Virginia Administrative Code (Last Updated: January 10, 2017) |
Title 9. Environment |
Agency 5. State Air Pollution Control Board |
Chapter 160. Regulation for General Conformity |
Section 160. Criteria for determining conformity of general federal actions
-
A. An action required under 9VAC5-160-30 to have a conformity determination for a specific pollutant, shall be determined to conform to the applicable implementation plan if, for each pollutant that exceeds the rates in 9VAC5-160-30 E, or otherwise requires a conformity determination due to the total of direct and indirect emissions from the action, the action meets the requirements of subsection C of this section, and meets any of the following requirements:
1. For any criteria pollutant or precursor, the total of direct and indirect emissions from the action are specifically identified and accounted for in the applicable implementation plan's attainment or maintenance demonstration or reasonable further progress milestone or in a facility-wide emission budget included in an applicable implementation plan in accordance with 9VAC5-160-181;
2. For precursors of ozone, nitrogen dioxide, or particulate matter, the total of direct and indirect emissions from the action are fully offset within the same nonattainment or maintenance area (or nearby area of equal or higher classification provided the emissions from that area contribute to the violations, or have contributed to violations in the past, in the area with the federal action) through a revision to the applicable implementation plan or a similarly enforceable measure that effects emission reductions so that there is no net increase in emissions of that pollutant;
3. For any directly emitted criteria pollutant, the total of direct and indirect emissions from the action meets the requirements:
a. Specified in subsection B of this section, based on areawide air quality modeling analysis and local air quality modeling analysis; or
b. Meet the requirements of subdivision 5 of this subsection, and, for local air quality modeling analysis, the requirement of subsection B of this section;
4. For carbon monoxide or particulate matter:
a. Where the department determines (in accordance with 9VAC5-160-120 and 9VAC5-160-130 and consistent with the applicable implementation plan) that an areawide air quality modeling analysis is not needed, the total of direct and indirect emissions from the action meet the requirements specified in subsection B of this section, based on local air quality modeling analysis; or
b. Where the department determines (in accordance with 9VAC5-160-120 and 9VAC5-160-130 and consistent with the applicable implementation plan) that an areawide air quality modeling analysis is appropriate and that a local air quality modeling analysis is not needed, the total of direct and indirect emissions from the action meet the requirements specified in subsection B of this section, based on areawide modeling, or meet the requirements of subdivision 5 of this subsection; or
5. For ozone or nitrogen dioxide, and for the purposes of subdivisions 3 b and 4 b of this subsection, each portion of the action or the action as a whole meets any of the following requirements:
a. Where EPA has approved a revision to the applicable implementation plan after the area was designated as nonattainment and the department makes a determination that as provided in subdivision 5 a (1) of this subsection or where the Commonwealth of Virginia makes a commitment as provided in subdivision 5 a (2) of this subsection:
(1) The total of direct and indirect emissions from the action or portion thereof is determined and documented by the department to result in a level of emissions which, together with all other emissions in the nonattainment or maintenance area, would not exceed the emissions budgets specified in the applicable implementation plan.
(2) The total of direct and indirect emissions from the action or portion thereof is determined and documented by the department to result in a level of emissions which, together with all other emissions in the nonattainment or maintenance area, would exceed an emissions budgets specified in the applicable implementation plan and the Governor or the Governor's designee for state implementation plan actions makes a written commitment to EPA which includes the following:
(a) A specific schedule for adoption and submittal of a revision to the applicable implementation plan which would achieve the needed emissions reductions prior to the time emissions from the federal action would occur;
(b) Identification of specific measures for incorporation into the applicable implementation plan which would result in a level of emissions which, together with all other emissions in the nonattainment or maintenance area, would not exceed any emissions budget specified in the applicable implementation plan;
(c) A demonstration that all existing applicable implementation plan requirements are being implemented in the area for the pollutants affected by the federal action, and that local authority to implement additional requirements has been fully pursued;
(d) A determination that the responsible federal agencies have required all reasonable mitigation measures associated with their action; and
(e) Written documentation including all air quality analyses supporting the conformity determination.
(3) Where a federal agency made a conformity determination based on a commitment from the Commonwealth of Virginia under subdivision 5 a (2) of this subsection, and the department has submitted an implementation plan to EPA covering the time period during which the emissions will occur or is scheduled to submit such an implementation plan within 18 months of the conformity determination, the commitment is automatically deemed a call for a revision to the applicable implementation plan by EPA under § 110(k)(5) of the federal Clean Air Act, effective on the date of the federal conformity determination and requiring response within 18 months or any shorter time within which the Commonwealth of Virginia commits to revise the applicable implementation plan.
(4) Where a federal agency made a conformity determination based on a commitment from the Commonwealth of Virginia under subdivision 5 a (2) of this subsection and the department has not submitted an implementation plan covering the time period when the emissions will occur or is not scheduled to submit such an implementation plan within 18 months of the conformity determination, the department will, within 18 months, submit to EPA a revision to the existing implementation plan committing to include the emissions in the future implementation plan revision.
b. The action or portion thereof, as determined by the metropolitan planning organization, is specifically included in a current transportation plan and transportation improvement program which have been found to conform to the applicable implementation plan under 40 CFR Part 51, Subpart T, or 40 CFR Part 93, Subpart A.
c. The action or portion thereof fully offsets its emissions within the same nonattainment or maintenance area (or nearby area of equal or higher classification provided the emissions from that area contribute to the violations, or have contributed to violation in the past, in the area with the federal action) through a revision to the applicable implementation plan or an equally enforceable measure that effects emissions reductions equal to or greater than the total of direct and indirect emissions from the action so that there is no net increase in emissions of that pollutant.
d. Where EPA has not approved a revision to the relevant implementation plan since the area was redesignated or classified, the total of direct and indirect emissions from the action for the future years (described in 9VAC5-160-170) do not increase emissions with respect to the baseline emissions.
(1) The baseline emissions reflect the historical activity levels that occurred in the geographic area affected by the proposed federal action during:
(a) The most current calendar year with a complete emissions inventory available before an area is designated unless EPA sets another year;
(b) The emission budget in the applicable implementation plan; or
(c) The year of the baseline inventory in the PM10-applicable implementation plan.
(2) The baseline emissions are the total of direct and indirect emissions calculated for the future years (described in 9VAC5-160-170 D) using the historic activity levels (described in subdivision 5 d (1) of this subsection) and appropriate emission factors for the future years.
e. Where the action involves regional water or wastewater projects or both, the projects are sized to meet only the needs of population projections that are in the applicable implementation plan, based on assumptions regarding per capita use that are developed or approved in accordance with 9VAC5-160-170 A.
B. The areawide or local air quality modeling analyses or both shall:
1. Meet the requirements of 9VAC5-160-170; and
2. Show that the action does not:
a. Cause or contribute to any new violation of any standard in any area; or
b. Increase the frequency or severity of any existing violation of any standard in any area.
C. Notwithstanding any other requirements of this section, an action subject to this section may not be determined to conform to the applicable implementation plan unless the total of direct and indirect emissions from the action is in compliance or consistent with all relevant requirements and milestones contained in the applicable implementation plan, such as elements identified as part of the reasonable further progress schedules, assumptions specified in the attainment or maintenance demonstration, prohibitions, numerical emission limits, and work practice requirements, and the action is otherwise in accordance with all relevant requirements of the applicable implementation plan.
D. Any analyses required under this section shall be completed, and any mitigation requirements necessary for a finding of conformity shall be identified in accordance with 9VAC5-160-180 before the determination of conformity is made.
Historical Notes
Derived from Volume 12, Issue 26, eff. January 1, 1997; amended, Virginia Register Volume 27, Issue 11, eff. March 2, 2011.
Statutory Authority
§ 10.1-1308 of the Code of Virginia.