Section 170. Requirements for state stormwater management annual standards and specifications  


Latest version.
  • A. Standards and specifications may, and after June 30, 2014, shall, be submitted to the department by a state agency on an annual basis. Such standards and specifications shall be consistent with the requirements of the Act, this chapter, the General Permit for Discharges of Stormwater from Construction Activities (9VAC25-880), and the Erosion and Sediment Control Law and associated regulations. Each project constructed in accordance with the requirements of the Act, this chapter, and where required standards and specifications shall obtain coverage issued under the state general permit prior to land disturbance. State agency stormwater management standards and specifications describe how land-disturbing activities shall be conducted and shall include, but are not limited to:

    1. Technical criteria to meet the requirements of the Act and this chapter;

    2. Provisions for the preparation of individual stormwater management and erosion and sediment control plans for each project. In addition, the individual plans, to the maximum extent practicable, shall comply with any locality's VSMP authority's technical requirements adopted pursuant to the Act. It shall be the responsibility of the state agency to demonstrate that the locality's VSMP authority's technical requirements are not practicable for the project under consideration;

    3. Provisions for the long-term responsibility and maintenance of stormwater management control devices and other techniques specified to manage the quantity and quality of runoff, including an inspection and maintenance schedule, shall be developed and implemented;

    4. Provisions for erosion and sediment control and stormwater management program administration, plan design, review and approval, and construction inspection and enforcement;

    5. Provisions for ensuring that responsible personnel and contractors obtain certifications or qualifications for erosion and sediment control and stormwater management comparable to those required for VSMP authorities;

    6. Implementation of a project tracking and notification system to the department of all land-disturbing activities covered under the Act and this chapter; and

    7. Requirements for documenting on-site changes as they occur to ensure compliance with the requirements of the Act and this chapter.

    B. Copies of such stormwater management specifications and standards including, but not limited to, design manuals, technical guides and handbooks, shall be submitted.

Historical Notes

Former 4VAC50-60-170 derived from Volume 21, Issue 03, eff. January 29, 2005; amended, Virginia Register Volume 29, Issue 04, eff. November 21, 2012; amended and renumbered, Virginia Register Volume 30, Issue 02, eff. October 23, 2013.

Statutory Authority

§§ 62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.