Section 230. Changes during project development  


Latest version.
  • Article 3. Changes During Project Development

    If, during the project development stage, any substantive change in the scope of the project, any increase in the estimated cost of construction, or any change in the security staff requirements occurs, the review process shall be suspended until the project is resubmitted to the board for further review and possible change in the status of reimbursement recommendation.

Historical Notes

Derived from VR230-30-005.1 § 3.3, eff. July 1, 1994.

Statutory Authority

§§ 53.1-5 and 53.1-80 through 53.1-82 of the Code of Virginia.