Section 90. Requirements for granting an authorization to construct and test under the general permit  


Latest version.
  • Part III. General Permit Administrative Procedures

    A. The department may grant an authorization to construct and test under the general permit for a biomass pilot test facility that meets the applicability criteria in 9VAC5-520-40 and the testing schedule in 9VAC5-520-180.

    B. The general permit will be issued in accordance with § 2.2-4006 A 8 of the Administrative Process Act.

Historical Notes

Derived from Volume 27, Issue 17, eff. May 25, 2011.

Statutory Authority

§ 10.1-1308.1 of the Code of Virginia; § 110(a) of the federal Clean Air Act; 40 CFR Part 51.