Section 240. Effective date of initial NOx Budget permit  


Latest version.
  • The initial NOx Budget permit covering a NOx Budget unit for which a complete NOx Budget permit application is timely submitted under 9VAC5-140-210 B shall become effective by the later of:

    1. May 31, 2004;

    2. May 1 of the year in which the NOx Budget unit commences operation, if the unit commences operation on or before May 1 of that year;

    3. The date on which the NOx Budget unit commences operation, if the unit commences operation during a control period; or

    4. May 1 of the year following the year in which the NOx Budget unit commences operation, if the unit commences operation on or after October 1 of the year.

Historical Notes

Derived from Volume 18, Issue 20, eff. July 17, 2002.

Statutory Authority

§§ 10.1-1308 and 10.1-1322.3 of the Code of Virginia.