of a copy of the general VPDES permit.9VAC25-193-50. Authorization to discharge.
A. Any owner governed by this general permit is hereby authorized to discharge process water, storm water associated with this industrial activity, cooling water, or commingled discharges of these types to surface waters of the Commonwealth of Virginia provided that
the owner has filed with the department theregistration statement described in 9VAC25-193-60, has filed the required permit fee, has complied or will comply with the effluent limitations and other requirements of 9VAC25-193-70, and has complied with the following conditions:1. The owner submits a registration statement in accordance with 9VAC25-193-60 and that registration statement is accepted by the board;
2. The owner submits the required permit fee;
3. The owner complies with the applicable effluent limitations and other requirements of 9VAC25-193-70; and
4. The board has not notified the owner that the discharge is not eligible for coverage in accordance with subsection B of this section.
B. The board will notify an owner that the discharge is not eligible for coverage under this general permit in the event of any of the following:
1. The owner
shall not have beenis required to obtain an individual permitas may be requiredin accordance with 9VAC25-31-170 B 3 of the VPDES Permit Regulation;and2. The owner
shall not be authorized by this general permitis proposing to discharge to state waters specifically named in other board regulationsor policies whichthat prohibit such discharges.;3. The discharge violates or would violate the antidegradation policy in the Water Quality Standards at 9VAC25-260-30; or
4. The discharge is not consistent with the assumptions and requirements of an approved TMDL.
B. Receipt ofC. Compliance with this general permit constitutes compliance with the federal Clean Water Act (33 USC § 1251 et seq.), the State Water Control Law, and applicable regulations under either with the exceptions stated in 9VAC25-31-60 of the VPDES Permit Regulation. Approval for coverage under this general permit does not relieve any owner of the responsibility to comply with any other applicable federal, state, or local statute, ordinance, or regulation.D. Continuation of permit coverage.
1. Any owner that was authorized to discharge under the concrete products general permit issued in 2008 and that submits a complete registration statement on or before October 1, 2013, is authorized to continue to discharge under the terms of the 2008 general permit until such time as the board either:
a. Issues coverage to the owner under this general permit; or
b. Notifies the owner that the discharge is not eligible for coverage under this general permit.
2. When the owner that was covered under the expiring or expired general permit has violated or is violating the conditions of that permit, the board may choose to do any or all of the following:
a. Initiate enforcement action based upon the general permit that has been continued;
b. Issue a notice of intent to deny coverage under the reissued general permit. If the general permit coverage is denied, the owner would then be required to cease the discharges authorized by the continued general permit or be subject to enforcement action for discharging without a permit;
c. Issue an individual permit with appropriate conditions; or
d. Take other actions authorized by the VPDES Permit Regulation (9VAC25-31).
9VAC25-193-60. Registration statement.
A. Deadlines for submitting registration statement.
The owner shall file a complete General VPDES Permit registration statement which shall serve as a notice of intent to be covered under the general VPDES permit for concrete products facilities. Any owner proposing a new discharge shall file a complete registration statement at least 30 days prior to the date planned for commencing operation of the concrete products facility. Any owner of an existing concrete products facility covered by an individual VPDES permit who is proposing to be covered by this general permit shall file a complete registration statement at least 180 days prior to the expiration date of the individual VPDES permit. Any owner of an existing concrete products facility not currently covered by a VPDES permit who is proposing to be covered by this general permit shall file a complete registration statement.The owner seeking coverage under this general permit shall submit a complete VPDES general permit registration statement in accordance with this section, which shall serve as a notice of intent for coverage under the general VPDES permit for concrete products facilities.1. New facilities. Any owner proposing a new discharge shall submit a complete registration statement at least 30 days prior to the date planned for commencement of the new discharge.
2. Existing facilities.
a. Any owner covered by an individual VPDES permit who is proposing to be covered by this general permit shall submit a complete registration statement at least 210 days prior to the expiration date of the individual VPDES permit.
b. Any owner that was authorized to discharge under the general VPDES permit that became effective on October 1, 2008, and who intends to continue coverage under this general permit shall submit a complete registration statement to the board on or before July 1, 2013.
B. Late registration statements. Registration statements for existing facilities covered under subdivision A 2 b of this section will be accepted after October 1, 2013, but authorization to discharge will not be retroactive. Owners described in subdivision A 2 b of this section that submit registration statements after July 1, 2013, are authorized to discharge under the provisions of 9VAC25-193-50 D if a complete registration statement is submitted on or before October 1, 2013.
C. The required registration statement shall contain the following information:
B. The owner shall submit a registration statement that contains the following information:1. Name and location of the facility;2. Name, mailing address, and telephone number of the facility owner;3. Name, mailing address, and telephone number of the operator if different than owner;1. Facility name and address, owner name, mailing address, telephone number, and email address (if available);
2. Operator or other contact name, mailing address, telephone number, and email address (if available) if different from owner;
4.3. Facility's Standard Industrial Classification (SIC) Code(s);5.4. Nature of business at facility;6.5. Indicate if the facility is proposed or existing; if the facility has a current VPDES and/or VPA Permit; and Permit Number(s) for any current VPDES and/or VPA Permits;7.6. Description of the wastewater treatment or reuse/recycle system(s); indicate if there are any system(s) which operate in a "no discharge" mode;8.7. If settling basins are used for treatment and control of process wastewater and commingled storm water, indicate the original date of construction, and whether these basins are lined with concrete or any other impermeable materials;9.8. Indicate if there arevehicle/equipment maintenancevehicle or equipment degreasing activities performed on site. If yes, indicate if there is any process wastewater generated from these activities;10.9. Indicate if a noncontact cooling water system is in use and if this facility discharges noncontact cooling water from a geothermal unit or other system. If yes,description of the source of noncontact cooling water; 11. Indicate if any chemical additives are used in the geothermal or other system which discharges noncontact cooling water. If yes, list of chemical additive employed and its purpose; proposed schedule and quantity of chemical usage, and estimated concentration in the discharge; description of any wastewater treatment or retention during the use of the additives, if applicable; and a Material Safety Data Sheet (MSDS) and available aquatic toxicity information for each additive proposed for use;provide the following:a. Describe the source of noncontact cooling water; and
b. If applicable, list chemical additives employed and their purpose, proposed schedule and quantity of chemical usage, estimated concentration in the discharge, description of any wastewater treatment or retention during the use of the additives, and a Material Safety Data Sheet (MSDS) and available aquatic toxicity information for each additive proposed for use;
12.10. Description of any measures employed to reclaim, reuse or disposal of thewasteresidual concrete materials;13.11. A schematic drawing which shows the source(s) of water used on the property, the industrial operations contributing to or using water,andthe conceptual design of the methods of treatment and disposal of wastewater and solids and the storm water pollution prevention plan site map (see 9VAC25-193-70 Part II G 6 c);14.12. A USGS 7.5 minute topographic map or equivalent computer generated map, extending to at least one mile beyond property boundary, which shows theoutline of the facilityproperty boundary, the location of each of its existing and proposed intake and discharge points, and the locations of any wells, springs, and other surface water bodies;15.13. Discharge outfall information, including outfall number(s),processes involveddescription of wastewater discharged from each outfall, estimated flow (gallons per day), receiving water bodies,andduration and frequency of each discharge (hours per day and days per week), and latitude and longitude of outfall location;14. Indicate which storm water outfalls will be representative outfalls (if any). For storm water outfalls that are to be represented by other outfall discharges, provide the following:
a. The locations of the outfalls;
b. Why the outfalls are expected to discharge substantially identical effluents including, where available, evaluation of monitoring data;
c. Estimates of the size of the drainage area (in square feet) for each of the outfalls; and
d. An estimate of the runoff coefficient of the drainage areas (low: under 40%; medium: 40% to 65%; high: above 65%);
16. For a proposed facility that discharges storm water, indicate15. Indicate if a Storm Water Pollution Prevention Plan has been prepared.;16. Whether the facility will discharge to a municipal separate storm sewer system (MS4). If so, provide the name of the MS4 owner. The owner of the facility shall notify the MS4 owner in writing of the existence of the discharge within 30 days of coverage under the general permit and shall copy the DEQ regional office with the notification. The notification shall include the following information: the name of the facility, a contact person and phone number, the location of the discharge, the nature of the discharge, and the facility's VPDES general permit number;
17. For portable concrete products operations, submit a closure plan and include the requirements specified by the operation and maintenance manual in 9VAC25-70 Part I B 9 a (4) of the permit; and
17.18. The following certification: "I hereby grant to duly authorized agents of the Department of Environmental Quality, upon presentation of credentials, permission to enter the property where the treatment works is located for the purpose of determining compliance with or the suitability of coverage under the General Permit. I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is to the best of my knowledge and belief true, accurate, and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment for knowing violations."D. The registration statement shall be signed in accordance with the requirements of 9VAC25-31-110.
9VAC25-193-70. General permit.
Any owner whose registration statement is accepted by the board will receive the following permit and shall comply with the requirements contained therein and be subject to all requirements of 9VAC25-31.
General Permit No: VAG11
Effective Date:October 1, 2008October 1, 2013
Expiration Date:September 30, 2013September 30, 2018GENERAL PERMIT FOR CONCRETE PRODUCTS FACILITIES AUTHORIZATION TO DISCHARGE UNDER THE VIRGINIA POLLUTANT DISCHARGE ELIMINATION SYSTEM AND THE VIRGINIA STATE WATER CONTROL LAW
In compliance with the provisions of the Clean Water Act, as amended, and pursuant to the State Water Control Law and regulations adopted pursuant thereto, owners of concrete products facilities are authorized to discharge to surface waters within the boundaries of the Commonwealth of Virginia, except those specifically named in board regulations
or policieswhich prohibit such discharges.The authorized discharge shall be in accordance with this cover page, Part I-Effluent Limitations, Monitoring Requirements, and Special Conditions, Part II-Storm Water Management, and Part III-Conditions Applicable to All VPDES Permits, as set forth herein.
Part I
Effluent Limitations, Monitoring Requirements, and Special Conditions.A. Effluent limitations and monitoring requirements.
1. Process wastewater.
During the period beginning
on the permit's effective datewith the permittee's coverage under this general permit and lasting until the permit's expiration date, the permittee is authorized to discharge process wastewater which may contain input fromvehicle/equipment maintenance activitiesvehicle wash water, or vehicle or equipment degreasing activities, and may be commingled with noncontact cooling wateror, storm water associated with industrial activity, or both. Samples taken in compliance with the monitoring requirements specified below shall be taken at outfall(s) .Such discharges shall be limited and monitored by the permittee as specified below:
EFFLUENT CHARACTERISTICS
DISCHARGE LIMITATIONS
MONITORING REQUIREMENTS
Average
Maximum
Minimum
Frequency(6)
Sample Type
Flow (MGD)
NL
NL
NLNA(6)1/3 MonthsEstimate
Total Suspended Solids (mg/l)
30
60
NLNA(6)1/3 MonthsGrab
pH (standard units)
NA
9.0(1)
6.0(1)
(6)1/3 MonthsGrab
Total Petroleum Hydrocarbons(2) (mg/l)
NA
15
NLNA1/3 Months
Grab
Total Residual Chlorine(3) (mg/l)
0.016
0.016
NLNA(6)1/3 MonthsGrab
Ammonia-N(3) (mg/l)
NA
NL
NLNA(6)1/3 MonthsGrab
Temperature(4) (°C)
NA
(5)
NLNA(6)1/3 MonthsImmersion Stabilization
NL = No limitation, monitoring required
NA = Not applicable
(1)Where the Water Quality Standards (9VAC25-260) establish alternate standards for pH in the waters receiving the discharge, those standards shall be the maximum and minimum effluent limitations.
(2)Total Petroleum Hydrocarbons limitation and monitoring are only required where a discharge contains process wastewater generated from the
vehicle/equipment maintenancevehicle or equipment degreasing activities. Total Petroleum Hydrocarbons shall be analyzed usingthe Wisconsin Department of Natural Resources Modified Diesel Range Organics Method as specified in Wisconsin publication SW-141 (1995), or byEPA SW-846 Method 8015 B (1996), 8015C (2000), 8015C (2007), 8015 D (2003) for diesel range organics, or by EPA SW-846 Method 8270D (2007)or EPA 40 CFR 136.If Method 8270D is used, the lab must report the combination of diesel range organics and polynuclear aromatic hydrocarbons.(3)Chlorine limitation and monitoring are only required where the discharge contains cooling water that is chlorinated. Ammonia monitoring is only required where the discharge contains cooling water that is disinfected using chloramines.
(4)Temperature limitation and monitoring are only required where a discharge contains cooling water.
(5)The effluent temperature shall not exceed a maximum 32°C for discharges to nontidal coastal and piedmont waters, 31°C for mountain and upper piedmont waters, 21°C for put and take trout waters, or 20°C for natural trout waters. No maximum temperature limit applies to discharges to estuarine waters.
For estuarine waters, nontidal coastal and piedmont waters, mountain and upper piedmont waters, and put and take trout waters, the effluent shall not cause an increase in temperature of the receiving stream of more than 3°C above the natural water temperature. For natural trout waters, the temperature of the effluent shall not cause an increase of 1°C above natural water temperature. The effluent shall not cause the temperature in the receiving stream to change more than 2°C per hour, except in the case of natural trout waters where the hourly temperature change shall not exceed 0.5°C.
Natural temperature is defined as that temperature of a body of water (measured as the arithmetic average over one hour) due solely to natural conditions without the influence of any point-source discharge.
(6)
For a facility that was covered by the previous general permit, and reduced monitoring was granted and compliance demonstrated, monitoring frequency shall be 1/quarter. In all other cases, monitoring frequency shall be 1/month in the first year of permit coverage. If the first year results demonstrate full compliance with the effluent limitations and the permittee receives authorization from the DEQ regional office, monitoring frequency shall be reduced to 1/quarter. Should the permittee be issued a warning letter related to violation of effluent limitations, a notice of violation, or be the subject of an active enforcement action, monitoring frequency shall revert to 1/month, upon issuance of the letter or notice or initiation of the enforcement action and remain in effect until the permit's expiration date. Reports of quarterly monitoring shall be submitted1/3 months means one sample collected per calendar quarter with reports due to the DEQ regional office no later than the 10th day of April, July, October, and January.Part I. Effluent Limitations and Monitoring RequirementsA. Effluent limitations and monitoring requirements.2. Noncontact cooling water.
During the period beginning
on the permit's effective datewith the permittee's coverage under this general permit and lasting until the permit's expiration date, the permittee is authorized to discharge noncontact cooling water. Samples taken in compliance with the monitoring requirements specified below shall be taken at outfall(s) .Such discharges shall be limited and monitored by the permittee as specified below:
EFFLUENT CHARACTERISTICS
DISCHARGE LIMITATIONS
MONITORING REQUIREMENTS
Average
Maximum
Minimum
Frequency(4)
Sample Type
Flow (MGD)
NL
NL
NA
(4)1/3 MonthsEstimate
pH (standard units)
NA
9.0(1)
6.0(1)
(4)1/3 MonthsGrab
Total Residual Chlorine(2) (mg/l)
0.016
0.016
NA
(4)1/3 MonthsGrab
Ammonia-N(2) (mg/l)
NA
NL
NA
(4)1/3 MonthsGrab
Temperature (°C)
NA
(3)
NA
(4)1/3 MonthsImmersion Stabilization
NL = No limitation, monitoring required
NA = Not applicable
(1)Where the Water Quality Standards (9VAC25-260) establish alternate standards for pH in the waters receiving the discharge, those standards shall be the maximum and minimum effluent limitations.
(2)Chlorine limitation and monitoring are only required where the source of cooling water is chlorinated. Ammonia monitoring is only required where cooling water is disinfected using chloramines.
(3)The effluent temperature shall not exceed a maximum 32°C for discharges to nontidal coastal and piedmont waters, 31°C for mountain and upper piedmont waters, 21°C for put and take trout waters, or 20°C for natural trout waters. No maximum temperature limit applies to discharges to estuarine waters. For estuarine waters, nontidal coastal and piedmont waters, mountain and upper piedmont waters, and put and take trout waters, the effluent shall not cause an increase in temperature of the receiving stream of more than 3°C above the natural water temperature. For natural trout waters, the temperature of the effluent shall not cause an increase of 1°C above natural water temperature. The effluent shall not cause the temperature in the receiving stream to change more than 2°C per hour, except in the case of natural trout waters where the hourly temperature change shall not exceed 0.5°C. Natural temperature is defined as that temperature of a body of water (measured as the arithmetic average over one hour) due solely to natural conditions without the influence of any point-source discharge.
(4)
For a facility that was covered by the previous general permit, and reduced monitoring was granted and compliance demonstrated, monitoring frequency shall be 1/quarter. In all other cases, monitoring frequency shall be 1/month in the first year of permit coverage. If the first year results demonstrate full compliance with the effluent limitations and the permittee receives authorization from the DEQ regional office, monitoring frequency shall be reduced to 1/quarter. Should the permittee be issued a warning letter related to violation of effluent limitations, a notice of violation, or be the subject of an active enforcement action, monitoring frequency shall be reverted to 1/month, upon issuance of the letter or notice or initiation of the enforcement action and remain in effect until the permit's expiration date. Reports of quarterly monitoring shall be submitted1/3 months means one sample collected per calendar quarter with reports due to the DEQ regional office no later than the 10th day of April, July, October, and January.Part I. Effluent Limitations and Monitoring RequirementsA. Effluent limitations and monitoring requirements.3. Storm water associated with industrial activity—storm event benchmark monitoring.
During the period beginning
on the permit's effective datewith the permittee's coverage under this general permit and lasting until the permit's expiration date, the permittee is authorized to discharge storm water associated with industrial activity which does not combine with other process wastewaters or noncontact cooling water prior to discharge. Samples taken in compliance with the monitoring requirements specified below shall be taken at outfall(s) .Such discharges shall be limited and monitored by the permittee as specified below:
EFFLUENT CHARACTERISTICS
DISCHARGE LIMITATIONS BENCHMARK MONITORING
MONITORING REQUIREMENTS(3), (5)
Maximum
Minimum
Frequency(4)
Sample Type
Flow
(MGD)(MG)NL
NA
1/Year
Estimate(1)
Total Petroleum Hydrocarbons(3) (mg/l)NLNA1/YearGrab(2)Total Suspended Solids (mg/l)
NL(2)
NA
1/Year
Grab(2)
Total Recoverable Iron (mg/l)NLNA1/YearGrab(2)pH (standard units)
NL(2)
NANL (2)1/Year
Grab(2)
NL = No limitation, monitoring required
NA = Not applicable
(1)Estimate of the total volume of the discharge during the storm event in accordance with the Operation and Maintenance Manual.
(2)The grab sample shall be taken during the first 30 minutes of the discharge. If during the first 30 minutes it was impracticable, then a grab sample shall be taken during the first hour of discharge, and the permittee shall submit with the Discharge Monitoring Report a description of why a grab sample during the first 30 minutes was impracticable.(3)Total Petroleum Hydrocarbons shall be analyzed using the Wisconsin Department of Natural Resources Modified Diesel Range Organics Method as specified in Wisconsin publication SW-141 (1995), or by EPA SW-846 Method 8015C (2007) for diesel range organics, or by EPA SW-846 Method 8270D (2007). If Method 8270D is used, the lab must report the combination of diesel range organics and polynuclear aromatic hydrocarbons.4. All storm water samples shall be collected from the discharge resulting from a storm event that is greater than 0.1 inches in magnitude and that occurs at least 72 hours from the previously measurable (greater than 0.1 inch rainfall) storm event. Specific storm event data shall be reported with the Discharge Monitoring Report in accordance with Part II A.5. Reports of annual monitoring shall be submitted to the DEQ regional office no later than the 10th day of January of each year.6. A quarterly visual monitoring shall be performed and recorded in accordance with Part II D.(2)Should the benchmark monitoring for TSS exceed 100 mg/l maximum or the pH fall outside of the range of 6.0-9.0 standard units, the permittee shall evaluate the overall effectiveness of the SWPPP in controlling the discharge of pollutants to receiving waters. Benchmark concentration values are not effluent limitations. Exceedance of a benchmark concentration does not constitute a violation of this permit and does not indicate that violation of a water quality standard has occurred; however, it does signal that modifications to the SWPPP are necessary, unless justification is provided in the routine facility inspection or comprehensive site compliance evaluation.
(3)Specific storm event data shall be reported with the Discharge Monitoring Report (DMR) in accordance with Part II A.
(4)1/year means one sample taken per calendar year with the annual report due to the DEQ regional office no later than the 10th day of January of each year.
(5)Quarterly visual monitoring shall be performed and recorded in accordance with Part II D.
B. Special conditions.
1. There shall be no discharge of floating solids or visible foam in other than trace amounts. There shall be no solids deposition or oil sheen from petroleum products in surface water as a result of the industrial activity in the vicinity of the outfall.
2. Except as expressly authorized by this permit, no product, materials, industrial wastes, or other wastes resulting from the purchase, sale, mining, extraction, transport, preparation, or storage of raw or intermediate materials, final product, byproduct or wastes, shall be handled, disposed of, or stored so as to permit a discharge of such product, materials, industrial wastes, or other wastes to surface waters.
3. Vehicles and equipment utilized during the industrial activity on a site must be operated and maintained in such a manner as to minimize the potential or actual point source pollution of surface waters. Fuels, lubricants, coolants, and hydraulic fluids, or any other petroleum products, shall not be disposed of by discharging on the ground or into surface waters. Spent fluids shall be disposed of in a manner so as not to enter the surface or ground waters of the state and in accordance with the applicable state and federal disposal regulations. Any spilled fluids shall be cleaned up
to the maximum extent practicableand disposed of in a manner so as not to allow their entry into the surface or ground waters of the state.4. All washdown and washout of trucks, mixers, transport buckets, forms or other equipment shall be conducted within designated washdown and washout areas. All
washout/washdownwashdown and washout water shall be collected for recycle or collected and treated to meet the limits in Part I A prior to discharge to the receiving stream.5. Any waste concrete and dredged solids from the settling basins shall be managed within a designated area, and any wastewaters including storm water generated from these activities shall be collected for recycle or treated prior to discharge.
6. Wastewater should be reused or recycled whenever feasible.
6.7. Nodomesticsewage discharges to surface waters are permitted under this general permit.7.8. For geothermal or other system which discharges noncontact cooling water, the use of any chemical additives, except chlorine, without prior approval is prohibited under this general permit. Prior approval shall be obtained from the DEQ Regional Office before any changes are made to the chemical usage in the geothermal or other system. Requests for approval of chemical use shall be made in writing and shall include the following information:a. The chemical additive to be employed and its purpose;
b. The proposed schedule and quantity of chemical usage, and the estimated concentration in the discharge;
c. The wastewater treatment or retention (if any) to be provided during the use of the additive; and
d. A Material Safety Data Sheet (MSDS) and
availableany of the manufacturer's aquatic toxicity information for each additive proposed for use.8.9. Operations and Maintenance (O&M) Manual.a. Within 180 days after the date of coverage under this general permit, the permittee shall develop or review and update, as appropriate, an Operations and Maintenance (O&M) Manual for the permitted facility. The O&M Manual shall include procedures and practices for the mitigation of pollutant discharges
andfor the protection of state waters from the facility's operations and to ensure compliance with the requirements of the permit. The manual shall address, at a minimum, operations:(1) Operations and maintenance practices for the wastewater treatment process units and chemical and material storage areas
, solids;(2) Methods for estimating process wastewater flows;
(3) Solids management and disposal procedures
, temporary;(4) Temporary and long-term facility closure plans
, testingthat shall include (i) treatment, removal, and final disposition of residual wastewater, contaminated storm water held at the facility, and solids; (ii) fate of structures; (iii) a removal plan for all exposed industrial materials; and (iv) description of the stabilization of land in which they were stored or placed;(5) Testing requirements and procedures
, recordkeeping;(6) Recordkeeping and reporting requirements
and the duties; and(7) Duties and roles of responsible officials.
b. The permittee shall
implement the O&M Manual procedures and practices as soon as possible but no later than 12 months after the date of coverage under this general permit. The manual shall be kept on site at the permitted facility and shall be made available to the department upon request.operate the treatment works in accordance with the O&M manual. The O&M manual shall be reviewed and updated at least annually and shall be signed and certified in accordance with Part III K of this permit. The O&M manual shall be made available for review by department personnel upon request.For a facility that was covered by the previous permit, an O&M Manual was required to be developed and implemented for that facility. Within 90 days after the date of coverage under this general permit, the existing O&M Manual shall be reviewed and modified, as appropriate, to conform to the requirements of this permit. The existing O&M Manual shall continue to be implemented until the manual, if required, is revised and implemented.9.10. If the concrete products facility discharges through a municipal separate storm sewer system to surface waters, the permittee shall, within 30 days of coverage under this general permit, notify the owner of the municipal separate storm sewer system of the existence of the discharge and provide the following information: the name of the facility;, a contact person and phone number;, the nature of the discharge; number of the outfalls; and, the location of the discharge, and the facility's VPDES general permit number. A copy of such notification shall be provided to the department.10.11. The permittee shall ensure that all basins and lagoons maintain a minimum freeboard of one foot at all times except during a 72-hour transition period after a measurable rainfall event. During the 72-hour transition period, no discharge from the basins and lagoons shall occur unless it is in accordance with this permit. Within 72 hours after a measurable rainfall event, the freeboard in all basins and lagoons shallreturnbe returned to the minimum freeboard of one foot. Where basins are operated in a series mode of operation, the one-foot freeboard requirement for the upper basins may be waived provided the final basin will maintain the freeboard requirements of this special condition. Should the one-foot freeboard not be maintained, the permittee shall immediately notify the DEQ Regional Office, describe the problem and corrective measures taken to correct the problem. Within five days of notification, the permittee shall submit a written statement to theregional office of explanationDEQ Regional Office with an explanation of the problem and corrective measures taken. In order to demonstrate compliance with this special condition, the permittee shall conduct daily inspections while the facility is in operation and maintain an inspection log. The inspection log shall include at least the date and time of inspection, the weather data including the occurrence of a measurable rainfall event, the printed name and the handwritten signature of the inspector, the freeboard measurement in inches, a notation of observation made, and any corrective measures, if appropriate, taken. The log shall be kept onsite and be made available to the department upon request.11.12. For treatment systems which operate only in a "no discharge" mode, there shall be no discharge of pollutants to surface waters from these systems except in the case of a storm event which is greater than a 25 year-24 hour storm event. The operation of these systems shall not contravene the Water Quality Standards (9VAC25-260), as adopted and amended by the board, or any provision of the State Water Control Law.12.13. The permittee shall notify the department as soon as he knows or has reason to believe:a. That any activity has occurred or will occur which would result in the discharge, on a routine or frequent basis, of any toxic pollutant which is not limited in this permit if that discharge will exceed the highest of the following notification levels:
(1) One hundred micrograms per liter (100 µg/l);
(2) Two hundred micrograms per liter (200 µg/l) for acrolein and acrylonitrile; five hundred micrograms per liter (500 µg/l) for 2,4-dinitrophenol and for 2-methyl-4,6-dinitrophenol; and one milligram per liter (1 mg/l) for antimony;
(3) Five times the maximum concentration value reported for that pollutant in the permit application; or
(4) The level established by the board in accordance with 9VAC25-31-220 F.
b. That any activity has occurred or will occur which would result in any discharge, on a nonroutine or infrequent basis, of a toxic pollutant which is not limited in this permit if that discharge will exceed the highest of the following notification levels:
(1) Five hundred micrograms per liter (500 µg/l);
(2) One milligram per liter (1 mg/l) for antimony;
(3) Ten times the maximum concentration value reported for that pollutant in the permit application; or
(4) The level established by the board in accordance with 9VAC25-31-220 F.
13.14. All settling basins used for treatment and control of process wastewater or process wastewater commingled with storm water that were constructed on or after February 2, 1998, shall be lined with concrete or any other impermeable materials. Regardless of date of construction, all settling basins used for treatment and control of process wastewater or process wastewater commingled with storm water that are expanded or dewatered for major structural repairs shall be lined with concrete or any other impermeable materials.14. Treated15. Settled wastewater may be used on site for the purposes of dust suppression or for spraying stockpiles.Dust suppressionThese activities shall be carried out as a best management practice but not a wastewater disposal method.No ponding or surface runoff shall occur as a result of such activity.There shall be no direct discharge to surface waters from dust suppression or as a result of spraying stockpiles.15.16. Compliance reporting under Part I A.a. The quantification levels (QL) shall be as follows:
Effluent Characteristic
Quantification Level
TSS
1.0 mg/l
TPH
5.0 mg/l
Chlorine
0.10 mg/l
Ammonia-N
0.20 mg/l
b. Reporting.
(1) Monthly Average. Compliance with the monthly average limitations and/or reporting requirements for the parameters listed in Part I A shall be determined as follows: All concentration data below the QL listed in
subsection 15subdivision 16 a of this subsection shall be treated as zero. All concentration data equal to or above the QL listed shall be treated as it is reported. An arithmetic average shall be calculated using all reported data, including the defined zeros, for the month. This arithmetic average shall be reported on the DMR as calculated. If all data are below the QL then the average shall be reported as "<QL." If reporting for quantity is required on the DMR and the calculated concentration is <QL then report "<QL" for the quantity, otherwise use the calculated concentration.(2) Daily Maximum. Compliance with the daily maximum limitations and/or reporting requirements for the parameters listed in Part I A shall be determined as follows: All concentration data below the QL listed in subdivision 15 a of this subsection shall be treated as zero. All concentration data equal to or above the QL shall be treated as reported. An arithmetic average of the values shall be calculated using all reported data, including the defined zeros, collected for each day during the reporting month. The maximum value of these daily averages thus determined shall be reported on the DMR as the Daily Maximum. If all data are below the QL then the average shall be reported as "<QL." If reporting for quantity is required on the DMR and the calculated concentration is <QL then report "<QL" for the quantity, otherwise use the calculated concentration.
(3) Any single datum required shall be reported as "<QL" if it less than the QL listed in subdivision
1516 a of this subsection. Otherwise the numerical value shall be reported.(4) The permittee shall report at least two significant digits for a given parameter. Regardless of the rounding convention used (i.e. five always rounding up or to the nearest even number) by the permittee, the permittee shall use the convention consistently and shall ensure that consulting laboratories employed by the permittee use the same convention.
17. Discharges to waters with an approved total maximum daily load (TMDL). Owners of facilities that are a source of the specified pollutant of concern to waters where an approved TMDL has been established shall implement measures and controls that are consistent with the assumptions and requirements of the TMDL.
18. Adding or deleting outfalls. The permittee may add new or delete existing outfalls at the facility as necessary and appropriate. The permittee shall update the O&M manual and storm water pollution prevention plan (SWPPP) and notify the department of all outfall changes within 30 days of the change. New outfalls require a new or updated registration statement including an updated SWPPP site map.
19. Notice of termination.
a. The owner may terminate coverage under this general permit by filing a complete notice of termination. The notice of termination may be filed after one or more of the following conditions have been met:
(1) Operations have ceased at the facility and there are no longer discharges of process wastewater, noncontact cooling water, or storm water associated with the industrial activity;
(2) A new owner has assumed responsibility for the facility (NOTE: A notice of termination does not have to be submitted if a VPDES Change of Ownership Agreement form has been submitted);
(3) All discharges associated with this facility have been covered by an individual VPDES permit or an alternative VPDES permit; or
(4) Termination of coverage is being requested for another reason, provided the board agrees that coverage under this general permit is no longer needed.
b. The notice of termination shall contain the following information:
(1) Owner's name, mailing address, telephone number, and email address (if available);
(2) Facility name and location;
(3) VPDES general permit registration number for the facility; and
(4) The basis for submitting the notice of termination, including:
(a) A statement indicating that a new owner has assumed responsibility for the facility;
(b) A statement indicating that operations have ceased at the facility, a closure plan has been implemented according to the O&M manual, and there are no longer discharges from the facility;
(c) A statement indicating that all discharges have been covered by an individual VPDES permit; or
(d) A statement indicating that termination of coverage is being requested for another reason (state the reason).
c. The following certification: "I certify under penalty of law that all concrete products waste water and storm water discharges from the identified facility that are authorized by this VPDES general permit have been eliminated, or covered under a VPDES individual or alternative permit, or that I am no longer the owner of the facility, or permit coverage should be terminated for another reason listed above. I understand that by submitting this notice of termination, that I am no longer authorized to discharge concrete products waste water or storm water in accordance with the general permit, and that discharging pollutants to surface waters is unlawful where the discharge is not authorized by a VPDES permit. I also understand that the submittal of this notice of termination does not release an owner from liability for any violations of this permit or the Clean Water Act."
d. The notice of termination shall be submitted to the department and signed in accordance with Part III K.
20. Temporary closure at inactive and unstaffed sites waiver.
a. When the permittee is unable to conduct effluent monitoring, benchmark monitoring, and/or storm water management requirements at an inactive and unstaffed site, a waiver of these requirements may be exercised by the board as long as the facility remains inactive and unstaffed and there are no industrial materials or activities exposed to storm water. The waiver request shall be submitted to the department for approval and shall include the information in the temporary closure plan specified in Part I B 9 a (4). If this waiver is granted, the permittee must retain a copy of the request and the board's written approval of the waiver in accordance with Part III B.
b. To reactivate the site the permittee must notify the department 30 days prior to reopening the facility and commencing any point source discharges of either treated process wastewater or storm water runoff associated with industrial activities. Upon this notification all effluent monitoring, benchmark monitoring, and/or storm water management requirement or requirements of this permit shall be required. This notification must be submitted to the department, signed in accordance with Part III K, and retained on site at the facility covered by this permit in accordance with Part III B.
21. The discharges authorized by this permit shall be controlled as necessary to meet applicable water quality standards.
22. Approval for coverage under this general permit does not relieve any owner of the responsibility to comply with any other federal, state, or local statute, ordinance, or regulation.
Part II
.
Storm Water Management.A. Monitoring instructions.
1. Collection and analysis of samples. Sampling requirements shall be assessed on an outfall by outfall basis. Samples shall be collected and analyzed in accordance with the requirements of Part III A.
2. When and how to sample. A minimum of one grab sample shall be taken resulting from a storm event that results in an actual discharge from the site (defined as a "measureable storm event"), providing the interval from the preceding measurable storm event is at least 72 hours. The 72-hour storm interval is waived if the permittee is able to document with the discharge monitoring report (DMR) that less than a 72-hour interval is representative for local storm events during the sampling period. The grab sample shall be taken during the first 30 minutes of the discharge. If it is not practicable to take the sample during the first 30 minutes, the sample may be taken during the first hour of discharge provide that the permittee explains with the DMR why a grab sample during the first 30 minutes was impractical.
A.3. Recording of results. For each discharge measurement or sample taken pursuant to the storm event monitoring requirements of this permit, the permittee shall record and report with the Discharge Monitoring Reports (DMRs) the following information:1. The datea. Date and duration (in hours) of the storm event(s) sampled;2. The rainfallb. Rainfall measurements or estimates (in inches) of the storm event which generated the sampled discharge; and3. The durationc. Duration between the storm event sampled and the end of the previous measurable(greater than 0.1 inch rainfall)storm event.B. Representative discharge.
WhenIf a facility has two or more exclusively storm water outfalls that discharge substantially identical effluents, based ona consideration of industrial activitysimilarities of the industrial activities, significant materials,and management practices and activities within the area drained by the outfall, the permittee reasonably believes discharge substantially identical effluent, the permittee may test the effluent of one of such outfalls and include with the DMRs an explanation that the quantitative data also applies to the substantially identical outfalls provided that the permittee includes a description of the location of the outfalls and explains in detail why the outfalls are expected to discharge substantially identical effluent. In addition, for each exclusively storm water outfall that the permittee believes is representative, an estimate of the size of the drainage area (in square feet) and an estimate of the runoff coefficient of the drainage area (e.g., low (under 40%), medium (40% to 65%) or high (above 65%)) shall be provided.size of drainage areas, and storm water management practices occurring within the drainage areas of the outfalls, the permittee may monitor the effluent of just one of the outfalls. Representative outfalls must be identified in the registration statement submitted for coverage under this permit. Substantially identical outfalls can apply to quarterly visual and benchmark monitoring. The permittee must include the following information in the storm water pollution prevention plan (SWPPP):1. The locations of the outfalls;
2. Why the outfalls are expected to discharge substantially identical effluents;
3. Estimates of the size of the drainage area (in square feet) for each of the outfalls; and
4. An estimate of the runoff coefficient of the drainage areas (low: under 40%; medium: 40% to 65%; high: above 65%).
C. Sampling
waiverwaivers.1. When a permittee is unable to
collect storm water samples required in Part I A or other applicable sections of this permit within a specified sampling periodconduct benchmark monitoring or visual examinations within the specified sampling period due to no "measureable" storm event or adverseclimaticweather conditions, the permittee shall collect a substitute sample fromathe next separate qualifying eventin the next periodand submit these data along withthe data for the routine sample in that perioddocumentation explaining a facility's inability to conduct benchmark monitoring or visual examinations (including dates and times the outfalls were viewed and sampling was attempted) of no "measureable" storm event or of adverse weather conditions with the DMR to the DEQ. Adverse weather conditions which may prohibit the collection of samples include weather conditions that create dangerous conditions for personnel (such as local flooding, high winds, hurricane, tornadoes, electrical storms, etc.)or otherwise make the collection of a sample impracticable (drought, extended frozen conditions, etc.). Acceptable documentation includes, but is not limited to National Climatic Data Center weather station data, local weather station data, facility rainfall logs, and other appropriate supporting data. All documentation shall also be maintained with the SWPPP.2. Sampling waiver for inactive and unstaffed sites. See Part I B 20.
D. Quarterly visual examination of storm water quality. The permittee shall perform and document a visual examination of a storm water discharge associated with industrial activity from each outfall, except discharges
exempted belowwaived in subdivision D 1 and subsection C of this section. The visual examination(s) must be made during daylight hours (e.g., normal working hours), at least once in each of the following three-month periods: January through March, April through June, July through September, and October through December.1. Examinations shall be made of samples collected within the first 30 minutes (or as soon thereafter as practical, but not to exceed one hour) of when the runoff or snowmelt begins discharging. The examination shall document observations of color, odor, clarity, floating solids, settled solids, suspended solids, foam, oil sheen, and other obvious indicators of storm water pollution. The examination must be conducted in a well lit area. No analytical tests are required to be performed on the samples. All such samples shall be collected from the discharge resulting from a storm event that
is greater than 0.1 inches in magnitude and that occurs at least 72 hours from the previous measurable (greater than 0.1 inch rainfall) storm eventresults in an actual discharge from the site (defined as a "measurable storm event") providing the interval from the preceding measurable storm event is at least 72 hours. The required 72-hour storm event interval is waived where the preceding measurable storm event did not result in a measurable discharge from the facility. Therequired72-hour storm event interval may also be waived where the permittee documents that less than a 72-hour interval is representative for local storm events during the season when sampling is being conducted. If no qualifying storm event resulted in discharge from the facility during a monitoring period, visual monitoring is exempted provided that the permitteedocumentdocuments that no qualifying storm event occurred that resulted in a storm water discharge during that quarter. Where practicable, the same individual should carry out the collection and examination of discharges for the entire permit term.2. Visual examination reports must be maintained onsite with the
pollution prevention planSWPPP. The report shall include the outfall location, the examination date and time, examination personnel, the nature of the discharge (i.e., runoff or snow melt), visual quality of the storm water discharge (including observations of color, odor, clarity, floating solids, settled solids, suspended solids, foam, oil sheen, and other obvious indicators of storm water pollution), visual quality of the receiving stream (including observations of solids deposition and oil sheen from the industrial activity) in the vicinity of the outfall (including ditches and conveyances) and probable sources of any observed storm water contamination.3. If the facility has two or more outfalls that, based on a consideration of industrial activity, significant materials, and management practices and activities within the area drained by the outfall, the permittee reasonably believes discharge substantially identical effluents, the permittee may collect a sample of effluent of one of such outfalls and report that the examination data also applies to the substantially identical outfall(s) provided that the permittee includes in the storm water pollution prevention plan a description of the location of the outfalls and explains in detail why the outfalls are expected to discharge substantially identical effluents. In addition, for each outfall that the permittee believes is representative, an estimate of the size of the drainage area (in square feet) and an estimate of the runoff coefficient of the drainage area (i.e., low (under 40%), medium (40 to 65%), or high (above 65%)) shall be provided in the plan.4. When the permittee is unable to conduct the visual examination due to adverse climatic conditions, the permittee must document the reason for not performing the visual examination and retain this documentation onsite with the records of the visual examinations. Adverse weather conditions that may prohibit the collection of samples include weather conditions that create dangerous conditions for personnel (such as local flooding, high winds, hurricane, tornadoes, electrical storms, etc.) or otherwise make the collection of a sample impracticable (drought, extended frozen conditions, etc.).E. Allowable nonstorm water discharges.
1. The following nonstorm water discharges are authorized by this permit provided the nonstorm water component of the discharge is in compliance with Part II E 2 below.
a. Discharges from fire fighting activities;
b. Fire hydrant flushings;
c. Potable water including water line flushings;
d. Uncontaminated air conditioning or compressor condensate;
e. Irrigation drainage;
f. Landscape watering provided all pesticides, herbicides, and fertilizer have been applied in accordance with manufacturer's instructions;
g. Pavement wash waters where no detergents are used and no spills or leaks of toxic or hazardous materials have occurred (unless all spilled material has been removed);
h. Routine external building wash down which does not use detergents;
i. Uncontaminated ground water or spring water;
j. Foundation or footing drains where flows are not contaminated with process materials
such as solventsand;k. Incidental windblown mist from cooling towers that collects on rooftops or adjacent portions of the facility, but NOT intentional discharges from the cooling tower (e.g., "piped" cooling tower blowdown or drains).
2. Except for flows from fire fighting activities, the
Storm Water Pollution Prevention PlanSWPPP must include:a. Identification of each allowable nonstorm water source;
b. The location where it is likely to be discharged; and
c. Descriptions of appropriate
BMPsbest management practices (BMPs) for each source.3. If mist blown from cooling towers is included as one of the allowable nonstorm water discharges, the
facility must specifically evaluate the potential for the discharges to be contaminated by chemicals used in the cooling tower. The permittee must determine that the levels of such chemicals in the discharges will not cause or contribute to a violation of an applicable water quality standard after implementation of the BMPs selected to control such discharges.permittee shall specifically evaluate the discharge for the presence of chemicals used in the cooling tower. This evaluation shall be included in the SWPPP.F. Releases of hazardous substances or oil in excess of reportable quantities. The discharge of hazardous substances or oil in the storm water discharge(s) from this facility shall be prevented or minimized in accordance with the
applicable storm water pollution prevention planSWPPP for the facility. This permit does not authorize the discharge of hazardous substances or oil resulting from an onsite spill. This permit does not relieve the permittee of the reporting requirements of 40 CFR Part 110, 40 CFR Part 117, and 40 CFR Part 302 or § 62.1-44.34:19 of the Code of Virginia.Where a release containing a hazardous substance or oil in an amount equal to or in excess of a reportable quantity established under either 40 CFR Part 110
(1998), 40 CFR Part 117(1998), or 40 CFR Part 302(1998)occurs during a 24-hour period, the;1. The permittee is required to notify the department in accordance with the requirements of Part III G as soon as he has knowledge of the discharge
.;2. Where a release enters a municipal separate storm sewer system (MS4), the permittee shall also notify the owner of the MS4
.; and3.
In addition, the storm water pollution prevention planThe SWPPP required by this permitmustshall be reviewed to identify measures to prevent the reoccurrence of such releases and to respond to such releases, and the plan must be modified where appropriate.This permit does not relieve the permittee of the reporting requirements of 40 CFR Part 110 (1998), 40 CFR Part 117 (1998) and 40 CFR Part 302 (1998) or § 62.1-44.34:19 of the Code of Virginia.G. Storm water pollution prevention plans (SWPPP).
A storm water pollution prevention plan is required to be developed for the facility. The plan shall be prepared in accordance with good engineering practices, and shall identify potential sources of pollution which may reasonably be expected to affect the quality of storm water discharges associated with industrial activity from the facility. In addition, the plan shall describe and ensure the implementation of practices which are to be used to reduce the pollutants in storm water discharges associated with industrial activity at the facility and to assure compliance with the terms and conditions of this permit. Permittees must implement the provisions of the storm water pollution prevention plan as a condition of this permit.A SWPPP shall be developed and implemented for the facility. The plan shall include BMPs that are reasonable, economically practicable, and appropriate in light of current industry practices. The BMPs shall be selected, designed, installed, implemented, and maintained in accordance with good engineering practices to eliminate or reduce the pollutants in all storm water discharges from the facility. The SWPPP shall also include any control measures necessary from the storm water discharges to meet applicable water quality standards.The
storm water pollution prevention planSWPPP requirements of this general permit may be fulfilled, in part, by incorporating by reference other plans or documents such as an erosion and sediment control plan, a spill prevention control and countermeasure (SPCC) plan developed for the facility under § 311 of the Clean Water Act orbest management practices (BMP)BMP programs otherwise required for the facility provided that the incorporated plan meets or exceeds the plan requirements of Part II G46 (Contents of Plan).If an erosion and sediment control plan is being incorporated by reference, it shall have been approved by the locality in which the activity is to occur or by another appropriate plan approving authority authorized under the Virginia Erosion and Sediment Control Regulation, 4VAC50-30.All plans incorporated by reference into thestorm water pollution prevention planSWPPP become enforceable under this permit. If a plan incorporated by reference does not contain all the requirements of Part II G 6, the permittee shall develop the missing SWPPP elements and include them in the required plan.1. Deadlines for plan preparation and compliance.
a. For a storm water discharge associated with industrial activity that is existing on or before the effective date of this permit, the storm water pollution prevention plan shall be prepared and implemented as expeditiously as practicable, but not later than 270 days from the date of coverage under this permit. For a facility that was covered by the previous permit, a storm water pollution prevention plan was required to be developed and implemented for that facility. Within 120 days after the date of coverage under this permit, the existing storm water pollution prevention plan shall be reviewed and modified, as appropriate, to conform to the requirements of this permit. The existing storm water pollution prevention plans shall continue to be implemented until a new plan, if required, is developed and implemented.b. The plan for any facility where industrial activity commences after the effective date of this permit, and except as provided elsewhere in this permit, shall be prepared, implemented and provide for compliance with the terms of the plan and this permit on or before the date of submission of a registration statement to be covered under this permit.c. In cases where construction is necessary to implement measures required by the plan, the plan shall contain a schedule that provides compliance with the plan as expeditiously as practicable, but no later than three years from the date of coverage under this permit. Where a construction compliance schedule is included in the plan, the schedule shall include appropriate nonstructural and/or temporary controls to be implemented in the affected portion(s) of the facility prior to completion of the permanent control measure.a. Owners of facilities that were covered under the 2008 Concrete Products General Permit who are continuing coverage under this general permit shall update and implement any revisions to the SWPPP not later than January 1, 2014.
b. Owners of new facilities, facilities previously covered by an expiring individual permit, and existing facilities not currently covered by a VPDES permit who elect to be covered under this general permit shall prepare and implement the SWPPP prior to commencing operations.
c. Where the owner of an existing facility that is covered by this permit changes, the new owner of the facility shall update and implement any revisions to the SWPPP within 60 days of the ownership change.
d. Upon a showing of good cause, the director may establish a later date in writing for the preparation and compliance with the SWPPP.
2. Signature and plan review.
a. The
planSWPPP shall be signed in accordance with Part III K, and be retained on-site at the facility covered by this permit in accordance with Part III B.b. The permittee shall make the
storm water pollution prevention planSWPPP, annual site compliance inspection report, or other information available to the department upon request.c. The director, or his designee, may notify the permittee in writing at any time that the
plan doesSWPPP, BMPs, or other components of the facility's storm water program do not meet one or more of theminimumrequirements of this part. Such notification shall identifythosespecific provisions of the permitwhichthat are not being metby the plan, and identify which provisions of the plan require modifications in order to meet the minimum requirements of this partand may include required modifications to the storm water program, additional monitoring requirements, and special reporting requirements. Within 60 days of such notification from the director, or as otherwise provided by the director, the permittee shall make the required changes to the plan and shall submit to the department a written certification that the requested changes have been made.3.
Keeping plans current. The permittee shall amend the plan whenever there is a change in design, construction, operation, or maintenance, which has a significant effect on the potential for the discharge of pollutants to surface waters of the state or if the storm water pollution prevention plan proves to be ineffective in eliminating or significantly minimizing pollutants from sources identified under Part II G 4 b of this permit, or in otherwise achieving the general objectives of controlling pollutants in storm water discharges associated with industrial activity.Maintaining an updated SWPPP. The permittee shall review and amend the SWPPP as appropriate whenever:a. There is construction or a change in design, operation, or maintenance that has a significant effect on the discharge or the potential for the discharge of pollutants to surface waters;
b. Routine inspections or compliance evaluations determine that there are deficiencies in the BMPs;
c. Inspections by local, state, or federal officials determine that modifications to the SWPPP are necessary;
d. There is a spill, leak, or other release at the facility; or
e. There is an unauthorized discharge from the facility.
4. SWPPP modifications shall be made within 30 calendar days after discovery, observation, or event requiring a SWPPP modification. Implementation of new or modified BMPs (distinct from regular preventive maintenance of existing BMPs described in Part II G 7) shall be initiated before the next storm event if possible, but no later than 60 days after discovery, or as otherwise provided or approved by the director. The amount of time taken to modify a BMP or implement additional BMPs shall be documented in the SWPPP.
5. If the SWPPP modification is based on a release or unauthorized discharge, include a description and date of the release, the circumstances leading to the release, actions taken in response to the release, and measures to prevent the recurrence of such releases. Unauthorized releases and discharges are subject to the reporting requirements of Part III G of this permit.
4.6. Contents of plan. The plan shall include, at a minimum, the following items:a. Pollution prevention team.
Each plan shall identify a specific individual or individuals within the facility organization as members of a storm water pollution prevention team that are responsible for developing the storm water pollution prevention plan and assisting the facility or plant manager in its implementation, maintenance, and revision. The plan shall clearly identify the responsibilities of each team member. The activities and responsibilities of the team shall address all aspects of the facility's storm water pollution prevention plan.Each plan shall identify the staff individuals by name or title that comprise the facility's storm water pollution prevention team. The pollution prevention team is responsible for assisting the facility or plant manager in developing, implementing, maintaining, revising, and ensuring compliance with the facility's SWPPP. Specific responsibilities of each staff individual on the team shall be identified and listed.b.
DescriptionSummary of potential pollutant sources.Each plan shall provide a description of potential sources which may reasonably be expected to add significant amounts of pollutants to storm water discharges or which may result in the discharge of pollutants during dry weather from separate storm sewers draining the facility. Each plan shall identify all activities and significant materials which may potentially be significant pollutant sources. Each plan shall include, at a minimum:The plan shall identify where industrial materials or activities at the facility are exposed to storm water. Industrial materials or activities include, but are not limited to: material handling equipment or activities, industrial machinery, raw materials, industrial production and processes, intermediate products, byproducts, final products, and waste products. Material handling activities include, but are not limited to: the storage, loading and unloading, transportation, disposal, or conveyance of any raw material, intermediate product, final product, or waste product. The description shall include:(1) A list of the activities (e.g., material storage, equipment fueling and cleaning, cutting steel beams); and
(2) A list of the associated pollutant(s) or pollutant constituents (e.g., crankcase oil, zinc, sulfuric acid, cleaning solvents, etc.) for each activity. The pollutant list shall include all significant materials handled, treated, stored or disposed that have been exposed to storm water in the three years prior to the date this SWPPP was prepared or amended. This list shall include any hazardous substances or oil at the facility.
(1) Drainage. A site map indicating anc. Site map. The site map shall document:(1) An outline of the
portions of thedrainage area of each storm water outfall that are within the facility boundaries, each;(2) Each existing structural control measure to reduce pollutants in storm water runoff
, surface;(3) Surface water bodies
, locations;(4) Locations where
significantmaterials are exposed to precipitation, locations;(5) Locations where major spills or leaks identified under Part
II G 4 b (3)II G 6 d have occurred, and the locations;(6) Locations of
the following activities:fueling stations;, vehicleandor equipmentmaintenance and/or cleaning areas;degreasing activities, maintenance areas,loading/unloadingloading or unloading areas;, vehicle wash down areas, vehicle wash out areas, bag house or other dust control device,recycle/sedimentation pondrecycle ponds, sedimentation ponds,clarifier or other deviceor clarifiers or other devices used for the treatment of process wastewater,(and the areas that drain to the treatment device), locations;(7) Locations used for the storage or disposal of wastes; liquid storage tanks; processing areas; and storage areas
. The map must indicate the outfall;(8) Outfall locations, designation (e.g., 001) and the types of discharges contained in the drainage areas of the outfalls;
and for(9) For each area of the facility that generates storm water discharges associated with industrial activity with a
reasonablepotential for containing significant amounts of pollutants,a prediction of the direction oflocations of storm water conveyances including ditches, pipes, swales, and inlets, and the directions of storm water flow,and an identification of the types of pollutants which are likely to be present in storm water discharges associated with industrial activity. Factors to consider include the toxicity of the chemicals; quantity of chemicals used, produced or discharged; the likelihood of contact with storm water; and history ofsignificantleaks or spills of toxic or hazardous pollutants.; and(10) Flows with a
significantpotential for causing erosion shall be identified.(2) Inventory of exposed materials. An inventory of the types of materials handled at the site that potentially may be exposed to precipitation. Such inventory shall include a narrative description of significant materials that have been handled, treated, stored or disposed in a manner to allow exposure to storm water between the time of three years prior to the date of coverage under this general permit and the present; method and location of on-site storage or disposal; materials management practices employed to minimize contact of materials with storm water runoff between the time of three years prior to the date of coverage under this general permit and the present; the location and a description of existing structural and nonstructural control measures to reduce pollutants in storm water runoff; and a description of any treatment the storm water receives.(3)d. Spills and leaks. A list of significant spills andsignificantleaks of toxic or hazardous pollutants that occurred at areas that are exposed to precipitation or that otherwise drain to a storm water conveyance at the facility after the date of three years prior to the date of coverage under this general permit. Such list shall be updated as appropriate during the term of the permit.(4)e. Sampling data.AThe plan shall include a summary of existing storm water discharge sampling datadescribing pollutants in storm water discharges fromtaken at the facility, including a. The summaryof samplingshall include, at a minimum, any data collected during theterm of this permitprevious three years.(5) Risk identification and summary of potential pollutant sources. A narrative description of the potential pollutant sources from the following activities: loading and unloading operations; outdoor storage activities; outdoor manufacturing or processing activities; significant dust or particulate generating processes; and on-site waste disposal practices. The description shall specifically list any significant potential source of pollutants at the site and for each potential source, any pollutant or pollutant parameter (e.g., biochemical oxygen demand, etc.) of concern shall be identified.c. Measures andf. Storm water controls.Each facility covered by this permit shall develop a description of storm water management controls appropriate for the facility, and implement such controls. The appropriateness and priorities of controls in a plan shall reflect identified potential sources of pollutants at the facility. The description of storm water management controls shall address the following minimum components, including a schedule for implementing such controls:(1) BMPs shall be implemented for all areas identified in Part II G 6 b to prevent or control pollutants in storm water discharges from the facility. All reasonable steps shall be taken to control or address the quality of discharges from the site that may not originate at the facility. The SWPPP shall describe the type, location, and implementation of all BMPs for each area where industrial materials or activities are exposed to storm water.
(1)(2) Good housekeeping. Good housekeeping requires the clean and orderly maintenance of areas that may contribute pollutants to storm waters discharges. The permittee shall keep clean all exposed areas of the facility that are potential sources of pollutants in storm water. Particular attention should be paid to areas where raw materials are stockpiled, material handling areas, storage areas, liquid storage tanks, vehicle fueling and maintenance areas, and loading/unloading areas. The plan shall describe procedures performed to minimize the discharge of: spilled cement, aggregate (including sand and gravel), kiln dust, fly ash, settled dust, or other significant material in storm water from paved portions of the site that are exposed to storm water. Regular sweeping of impervious areas or other equivalent measures to minimize the presence of these materials shall be employed. The frequency of sweeping or equivalent measures shall be specified in the plan based upon a consideration of the amount of industrial activity occurring in the areas and the frequency of precipitation, but it shall be a minimum of once a week if cement, aggregate, kiln dust, fly ash or settled dust are being handled/processed.Where practicable, effortsEfforts must be made to prevent the exposure of fine granular solids (cement, fly ash, etc.) to storm water by storing these materials in enclosed silos/hoppers, buildings or under other covering. The introduction of raw, final, or waste materials to exposed areas of the facility shall be minimized to the maximum extent practicable. The generation of dust, along with off-site vehicle tracking of raw, final or waste materials, or sediments, shall be minimized to the maximum extent practicable.(2)(3) Preventive maintenance. A preventive maintenance program shall involvetimely inspection and maintenance of storm water management devices (e.g., cleaning oil/water separators, catch basins) inspecting and testing facilityregular inspection, testing, maintenance, and repairing of all industrial equipment and systems touncover conditions that could causeavoid breakdowns or failuresresulting in discharges of pollutants to surface waters, and appropriate maintenance of such equipment and systems.that could result in leaks, spills and other releases. This program is in addition to the specific BMP maintenance required under Part II G 7 (Maintenance of BMPs).(3)(4) Spill prevention and response procedures.Areas where potential spills which can contribute pollutants to storm water discharges can occur, and their accompanying drainage points shall be identified clearly in the storm water pollution prevention plan. Where appropriate, specifying material handling procedures, storage requirements, and use of equipment such as diversion valves in the plan should be considered. Procedures for cleaning up spills shall be identified in the plan and made available to the appropriate personnel. The necessary equipment to implement a clean up should be available to personnel.The plan shall describe the procedures that will be followed for preventing and responding to spills and leaks.(a) Preventive measures include barriers between material storage and traffic areas, secondary containment provisions, and procedures for material storage and handling.
(b) Response procedures shall include (i) notification of appropriate facility personnel, emergency agencies, and regulatory agencies and (ii) procedures for stopping, containing, and cleaning up spills. Measures for cleaning up hazardous material spills or leaks shall be consistent with applicable RCRA regulations at 40 CFR Part 264 and 40 CFR Part 265. Employees who may cause, detect, or respond to a spill or leak shall be trained in these procedures and have necessary spill response equipment available. If possible, one of these individuals shall be a member of the pollution prevention team.
(c) Contact information for individuals and agencies that must be notified in the event of a spill shall be included in the SWPPP and in other locations where it will be readily available.
(4)(5) Routine facility inspections. Facility personnel whoare familiar with the industrial activity, the BMPs and the storm water pollution prevention plan shall be identified topossess the knowledge and skills to assess conditions and activities that could impact storm water quality at the facility and who can also evaluate the effectiveness of BMPs shall regularly inspect designated equipment and areas of the facility. Inspections shall be conducted while the facility is in operation and include, but are not limited to, the following areas exposed to storm water: material handling areas, above ground storage tanks, hoppers or silos, dust collection/containment systems, and truck wash down/equipment cleaning areas. The inspection frequency shall be specified in the plan based on a consideration of the level of industrial activity at the facility, but it shall be a minimum of quarterly unless more frequent intervals are specified elsewhere in the permit. When practical, the routine facility inspection should be conducted once each calendar year during a period when a storm water discharge is occurring. A set of tracking or followup procedures shall be used to ensure that appropriate actions are taken in response to the inspections. Records of inspections shall be maintained with the pollution prevention plan. These inspections are in addition to, or as part of, the comprehensive site compliance evaluation required under Part II G 8. At least one member of the pollution prevention team shall participate in the routine facility inspections.Any deficiencies in the implementation of the SWPPP that are found shall be corrected as soon as practicable, but not later than within 30 days of the inspection, unless permission for a later date is granted in writing by the director. The results of the inspections shall be documented in the SWPPP, along with the date(s) and description(s) of any corrective actions that were taken in response to any deficiencies or opportunities for improvement that were identified.
(5)(6) Employee training.Employee training programs shall inform personnel responsible for implementing activities identified in the storm water pollution prevention plan or otherwise responsible for storm water management at all levels of responsibility of the components and goals of the storm water pollution prevention plan. Training should address topics such as spill response, good housekeeping and material management practices. A pollution prevention plan shall identify periodic dates for such training.The permittee shall implement a storm water employee training program for the facility. The SWPPP shall include a schedule for all types of necessary training, and shall document all training sessions and the employees who received the training. Training shall be provided for all employees who work in areas where industrial materials or activities are exposed to storm water and for employees who are responsible for implementing activities identified in the SWPPP (e.g., inspectors, maintenance personnel, etc.). The training shall cover the components and goals of the SWPPP and include such topics as spill response, good housekeeping, material management practices, BMP operation and maintenance, etc. The SWPPP shall include a summary of any training performed.(6) Recordkeeping and internal reporting procedures. A description of incidents such as spills, or other discharges, along with other information describing the quality and quantity of storm water discharges shall be included in the plan. Inspections and maintenance activities shall be documented and records of such activities shall be incorporated into the plan.(7) Sediment and erosion control. The plan shall identify areas
which,that, due to topography,activities,land disturbance (e.g., construction, landscaping, sit grading), or other factors, have ahighpotential forsignificantsoil erosion, and. The permittee shall identify and implement structural, vegetative, and/or stabilizationmeasures to be used to limit erosion.BMPs to prevent or control on-site and off-site erosion and sedimentation.(8) Management of runoff. The plan shall
contain a narrative consideration of the appropriateness of traditionaldescribe the storm water run-off management practices(practices other than those which control the generation or source(s) of pollutants)(i.e., permanent structural BMPs) for the facility. These types of BMPs are typically used to divert, infiltrate, reuse, or otherwisemanage storm water runoff in a manner that reducesreduce pollutants in storm water discharges from the site.The plan shall provide that measures that the permittee determines to be reasonable and appropriate shall be implemented and maintained. The potential of various sources at the facility to contribute pollutants to storm water discharges associated with industrial activity shall be considered when determining reasonable and appropriate measures.Appropriate measures may include: vegetative swales and practices, reuse of collected storm water (such as for a process or as an irrigation source), inlet controls (such as oil/water separators), snow management activities, infiltration devices, wet detention/retention devices; or other equivalent measures. Some structural BMPs may require a separate permit under § 404 of the Clean Water Act and the Virginia Water Protection Permit Program Regulation (9VAC25-210) before installation begins.7. Maintenance of BMPs. All BMPs identified in the SWPPP shall be maintained in effective operating condition. Storm water BMPs identified in the SWPPP should be observed during active operation where feasible (i.e., during a storm water runoff event) to ensure that they are functioning correctly. Where discharge locations are inaccessible, nearby downstream locations shall be observed. The observations shall be documented in the SWPPP.
The SWPPP shall include a description of procedures and a regular schedule for preventive maintenance of all BMPs and shall include a description of the back-up practices that are in place should a runoff event occur while a BMP is off line. The effectiveness of nonstructural BMPs shall also be maintained by appropriate means (e.g., spill response supplies available and personnel trained, etc.).
If site inspections required by Part II G 6 f (5) (Routine facility inspections) or Part II G 8 (Comprehensive site compliance evaluation) identify BMPs that are not operating effectively, repairs or maintenance shall be performed before the next anticipated storm event. If maintenance prior to the next anticipated storm event is not possible, maintenance shall be scheduled and accomplished as soon as practicable. In the interim, back-up measures shall be employed and documented in the SWPPP until repairs or maintenance is complete. Documentation shall be kept with the SWPPP of maintenance and repairs of BMPs, including the date(s) of regular maintenance, date(s) of discovery of areas in need of repair or replacement, and for repairs, date(s) that the BMP(s) returned to full function, and the justification for any extended maintenance or repair schedules.
d.8. Comprehensive site compliance evaluation.Qualified facility personnel who are familiar with the industrial activity, the BMPs and the storm water pollution prevention plan shall conduct site compliance evaluations at appropriate intervals specified in the plan, but, in no case less than once a year.The permittee shall conduct comprehensive site compliance evaluations at least once a year. The evaluations shall be done by qualified personnel who possess the knowledge and skills to assess conditions and activities that could impact storm water quality at the facility and who can also evaluate the effectiveness of BMPs. The personnel conducting the evaluations may be either facility employees or outside constituents hired by the facility. Such evaluations shall include the following:(1) Areas contributing to a storm water discharge associated with industrial activity shall be visually inspected for evidence of, or the potential for, pollutants entering the drainage system. Measures to reduce pollutant loadings shall be evaluated to determine whether they are adequate and properly implemented in accordance with the terms of the permit or whether additional control measures are needed. Structural storm water management measures, sediment and erosion control measures, and other structural pollution prevention measures identified in the plan shall be observed to ensure that they are operating correctly. A visual inspection of equipment needed to implement the plan, such as spill response equipment, shall be made.a. Industrial materials, residue or trash that may have or could come into contact with storm water;
b. Leaks or spills from industrial equipment, drums, barrels, tanks, or other containers that have occurred within the past three years;
c. Off-site tracking of industrial or waste materials or sediment where vehicles enter or exit the site;
d. Evidence of or the potential for pollutants entering the drainage system;
e. Evidence of pollutants discharging to surface waters at all facility outfalls and the condition of and around the outfall, including flow dissipation measures to prevent scouring;
f. Review of training performed, inspections completed, maintenance performed, quarterly visual examinations, and effective operation of BMPs;
g. Documentation that all outfalls have been evaluated annually for the presence of unauthorized discharges (i.e., discharges other than storm water; the authorized nonstorm water discharges described in Part II E; or discharges covered under a separate VPDES permit, other than this permit). The documentation shall include:
(1) The date of the evaluation;
(2) A description of the evaluation criteria used;
(3) A list of the outfalls or on-site drainage points that were directly observed during the evaluation;
(4) A description of the results of the evaluation for the presence of unauthorized discharges; and
(5) The actions taken to eliminate unauthorized discharges, if any were identified (i.e., a floor drain was sealed, a sink drain was rerouted to sanitary, or a VPDES permit application was submitted for a cooling water discharge);
h. Results of both visual and any analytical monitoring done during the past year shall be taken into consideration during the evaluation;
(2)i. Based on the results of the evaluation,the description of potential pollutant sources identified in the plan in accordance with Part II G 4 b and pollution prevention measures and controls identified in the plan in accordance with Part II G 4 c shall be revised as appropriate within two weeks of such evaluation and shall provide for implementation of any changes to the plan in a timely manner, but in no case more than 12 weeks after the evaluation.the SWPPP shall be modified as necessary (e.g., show additional controls on the site map required by Part II G 6 c; revise the description of storm water controls required by Part II G 6 f to include additional or modified BMPs designed to correct problems identified). Revisions to the SWPPP shall be completed within 30 days following the evaluation, unless permission for a later date is granted in writing by the director. If existing BMPs need to be modified or if additional BMPs are necessary, implementation shall be completed before the next anticipated storm event, if practicable, but not more than 60 days after completion of the comprehensive site evaluation, unless permission for a later date is granted in writing by the department;(3)j. Compliance evaluation report. A report shall be written summarizing the scope of theinspectionevaluation, names(s) of personnel making theinspectionevaluation, thedate(s)date of theinspection, majorevaluation, and all observations relating to the implementation of thestorm water pollution prevention planSWPPP,and actions taken in accordance with Part II G 4 d shall be made and retained as part of the storm water pollution prevention plan as required in Part III B.including elements stipulated in Part II G 8 a through e above. Observations shall include such things as: the location(s) of discharges of pollutants from the site; locations(s) of previously unidentified sources of pollutants; location(s) of BMPs that need to be maintained or repaired; locations(s) of failed BMPs that need replacement; and location(s) where additional BMPs are needed. The report shall identify any incidents of noncompliance that were observed. Where a report does not identify any incidents of noncompliance, the report shall contain a certification that the facility is in compliance with thestorm water pollution prevention planSWPPP and this permit. The report shall be signed in accordance with Part III K.and maintained with the SWPPP; and(4)k. Where compliance evaluation schedules overlap with routine inspections required under Part II G4 c (4)6 f (5), the annual compliance evaluation may beconducted in place of one such inspectionused as one of the routine inspections.5. Special pollution prevention plan requirements:a. Additional requirements for storm water discharges associated with industrial activity from facilities subject to § 313 of the Emergency Planning and Community Right-to-Know Act of 1986 (EPCRA) reporting requirements. Potential pollutant sources for which the facility has reporting requirements under EPCRA 313 must be identified in the summary of potential pollutant sources as per Part II G 4 b.b. Additional requirements for salt storage. Storage piles of salt used for deicing or other commercial or industrial purposes must be enclosed or covered to prevent exposure to precipitation (except for exposure resulting from adding or removing materials from the pile). Piles do not need to be enclosed or covered where storm water from the pile is not discharged to surface waters or the discharges from the piles are authorized under another permit.Part III
.
Conditions Applicable To All VPDES Permits.A. Monitoring.
1. Samples and measurements taken as required by this permit shall be representative of the monitored activity.
2. Monitoring shall be conducted according to procedures approved under 40 CFR Part 136 or alternative methods approved by the U.S. Environmental Protection Agency unless other procedures have been specified in this permit.
3. The permittee shall periodically calibrate and perform maintenance procedures on all monitoring and analytical instrumentation at intervals that will ensure accuracy of measurements.
4. Samples taken as required by this permit shall be analyzed in accordance with 1VAC30-45 (Certification for Noncommercial Environmental Laboratories) or 1VAC30-46 (Accreditation for Commercial Environmental Laboratories).
B. Records.
1. Records of monitoring information shall include:
a. The date, exact place, and time of sampling or measurements;
b. The individuals who performed the sampling or measurements;
c. The dates and times analyses were performed;
d. The individuals who performed the analyses;
e. The analytical techniques or methods used; and
f. The results of such analyses.
2. Except for records of monitoring information required by this permit related to the permittee's sewage sludge use and disposal activities, which shall be retained for a period of at least five years, the permittee shall retain (i) records of all monitoring information including all calibration and maintenance records and all original strip chart recordings for continuous monitoring instrumentation, (ii) copies of all reports required by this permit, and (iii) records of all data used to complete the registration statement for this permit for a period of at least three years from the date
of the sample, measurement, report or request for coveragethat coverage under this permit expires or is terminated. This period of retention shall be extended automatically during the course of any unresolved litigation regarding the regulated activity or regarding control standards applicable to the permittee, or as requested by the board.C. Reporting monitoring results.
1. The permittee shall submit the results of the monitoring required by this permit not later than the 10th day of the month after monitoring takes place, unless another reporting schedule is specified elsewhere in this permit. Monitoring results shall be submitted to the department's regional office.
2. Monitoring results shall be reported on a Discharge Monitoring Report (DMR) or on forms provided, approved or specified by the department.
3. If the permittee monitors any pollutant specifically addressed by this permit more frequently than required by this permit using test procedures approved under 40 CFR Part 136 or using other test procedures approved by the U.S. Environmental Protection Agency or using procedures specified in this permit, the results of this monitoring shall be included in the calculation and reporting of the data submitted in the DMR or reporting form specified by the department.
4. Calculations for all limitations which require averaging of measurements shall utilize an arithmetic mean unless otherwise specified in this permit.
D. Duty to provide information. The permittee shall furnish to the department, within a reasonable time, any information which the board may request to determine whether cause exists for modifying, revoking and reissuing, or terminating coverage under this permit or to determine compliance with this permit. The board may require the permittee to furnish, upon request, such plans, specifications, and other pertinent information as may be necessary to determine the effect of the wastes from
hisits discharge on the quality of state waters, or such other information as may be necessary to accomplish the purposes of the State Water Control Law. The permittee shall also furnish to the department upon request copies of records required to be kept by this permit.E. Compliance schedule reports. Reports of compliance or noncompliance with, or any progress reports on, interim and final requirements contained in any compliance schedule of this permit shall be submitted no later than 14 days following each schedule date.
F. Unauthorized discharges. Except in compliance with this permit, or another permit issued by the board, it shall be unlawful for any person to:
1. Discharge into state waters sewage, industrial wastes, other wastes, or any noxious or deleterious substances; or
2. Otherwise alter the physical, chemical or biological properties of such state waters and make them detrimental to the public health, or to animal or aquatic life, or to the use of such waters for domestic or industrial consumption, for recreation, or for other uses.
G. Reports of unauthorized discharges. Any permittee who discharges or causes or allows a discharge of sewage, industrial waste, other wastes or any noxious or deleterious substance into or upon state waters in violation of Part III F; or who discharges or causes or allows a discharge that may reasonably be expected to enter state waters in violation of Part III F, shall notify the department of the discharge immediately upon discovery of the discharge, but in no case later than 24 hours after said discovery. A written report of the unauthorized discharge shall be submitted to the department, within five days of discovery of the discharge. The written report shall contain:
1. A description of the nature and location of the discharge;
2. The cause of the discharge;
3. The date on which the discharge occurred;
4. The length of time that the discharge continued;
5. The volume of the discharge;
6. If the discharge is continuing, how long it is expected to continue;
7. If the discharge is continuing, what the expected total volume of the discharge will be; and
8. Any steps planned or taken to reduce, eliminate and prevent a recurrence of the present discharge or any future discharges not authorized by this permit.
Discharges reportable to the department under the immediate reporting requirements of other regulations are exempted from this requirement.
H. Reports of unusual or extraordinary discharges. If any unusual or extraordinary discharge including a bypass or upset should occur from a treatment works and the discharge enters or could be expected to enter state waters, the permittee shall promptly notify, in no case later than 24 hours, the department by telephone after the discovery of the discharge. This notification shall provide all available details of the incident, including any adverse affects on aquatic life and the known number of fish killed. The permittee shall reduce the report to writing and shall submit it to the department within five days of discovery of the discharge in accordance with Part III I 2. Unusual and extraordinary discharges include but are not limited to any discharge resulting from:
1. Unusual spillage of materials resulting directly or indirectly from processing operations;
2. Breakdown of processing or accessory equipment;
3. Failure or taking out of service some or all of the treatment works; and
4. Flooding or other acts of nature.
I. Reports of noncompliance. The permittee shall report any noncompliance which may adversely affect state waters or may endanger public health.
1. An oral report shall be provided within 24 hours from the time the permittee becomes aware of the circumstances. The following shall be included as information which shall be reported within 24 hours under this subdivision:
a. Any unanticipated bypass; and
b. Any upset which causes a discharge to surface waters.
2. A written report shall be submitted within five days and shall contain:
a. A description of the noncompliance and its cause;
b. The period of noncompliance, including exact dates and times, and if the noncompliance has not been corrected, the anticipated time it is expected to continue; and
c. Steps taken or planned to reduce, eliminate, and prevent reoccurrence of the noncompliance.
The board may waive the written report on a case-by-case basis for reports of noncompliance under Part III I if the oral report has been received within 24 hours and no adverse impact on state waters has been reported.
3. The permittee shall report all instances of noncompliance not reported under Parts III I 1 or 2, in writing, at the time the next monitoring reports are submitted. The reports shall contain the information listed in Part III I 2.
NOTE: The immediate (within 24 hours) reports required in Parts III G, H and I may be made to the department's regional office by telephone
or by fax, FAX, or online at http://www.deq.virginia.gov/Programs/PollutionResponsePreparedness/MakingaReport.aspx. For reports outside normal working hours, leave a message and this shall fulfill the immediate reporting requirement. For emergencies, the Virginia Department of Emergency Services maintains a 24 hour telephone service at 1-800-468-8892.J. Notice of planned changes.
1. The permittee shall give notice to the department as soon as possible of any planned physical alterations or additions to the permitted facility. Notice is required only when:
a. The permittee plans alteration or addition to any building, structure, facility, or installation from which there is or may be a discharge of pollutants, the construction of which commenced:
(1) After promulgation of standards of performance under § 306 of Clean Water Act which are applicable to such source; or
(2) After proposal of standards of performance in accordance with § 306 of Clean Water Act which are applicable to such source, but only if the standards are promulgated in accordance with § 306 within 120 days of their proposal;
b. The alteration or addition could significantly change the nature or increase the quantity of pollutants discharged. This notification applies to pollutants which are subject neither to effluent limitations nor to notification requirements specified elsewhere in this permit; or
c. The alteration or addition results in a significant change in the permittee's sludge use or disposal practices, and such alteration, addition, or change may justify the application of permit conditions that are different from or absent in the existing permit, including notification of additional use or disposal sites not reported during the permit application process or not reported pursuant to an approved land application plan.
2. The permittee shall give advance notice to the department of any planned changes in the permitted facility or activity which may result in noncompliance with permit requirements.
K. Signatory requirements.
1. Registration statements. All registration statements shall be signed as follows:
a. For a corporation: by a responsible corporate officer. For the purpose of this section, a responsible corporate officer means (i) president, secretary, treasurer, or vice-president of the corporation in charge of a principal business function, or any other person who performs similar policy- or decision-making functions for the corporation or (ii) the manager of one or more manufacturing, production, or operating facilities provided the manager is authorized to make management decisions that govern the operation of the regulated facility including having the explicit or implicit duty of making major capital investment recommendations, and initiating and directing other comprehensive measures to assure long-term environmental compliance with environmental laws and regulations; the manager can ensure that the necessary systems are established or actions taken to gather complete and accurate information for permit application requirements; and where
ifauthority to sign documents has been assigned or delegated to the manager in accordance with corporate procedures;b. For a partnership or sole proprietorship: by a general partner or the proprietor, respectively; or
c. For a municipality, state, federal, or other public agency: by either a principal executive officer or ranking elected official. For purposes of this section, a principal executive officer of a public agency includes (i) the chief executive officer of the agency or (ii) a senior executive officer having responsibility for the overall operations of a principal geographic unit of the agency.
2. Reports, etc. All reports required by permits, and other information requested by the board shall be signed by a person described in Part III K 1, or by a duly authorized representative of that person. A person is a duly authorized representative only if:
a. The authorization is made in writing by a person described in Part III K 1;
b. The authorization specifies either an individual or a position having responsibility for the overall operation of the regulated facility or activity such as the position of plant manager, operator of a well or a well field, superintendent, position of equivalent responsibility, or an individual or position having overall responsibility for environmental matters for the company. A duly authorized representative may thus be either a named individual or any individual occupying a named position; and
c. The written authorization is submitted to the department.
3. Changes to authorization. If an authorization under Part III K 2 is no longer accurate because a different individual or position has responsibility for the overall operation of the facility, a new authorization satisfying the requirements of Part III K 2 shall be submitted to the department prior to or together with any reports, or information to be signed by an authorized representative.
4. Certification. Any person signing a document under Parts III K 1 or 2 shall make the following certification:
"I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."
L. Duty to comply. The permittee shall comply with all conditions of this permit. Any permit noncompliance constitutes a violation of the State Water Control Law and the Clean Water Act, except that noncompliance with certain provisions of this permit may constitute a violation of the State Water Control Law but not the Clean Water Act. Permit noncompliance is grounds for enforcement action; for permit termination, revocation and reissuance, or modification; or denial of a permit renewal application.
The permittee shall comply with effluent standards or prohibitions established under § 307(a) of the Clean Water Act for toxic pollutants and with standards for sewage sludge use or disposal established under § 405(d) of the Clean Water Act within the time provided in the regulations that establish these standards or prohibitions or standards for sewage sludge use or disposal, even if this permit has not yet been modified to incorporate the requirement.
M. Duty to reapply. If the permittee wishes to continue an activity regulated by this permit after the expiration date of this permit, the permittee shall apply for and obtain a new permit. All permittees with a currently effective permit shall submit a new application at least
18090 days before the expiration date of the existing permit, unless permission for a later date has been granted by the board. The board shall not grant permission for applications to be submitted later than the expiration date of the existing permit.N. Effect of a permit. This permit does not convey any property rights in either real or personal property or any exclusive privileges, nor does it authorize any injury to private property or invasion of personal rights, or any infringement of federal, state or local law or regulations.
O. State law. Nothing in this permit shall be construed to preclude the institution of any legal action under, or relieve the permittee from any responsibilities, liabilities, or penalties established pursuant to any other state law or regulation or under authority preserved by § 510 of the Clean Water Act. Except as provided in permit conditions on "bypassing" (Part III U), and "upset" (Part III V) nothing in this permit shall be construed to relieve the permittee from civil and criminal penalties for noncompliance.
P. Oil and hazardous substance liability. Nothing in this permit shall be construed to preclude the institution of any legal action or relieve the permittee from any responsibilities, liabilities, or penalties to which the permittee is or may be subject under §§ 62.1-44.34:14 through 62.1-44.34:23 of the State Water Control Law.
Q. Proper operation and maintenance. The permittee shall at all times properly operate and maintain all facilities and systems of treatment and control (and related appurtenances) which are installed or used by the permittee to achieve compliance with the conditions of this permit. Proper operation and maintenance also includes effective plant performance, adequate funding, adequate staffing, and adequate laboratory and process controls, including appropriate quality assurance procedures. This provision requires the operation of back-up or auxiliary facilities or similar systems which are installed by the permittee only when the operation is necessary to achieve compliance with the conditions of this permit.
R. Disposal of solids or sludges. Solids, sludges or other pollutants removed in the course of treatment or management of pollutants shall be disposed of in a manner so as to prevent any pollutant from such materials from entering state waters.
S. Duty to mitigate. The permittee shall take all reasonable steps to minimize or prevent any discharge or sludge use or disposal in violation of this permit which has a reasonable likelihood of adversely affecting human health or the environment.
T. Need to halt or reduce activity not a defense. It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the permitted activity in order to maintain compliance with the conditions of this permit.
U. Bypass.
1. "Bypass" means the intentional diversion of waste streams from any portion of a treatment facility. The permittee may allow any bypass to occur which does not cause effluent limitations to be exceeded, but only if it also is for essential maintenance to assure efficient operation. These bypasses are not subject to the provisions of Parts III U 2 and U 3.
2. Notice.
a. Anticipated bypass. If the permittee knows in advance of the need for a bypass, prior notice shall be submitted, if possible at least 10 days before the date of the bypass.
b. Unanticipated bypass. The permittee shall submit notice of an unanticipated bypass as required in Part III I.
3. Prohibition of bypass.
a. Bypass is prohibited, and the board may take enforcement action against a permittee for bypass, unless:
(1) Bypass was unavoidable to prevent loss of life, personal injury, or severe property damage;
(2) There were no feasible alternatives to the bypass, such as the use of auxiliary treatment facilities, retention of untreated wastes, or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate back-up equipment should have been installed in the exercise of reasonable engineering judgment to prevent a bypass which occurred during normal periods of equipment downtime or preventive maintenance; and
(3) The permittee submitted notices as required under Part III U 2.
b. The board may approve an anticipated bypass, after considering its adverse effects, if the board determines that it will meet the three conditions listed above in Part III U 3 a.
V. Upset.
1. An upset constitutes an affirmative defense to an action brought for noncompliance with technology based permit effluent limitations if the requirements of Part III V 2 are met. A determination made during administrative review of claims that noncompliance was caused by upset, and before an action for noncompliance, is not a final administrative action subject to judicial review.
2. A permittee who wishes to establish the affirmative defense of upset shall demonstrate, through properly signed, contemporaneous operating logs, or other relevant evidence that:
a. An upset occurred and that the permittee can identify the causes of the upset;
b. The permitted facility was at the time being properly operated;
c. The permittee submitted notice of the upset as required in Part III I; and
d. The permittee complied with any remedial measures required under Part III S.
3. In any enforcement proceeding the permittee seeking to establish the occurrence of an upset has the burden of proof.
W. Inspection and entry. The permittee shall allow the director, or his designee, upon presentation of credentials and other documents as may be required by law, to:
1. Enter upon the permittee's premises where a regulated facility or activity is located or conducted, or where records must be kept under the conditions of this permit;
2. Have access to and copy at reasonable times any records that must be kept under the conditions of this permit;
3. Inspect at reasonable times any facilities, equipment (including monitoring and control equipment), practices, or operations regulated or required under this permit; and
4. Sample or monitor at reasonable times, for the purposes of assuring permit compliance or as otherwise authorized by the Clean Water Act and the State Water Control Law, any substances or parameters at any location.
For purposes of this section, the time for inspection shall be deemed reasonable during regular business hours, and whenever the facility is discharging. Nothing contained herein shall make an inspection unreasonable during an emergency.
X. Permit actions. Permits may be modified, revoked and reissued, or terminated for cause. The filing of a request by the permittee for a permit modification, revocation and reissuance, or termination, or a notification of planned changes or anticipated noncompliance does not stay any permit condition.
Y. Transfer of permits.
1. Permits are not transferable to any person except after notice to the department. Except as provided in Part III Y 2, a permit may be transferred by the permittee to a new owner or operator only if the permit has been modified or revoked and reissued, or a minor modification made, to identify the new permittee and incorporate such other requirements as may be necessary under the State Water Control Law and the Clean Water Act.
2. As an alternative to transfers under Part III Y 1, this permit may be automatically transferred to a new permittee if:
a. The current permittee notifies the department
at leastwithin 30 daysin advanceof theproposedtransfer of the title to the facility or property;b. The notice includes a written agreement between the existing and new permittees containing a specific date for transfer of permit responsibility, coverage, and liability between them; and
c. The board does not notify the existing permittee and the proposed new permittee of its intent to modify or revoke and reissue the permit. If this notice is not received, the transfer is effective on the date specified in the agreement mentioned in Part III Y 2 b.
Z. Severability. The provisions of this permit are severable, and if any provision of this permit or the application of any provision of this permit to any circumstance is held invalid, the application of such provision to other circumstances, and the remainder of this permit, shall not be affected thereby.
DOCUMENTS INCORPORATED BY REFERENCE (9VAC25-193)
Standard Industrial Classification Manual, 1987, Office of Management and Budget.
Standard Methods for the Examination of Water and Wastewater, 18th, 19th, 20th and 21st Editions, 1992, 1995, 1998 and 2005, American Public Health Association.
Method 8270D, Semivolatile Organic Compounds by Gas Chromatography/Mass Spectrometry (GC/MS), Revision 4, February 2007, U.S. Government Printing Office.Modified DRO Method for Determining Diesel Range Organics, PUBL-SW-141, September 1995, Wisconsin Department of Natural Resources.VA.R. Doc. No. R12-3072; Filed October 10, 2012, 12:37 p.m.