Section 1773. Action on permit application  


Latest version.
  • A. Within 30 days after receipt of an application, the board will notify the applicant of the status of the application. The notification of the initial determination with regard to the status of the application will be provided by the board in writing and will include (i) a determination as to which provisions of the new source review program are applicable, (ii) the identification of any deficiencies, and (iii) a determination as to whether the application contains sufficient information to begin application review. The determination that the application has sufficient information to begin review is not necessarily a determination that it is complete. Within 30 days after receipt of any additional information, the board will notify the applicant in writing of any deficiencies in such information. The date of receipt of a complete application shall be, for the purpose of this article, the date on which the board received all required information and the provisions of § 10.1-1321.1 of the Virginia Air Pollution Control Law have been met, if applicable.

    B. The board will normally process an application according to the steps specified in subdivisions 1 through 4 of this subsection. Processing time for these steps is normally one year following receipt of a complete application. The board may extend this time period if additional information is needed.

    1. Complete the preliminary review and analysis in accordance with 9VAC5-80-1705 and the preliminary determination whether construction should be approved, approved with conditions, or disapproved.

    2. Complete the public participation requirements in accordance with 9VAC5-80-1775.

    3. Consider the public comments received in accordance with 9VAC5-80-1775.

    4. Complete the final review and analysis and the final determination of the board.

    C. The board will consider all written comments submitted within a time specified in the notice of public comment and all comments received at any public hearing in making a final decision on the application. No later than 10 days after the close of the public comment period, the applicant may submit a written response to any comments submitted by the public. The board will consider the applicant's response in making a final decision. The board will make all comments available for public inspection in the same locations where the board made available preconstruction information relating to the proposed source or modification.

    D. The board will make a final decision on an application after completion of the steps in subsections B and C of this section except in cases where direct consideration of the application by the board is granted pursuant to 9VAC5-80-25. The board will review any request made under 9VAC5-80-1775 G, and will take final action on the request and application as provided in Part I (9VAC5-80-5 et seq.) of this chapter.

    E. The board will notify the applicant in writing of the final decision and make such notification available for public inspection at the same location where the board made available preconstruction information and public comments relating to the source or modification.

    F. The applicant may appeal the decision pursuant to Part VIII (9VAC5-170-190 et seq.) of 9VAC5-170 (Regulation for General Administration).

    G. Within five days after notification to the applicant pursuant to subsection C of this section, the notification and any comments received pursuant to the public comment period and public hearing will be made available for public inspection at the same location as was the information in 9VAC5-80-1775 F 1.

Historical Notes

Derived from Volume 25, Issue 06, eff. December 31, 2008.

Statutory Authority

§ 10.1-1308 of the Code of Virginia; Clean Air Act (§§ 110, 112, 165, 173, 182 and Title V); 40 CFR Parts 51, 61, 63, 70 and 72.