Section 114. Inspections  


Latest version.
  • A. The VSMP authority shall inspect the land-disturbing activity during construction for:

    1. Compliance with the approved erosion and sediment control plan;

    2. Compliance with the approved stormwater management plan;

    3. Development, updating, and implementation of a pollution prevention plan; and

    4. Development and implementation of any additional control measures necessary to address a TMDL.

    B. The VSMP authority shall establish an inspection program that ensures that stormwater management facilities are being adequately maintained as designed after completion of land-disturbing activities. Inspection programs shall:

    1. Be approved by the board;

    2. Ensure that each stormwater management facility is inspected by the VSMP authority, or its designee, not to include the owner, except as provided in subsections C and D of this section, at least once every five years; and

    3. Be documented by records.

    C. The VSMP authority may utilize the inspection reports of the owner of a stormwater management facility as part of an inspection program established in subsection B of this section if the inspection is conducted by a person who is licensed as a professional engineer, architect, landscape architect, or land surveyor pursuant to Article 1 (§ 54.1-400 et seq.) of Chapter 4 of Title 54.1; a person who works under the direction and oversight of the licensed professional engineer, architect, landscape architect, or land surveyor; or a person who holds an appropriate certificate of competence from the board.

    D. If a recorded instrument is not required pursuant to 9VAC25-870-112, a VSMP authority shall develop a strategy for addressing maintenance of stormwater management facilities designed to treat stormwater runoff primarily from an individual residential lot on which they are located. Such a strategy may include periodic inspections, homeowner outreach and education, or other method targeted at promoting the long-term maintenance of such facilities. Such facilities shall not be subject to the requirement for an inspection to be conducted by the VSMP authority.

Historical Notes

Former 4VAC50-60-114 derived from Volume 27, Issue 26, eff. September 13, 2011; amended, Virginia Register Volume 29, Issue 04, eff. November 21, 2012; amended and renumbered, Virginia Register Volume 30, Issue 02, eff. October 23, 2013.

Statutory Authority

§§ 62.1-44.15:25 and 62.1-44.15:28 of the Code of Virginia.