  • The VESCP authority may waive or modify any of the requirements that are deemed inappropriate or too restrictive for site conditions, by granting a variance. A variance may be granted under these conditions:

    1. At the time of plan submission, an applicant may request a variance to become part of the approved erosion and sediment control plan. The applicant shall explain the reasons for requesting variances in writing. Specific variances which are allowed by the VESCP authority shall be documented in the plan.

    2. During construction, the person responsible for implementing the approved plan may request a variance in writing from the VESCP authority. The VESCP authority shall respond in writing either approving or disapproving such a request. If the VESCP authority does not approve a variance within 10 days of receipt of the request, the request shall be considered to be disapproved. Following disapproval, the applicant may resubmit a variance request with additional documentation.

    3. The VESCP authority shall consider variance requests judiciously, keeping in mind both the need of the applicant to maximize cost effectiveness and the need to protect off-site properties and resources from damage.

Historical Notes

Former 4VAC50-30-50, derived from VR625-02-00 § 5, eff. September 13, 1990; amended, Volume 11, Issue 11, eff. March 22, 1995; Volume 29, Issue 04, eff. November 21, 2012; amended and renumbered, Virginia Register Volume 30, Issue 02, eff. October 23, 2013.

Statutory Authority

§ 62.1-44.15:52 of the Code of Virginia.