Section 8650. Permits  


Latest version.
  • A permit may be required prior to beginning any of the activities specified below if the provisions of 9VAC5-50 (New and Modified Stationary Sources) and 9VAC5-80 (Permits for Stationary Sources) apply. Owners contemplating such action should review those provisions and contact the appropriate regional office for guidance on whether those provisions apply.

    1. Construction of a facility.

    2. Reconstruction (replacement of more than half) of a facility.

    3. Modification (any physical change to equipment) of a facility.

    4. Relocation of a facility.

    5. Reactivation (re-startup) of a facility.

    6. Operation of a facility.

Historical Notes

Derived from Volume 32, Issue 07, eff. February 1, 2016.

Statutory Authority

§ 10.1-1308 of the Code of Virginia; §§ 110, 111, 123, 129, 171, 172, and 182 of the federal Clean Air Act; 40 CFR Parts 51 and 60.