An applicant for a VWP permit for completion of a dredging project in tidal waters must file proof of mitigation bank credit purchase or in-lieu fee fund donation or a financial responsibility mechanism with the board at least 60 days prior to onset of any activity in permitted impact areas. The compensatory mitigation plan and financial responsibility documentation or proof of mitigation bank credit purchase or in-lieu fee fund donation shall be submitted by the permittee and approved by the board prior to the onset of any dredging activities in permitted impact areas.