Section 210. Reporting requirements  


Latest version.
  • The owner shall furnish written notification to the regional office of the following:

    1. The actual date on which construction or modification of each affected unit commenced within 30 days after such date.

    2. If necessary, the actual date on which the integration operational period of each affected unit commenced within 15 days after such date.

    3. The anticipated start-up date of each affected unit postmarked not more than 60 days nor less than 30 days prior to such date.

    4. The actual start-up date of each affected unit within 15 days after such date.

Historical Notes

Derived from Volume 27, Issue 23, eff. August 17, 2011.

Statutory Authority

§§ 10.1-1307.2 and 10.1-1308 of the Code of Virginia.