Section 260. Final inspection  


Latest version.
  • A. The reviewing authority shall inspect the facility upon completion. Upon construction completion, the locality shall require its architect to establish a schedule for final inspection of the project.

    1. The locality shall notify the reviewing authority and all regulatory agencies which reviewed preliminary design or construction documents of the schedule for final inspection.

    2. The locality or localities shall request personnel or agencies other than the reviewing authority involved in the final inspection to submit comments or recommendations in writing to the locality with copies to the reviewing authority.

    3. The locality shall require corrective action on all deficiencies noted in the comments and submit a report of completed actions to the appropriate reviewing agencies and to the reviewing authority.

    B. Upon completion of the final inspection, and corrective actions as required, the locality shall provide to the reviewing authority copies of all regulatory agency letters verifying approval of the completed project.

Historical Notes

Derived from VR230-30-005.1 § 3.6, eff. July 1, 1994.

Statutory Authority

§§ 53.1-5 and 53.1-80 through 53.1-82 of the Code of Virginia.