Virginia Administrative Code (Last Updated: January 10, 2017) |
Title 9. Environment |
Agency 25. State Water Control Board |
Chapter 151. General Virginia Pollutant Discharge Elimination System (VPDES) Permit Fordischarges of Storm Water Associated with Industrial Activity |
Section 60. Registration statement and Stormwater Pollution Prevention Plan (SWPPP)
-
A. An owner seeking coverage under this general permit shall submit a complete VPDES general permit registration statement in accordance with this section, which shall serve as a notice of intent for coverage under the general VPDES permit for discharges of stormwater associated with industrial activity.
Any owner that was authorized to discharge under the industrial stormwater general permit that became effective on July 1, 2009, and that intends to continue coverage under this general permit shall review and update the Stormwater Pollution Prevention Plan (SWPPP) to meet all provisions of the general permit (9VAC25-151-70 et seq.) within 90 days of the board granting coverage under this permit. Owners of new facilities, facilities previously covered by an expiring individual permit, and existing facilities not currently covered by a VPDES permit who wish to obtain coverage under this general permit shall prepare and implement a written SWPPP for the facility in accordance with the general permit (9VAC25-151-70 et seq.) prior to submitting the registration statement.
B. Deadlines for submitting registration statements.
1. Existing facilities.
a. Any owner that was authorized to discharge under the industrial stormwater general permit that became effective on July 1, 2009, and that intends to continue coverage under this general permit shall submit a complete registration statement to the board on or before May 2, 2014.
b. Any owner covered by an individual VPDES permit for stormwater discharges associated with industrial activity that is proposing to be covered under this general permit shall submit a complete registration statement at least 240 days prior to the expiration date of the individual VPDES permit.
c. Any owner of an existing facility with stormwater discharges associated with industrial activity, not currently covered by a VPDES permit, that is proposing to be covered under this general permit shall submit a complete registration statement to the board.
2. New facilities. Any owner proposing a new discharge of stormwater associated with industrial activity shall submit a complete registration statement at least 60 days prior to the date planned for the commencement of the industrial activity at the facility.
3. New owners of existing facilities. Where the owner of an existing facility that is covered by this permit changes, the new owner of the facility shall submit a complete registration statement within 30 days of the ownership change.
4. Late registration statements. Registration statements for existing facilities covered under subdivision 1 a of this subsection will be accepted after June 30, 2014, but authorization to discharge will not be retroactive. Owners described in subdivision 1 a of this subsection that submit registration statements after May 2, 2014, are authorized to discharge under the provisions of 9VAC25-151-50 F (Continuation of permit coverage) if a complete registration statement is submitted before July 1, 2014.
C. The required registration statement shall contain the following information:
1. Name, mailing address, email address (where available), and telephone number of the:
a. Facility owner; and
b. Operator applying for permit coverage (if different than the facility owner);
2. Facility name, street address, county (or city), contact name, email address (where available), phone number, and FAX number (where available);
3. The nature of the business;
4. The receiving waters of the industrial activity discharges;
5. Whether the facility discharges, or will discharge, to an MS4. If so, provide the name of the MS4 owner. (Note: Permit special condition 13 requires the permittee to notify the MS4 owner in writing of the existence of the discharge within 30 days of coverage under this permit. The notification shall include the following information: the name of the facility, a contact person and phone number, the location of the discharge, the nature of the discharge, and the facility's VPDES general permit registration number);
6. The permit number for any existing VPDES permit assigned to the facility;
7. Whether an SWPPP has been prepared prior to submitting this registration statement by the owner of a new facility, a facility previously covered by an expiring individual permit, or an existing facility not currently covered by a VPDES permit;
8. Whether or not this facility will discharge stormwater runoff from coal storage piles;
9. Identification of up to four 4-digit Standard Industrial Classification (SIC) Codes or 2-letter Industrial Activity Codes that best represent the principal products or services rendered by the facility and major colocated industrial activities (2-letter Industrial Activity Codes are: HZ – hazardous waste treatment, storage, or disposal facilities; LF – landfills and disposal facilities that receive or have received any industrial wastes; SE – steam electric power generating facilities; or TW – treatment works treating domestic sewage);
10. Identification of all applicable industrial sectors in this permit (as designated in Table 50‑2) that cover the industrial activities at the facility, and major colocated industrial activities to be covered under this permit, and the stormwater outfalls associated with each industrial sector.
a. If the facility is a landfill (sector L), indicate the type of landfill (i.e., MSWLF (municipal solid waste landfill), CDD (construction debris and demolition), or other), and which outfalls (if any) receive contaminated stormwater runoff;
b. If the facility is a timber products operation (sector A), indicate which outfalls (if any) receive discharges from wet decking areas;
c. For all facilities, indicate which outfalls (if any) receive discharges from coal storage piles;
d. If the facility manufactures asphalt paving and roofing materials (sector D), indicate which outfalls (if any) receive discharges from areas where production of asphalt paving and roofing emulsions occurs;
e. If the facility manufactures cement (sector E), indicate which outfalls (if any) receive discharges from material storage piles;
f. If a scrap recycling and waste recycling facility (sector N - SIC 5093) only receives source-separated recyclable materials, indicate which outfalls (if any) receive discharges from this activity. List the metals (if any) that are received; or
g. For primary airports (sector S), list the average deicing season and indicate which outfalls (if any) receive discharges from deicing of non-propeller aircraft, and the annual average departures of non-propeller aircraft;
11. Facility area information. List the total area of the facility (in acres), the area of industrial activity at the facility (in acres), the total impervious area of the industrial activity at the facility (in acres), and the area (in acres) draining to each industrial activity outfall at the facility. Outfalls shall be numbered using a unique numerical identification code for each outfall (e.g., Outfall No. 001, No. 002, etc.);
12. The following maps shall be included with the registration statement:
a. General location map. A USGS 7.5 minute topographic map, or other equivalent computer generated map, with sufficient resolution to clearly show the location of the facility and the surrounding locale; and
b. Site map. A map showing the property boundaries, the location of all industrial activity areas, all stormwater outfalls, and all water bodies receiving stormwater discharges from the site. Outfall numbering shall be the same as that used for the facility area information in subdivision 11 of this subsection;
13. Virginia's Phase I Chesapeake Bay TMDL Watershed Implementation Plan (November 29, 2010) states that wasteloads for future growth for new facilities in the Chesapeake Bay watershed with industrial stormwater discharges cannot exceed the nutrient and sediment loadings that were discharged prior to the land being developed for the industrial activity. For purposes of this permit regulation, facilities that commence construction after June 30, 2014, must be consistent with this requirement to be eligible for coverage under this general permit.
If this is a new facility that commenced construction after June 30, 2014, in the Chesapeake Bay watershed, and applying for first time general permit coverage, attach documentation to the registration statement to show:
a. That the total phosphorus load does not exceed the greater of: (i) the total phosphorus load that was discharged from the industrial area of the property prior to the land being developed for the new industrial activity or (ii) 0.41 pounds per acre per year (VSMP water quality design criteria). The documentation must include the measures and controls that were employed to meet this requirement, along with the supporting calculations. The owner may include additional nonindustrial land on the site as part of any plan to comply with the no net increase requirement. Consistent with the definition of "site," this includes adjacent land used in connection with the facility. Compliance with the water quality design criteria may be determined utilizing the Virginia Runoff Reduction Method or another equivalent methodology approved by the board. Design specifications and pollutant removal efficiencies for specific BMPs can be found on the Virginia Stormwater BMP Clearinghouse website at http://www.vwrrc.vt.edu/swc; or
b. The owner may consider utilization of any pollutant trading or offset program in accordance with §§ 62.1-44.19:20 through 62.1-44.19:23 of the Code of Virginia, governing trading and offsetting, to meet the no net increase requirement; and
14. The following certification: "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."
D. The registration statement shall be signed in accordance with 9VAC25-31-110 A of the VPDES Permit Regulation.
E. Where to submit. The registration statement may be delivered to the department by either postal or electronic mail and shall be submitted to the DEQ regional office serving the area where the industrial facility is located.
Historical Notes
Derived from Volume 15, Issue 09, eff. June 30, 1999; amended, Virginia Register Volume 20, Issue 16, eff. July 1, 2004; Volume 25, Issue 19, eff. June 24, 2009; Volume 30, Issue 11, eff. July 1, 2014.
Statutory Authority
§ 62.1-44.15 of the Code of Virginia; § 402 of the federal Clean Water Act; 40 CFR Parts 122, 123, and 124.