(a) The division may issue a permit for nonmountaintop removal, steep slope mining which includes a variance from the requirements of 4VAC25-130-816.102, 4VAC25-130-816.104, 4VAC25-130-816.105, and 4VAC25-130-816.107 or 4VAC25-130-817.102 and 4VAC25-130-817.107 to restore the disturbed areas to their approximate original contour. The permit may contain such a variance only if the division finds, in writing, that the applicant has demonstrated, on the basis of a complete application, that the following requirements are met:
(1) After reclamation, the lands to be affected by the variance within the permit area will be suitable for an industrial, commercial, residential, or public postmining land use (including recreational facilities).
(2) The requirements of 4VAC25-130-816.133 or 4VAC25-130-817.133 will be met.
(3) The watershed of lands within the proposed permit and adjacent areas will be improved by the operations when compared with the condition of the watershed before mining or with its condition if the approximate original contour were to be restored. The watershed will be deemed improved only if--
(i) The amount of total suspended solids or other pollutants discharged to ground or surface water from the permit area will be reduced, so as to improve the public or private uses or the ecology of such water, or flood hazards within the watershed containing the permit area will be reduced by reduction of the peak flow discharge from precipitation events or thaws;
(ii) The total volume of flow from the proposed permit area, during every season of the year, will not vary in a way that adversely affects the ecology of any surface water or any existing or planned use of surface or ground water; and
(iii) The appropriate State environmental agencies approve the plan.
(4) The owner of the surface of the lands within the permit area has knowingly requested, in writing, as part of the application, that a variance be granted. The request shall be made separately from any surface owner consent given for the operations under 4VAC25-130-778.15 and shall show an understanding that the variance could not be granted without the surface owner's request.
(b) If a variance is granted under this section--
(1) The requirements of 4VAC25-130-816.133(d) or 4VAC25-130-817.133(d) shall be included as a specific condition of the permit; and
(2) The permit shall be specifically marked as containing a variance from approximate original contour.
(c) A permit incorporating a variance under this section shall be reviewed by the division at least every 30 months following the issuance of the permit to evaluate the progress and development of the surface coal mining and reclamation operations to establish that the permittee is proceeding in accordance with the terms of the variance.
(d) If the permittee demonstrates to the division that the operations have been, and continue to be, conducted in compliance with the terms and conditions of the permit, the requirements of the Act, this chapter, and the regulatory program, the review specified in Paragraph (c) of this section need not be held.
(e) The terms and conditions of a permit incorporating a variance under this section may be modified at any time by the division, if it determines that more stringent measures are necessary to ensure that the operations involved are conducted in compliance with the requirements of the Act, this chapter, and the regulatory program.
Historical Notes
Derived from VR480-03-19 § 785.16, eff. December 15, 1981; amended, eff. June 28, 1982; October 28, 1982; December 14, 1982; October 11, 1983; December 27, 1983; May 8, 1984; June 22, 1984; August 2, 1984; October 16, 1985; January 7, 1987; July 22, 1987; November 25, 1987; October 12, 1988; December 26, 1990; July 1, 1991; July 17, 1991; November 20, 1991; July 7, 1992; May 5, 1993; October 19, 1994.