Section 65. Water quality compliance  


Latest version.
  • A. Compliance with the water quality design criteria set out in subdivisions A 1 and A 2 of 9VAC25-870-63 shall be determined by utilizing the Virginia Runoff Reduction Method or another equivalent methodology that is approved by the board.

    B. The BMPs listed in this subsection are approved for use as necessary to effectively reduce the phosphorus load and runoff volume in accordance with the Virginia Runoff Reduction Method. Other approved BMPs found on the Virginia Stormwater BMP Clearinghouse Website may also be utilized. Design specifications and the pollutant removal efficiencies for all approved BMPs are found on the Virginia Stormwater BMP Clearinghouse Website.

    1. Vegetated Roof (Version 2.3, March 1, 2011);

    2. Rooftop Disconnection (Version 1.9, March 1, 2011);

    3. Rainwater Harvesting (Version 1.9.5, March 1, 2011);

    4. Soil Amendments (Version 1.8, March 1, 2011);

    5. Permeable Pavement (Version 1.8, March 1, 2011);

    6. Grass Channel (Version 1.9, March 1, 2011);

    7. Bioretention (Version 1.9, March 1, 2011);

    8. Infiltration (Version 1.9, March 1, 2011);

    9. Dry Swale (Version 1.9, March 1, 2011);

    10. Wet Swale (Version 1.9, March 1, 2011);

    11. Sheet Flow to Filter/Open Space (Version 1.9, March 1, 2011);

    12. Extended Detention Pond (Version 1.9, March 1, 2011);

    13. Filtering Practice (Version 1.8, March 1, 2011);

    14. Constructed Wetland (Version 1.9, March 1, 2011); and

    15. Wet Pond (Version 1.9, March 1, 2011).

    C. BMPs differing from those listed in subsection B of this section or proprietary BMPs certified in other states shall be reviewed and approved by the director in accordance with procedures established by the department.

    D. A VSMP authority may establish limitations on the use of specific BMPs in accordance with § 62.1-44.15:33 of the Code of Virginia.

    E. The VSMP authority shall have the discretion to allow for application of the design criteria to each drainage area of the site. However, where a site drains to more than one HUC, the pollutant load reduction requirements shall be applied independently within each HUC unless reductions are achieved in accordance with a comprehensive watershed stormwater management plan in accordance with 9VAC25-870-92.

    F. Offsite alternatives where allowed in accordance with 9VAC25-870-69 may be utilized to meet the design criteria of subsection A of 9VAC25-870-63.

Historical Notes

Former 4VAC50-60-65 derived from Volume 27, Issue 26, eff. September 13, 2011; amended, Virginia Register Volume 29, Issue 04, eff. November 21, 2012; amended and renumbered, Virginia Register Volume 30, Issue 02, eff. October 23, 2013; amended, Virginia Register Volume 30, Issue 24, eff. July 1, 2014.