Section 110. Repairs allowed  


Latest version.
  • Owners and operators must obtain a permit and the required inspections in accordance with the provisions of the Virginia Uniform Statewide Building Code (§ 36-97 et seq. of the Code of Virginia).

    A permit from the building official must be obtained prior to repairing any UST system. No repaired UST system shall be placed into use unless and until the system is inspected in accordance with the provisions of the Virginia Uniform Statewide Building Code (§ 36-97 et seq. of the Code of Virginia).

    In the case of state-owned facilities the Department of General Services shall function as the building official in accordance with § 36-98.1 of the Code of Virginia.

    In the case of federal facilities the building official must be contacted. Owners and operators must obtain a permit and the required inspections in accordance with the provisions of the Virginia Uniform Statewide Building Code (§ 36-97 et seq. of the Code of Virginia).

    Owners and operators of UST systems must ensure that repairs will prevent releases due to structural failure or corrosion as long as the UST system is used to store regulated substances. The repairs must meet the following requirements:

    1. Repairs to UST systems must be properly conducted in accordance with a code of practice developed by a nationally recognized association or an independent testing laboratory.

    NOTE: The following codes and standards may be used to comply with subdivision 1 of this section: National Fire Protection Association Standard 30, "Flammable and Combustible Liquids Code"; American Petroleum Institute Publication 2200, "Repairing Crude Oil, Liquefied Petroleum Gas, and Product Pipelines"; American Petroleum Institute Publication 1631, "Recommended Practice for the Interior Lining of Existing Steel Underground Storage Tanks"; and National Leak Prevention Association Standard 631, "Spill Prevention, Minimum 10 Year Life Extension of Existing Steel Underground Tanks by Lining Without the Addition of Cathodic Protection."

    2. Repairs to fiberglass-reinforced plastic tanks may be made by the manufacturer's authorized representatives or in accordance with a code of practice developed by a nationally recognized association or an independent testing laboratory.

    3. Metal pipe sections and fittings that have released product as a result of corrosion or other damage must be replaced. Fiberglass pipes and fittings may be repaired in accordance with the manufacturer's specifications.

    4. Repaired tanks and piping must be tightness tested in accordance with subsection 3 of 9VAC25-580-160 and subdivision 2 of 9VAC25-580-170 within 30 days following the date of the completion of the repair except as provided in subdivisions 4 a through c of this section:

    a. The repaired tank is internally inspected in accordance with a code of practice developed by a nationally recognized association or an independent testing laboratory;

    b. The repaired portion of the UST system is monitored monthly for releases in accordance with a method specified in subsections 4 through 8 of 9VAC25-580-160; or

    c. Another test method is used that is determined by the board to be no less protective of human health and the environment than those listed above.

    5. Within six months following the repair of any cathodically protected UST system, the cathodic protection system must be tested in accordance with subdivisions 2 and 3 of 9VAC25-580-90 to ensure that it is operating properly.

    6. UST system owners and operators must maintain records of each repair for the remaining operating life of the UST system that demonstrate compliance with the requirements of this section.