A. Each application for a permit or permit modification shall include an operations plan, in a format approved by or on a form prescribed by the director. The operations plan and accompanying maps or drawings shall become part of the terms and conditions of any permit which is issued.
B. The operations plan shall describe the specifications for the use of centralizers to ensure casing is centered in the hole. The specifications shall include, at a minimum, one centralizer within 50 feet of the water protection string seat and then in intervals no greater than every 150 feet above the first centralizer and are subject to the approval of the director.
C. The applicant shall indicate how risks to the public safety or to the site and adjacent lands are to be managed, consistent with the requirements of § 45.1-361.27 B of the Code of Virginia, and shall provide a short narrative, if pertinent. The operations plan shall identify red zone areas.
Historical Notes
Derived from VR480-05-22.1 § 1.10, eff. September 25, 1991; amended, Volume 15, Issue 02, eff. November 11, 1998; Volume 29, Issue 03, eff. November 8, 2012; Volume 30, Issue 01, eff. October 10, 2013; Volume 33, Issue 07, eff. December 28, 2016.
Statutory Authority
§§ 45.1-161.3, 45.1-361.4, and 45.1-361.27 of the Code of Virginia.