Section 2060. Action on permit application  


Latest version.
  • A. Within 30 days after receipt of an application, the board will notify the applicant of the status of the application. The notification of the initial determination with regard to the status of the application shall be provided by the board in writing and shall include (i) a determination as to which provisions of the new source review program are applicable, (ii) the identification of any deficiencies, and (iii) a determination as to whether the application contains sufficient information to begin application review. The determination that the application has sufficient information to begin review is not necessarily a determination that it is complete. Within 30 days after receipt of any additional information, the board will notify the applicant in writing of any deficiencies in such information. The date of receipt of a complete application for processing under subsection B of this section shall be the date on which the board received all required information and the provisions of § 10.1-1321.1 of the Virginia Air Pollution Control Law have been met, if applicable.

    B. The board will normally process an application according to the steps specified in subdivisions 1 through 4 of this subsection. Processing time for these steps is normally 180 days following receipt of a complete application. The board may extend this time period if additional information is needed.

    1. Complete the preliminary review and analysis in accordance with 9VAC5-80-2090 and the preliminary determination of the board.

    2. Complete the public participation requirements in accordance with 9VAC5-80-2070.

    3. Consider the public comments received in accordance with 9VAC5-80-2070.

    4. Complete the final review and analysis and the final determination of the board.

    C. The board will normally take final action on an application after completion of the steps in subsection B of this section, except in cases where direct consideration of the application by the board is granted pursuant to 9VAC5-80-25. The board will review any request made under 9VAC5-80-2070 G, and will take final action on the request and application as provided in Part I (9VAC5-80-5 et seq.) of this chapter.

    D. The board will notify the applicant in writing of its decision on the application, including its reasons, and shall also specify the applicable emission limitations. These emission limitations are applicable during any emission testing conducted in accordance with 9VAC5-80-2080.

    E. The applicant may appeal the decision pursuant to Part VIII (9VAC5-170-190 et seq.) of 9VAC5 Chapter 170.

    F. Within five days after notification to the applicant pursuant to subsection C of this section, the notification and any comments received pursuant to the public comment period and public hearing shall be made available for public inspection at the same location as was the information in 9VAC5-80-2070 F 1.

Historical Notes

Derived from Volume 15, Issue 11, eff. April 1, 1999; amended, Virginia Register Volume 18, Issue 14, eff. May 1, 2002; Volume 22, Issue 23, eff. September 1, 2006; Volume 25, Issue 06, eff. December 31, 2008.

Statutory Authority

§ 10.1-1308 of the Code of Virginia; Clean Air Act (§§ 110, 112, 165, 173, 182 and Title V); 40 CFR Parts 51, 61, 63, 70 and 72.