Virginia Administrative Code (Last Updated: January 10, 2017) |
Title 9. Environment |
Agency 5. State Air Pollution Control Board |
Chapter 530. Electric Generator Voluntary Demand Response General Permit |
Section 160. Monitoring requirements
-
A. The owner shall install and use a fuel flow meter to monitor the fuel throughput for each affected unit, calculated monthly as the sum of each consecutive 12-month period.
B. Each fuel flow meter shall be installed, maintained, calibrated, and operated in accordance with approved procedures which shall include, as a minimum, the manufacturer's written requirements or recommendations.
C. The fuel flow meter used to continuously measure the fuel throughput for each affected unit shall be observed by the owner with a frequency of not less than once per month. The owner shall keep a log of the observations from the fuel flow meter.
Historical Notes
Derived from Volume 27, Issue 23, eff. August 17, 2011.
Statutory Authority
§§ 10.1-1307.02 and 10.1-1308 of the Code of Virginia.