Section 210. Reporting requirements  


Latest version.
  • A. The permittee shall comply with the reporting requirements in this section. Any document (including reports) required by a permit term or condition to be submitted to the department shall contain a document certification signed by a responsible official that meets the requirements of 9VAC5-20-230.

    B. The permittee shall furnish written notification to the department of the following dates relative to the requirements of 9VAC5-520-180:

    1. The actual date on which construction or installation of any biomass pilot test facility commenced, postmarked within 30 days after that date;

    2. The anticipated startup date of the biomass pilot test facility, postmarked not more than 60 days nor less than 30 days prior to such date;

    3. The actual startup date of the biomass pilot test facility postmarked within 15 days after that date;

    4. The test protocol, postmarked at least 30 days prior to the date that testing commences; and

    5. The test results, no later than 45 days after test completion of the stack tests and visible emissions evaluation.