Section 53. Special criteria for reduced SDF requirement for certain high hazard dams  


Latest version.
  • A. An existing impounding structure that is currently classified as high hazard, or is subsequently found to be high hazard through reclassification, shall be allowed to pass the flood resulting from 0.6 PMP instead of the flood resulting from 0.9 PMP SDF if the dam owner certifies annually that such impounding structure meets each of the following conditions:

    1. The owner has a current emergency action plan that is approved by the board and that is developed and updated in accordance with 4VAC50-20-175;

    2. The owner has exercised the emergency action plan in accordance with 4VAC50-20-175 and conducts a table-top exercise at least once every two years;

    3. The department has verification that both the local organization for emergency management and the Virginia Department of Emergency Management have on file current emergency action plans and updates for the impounding structure;

    4. The conditions at the impounding structure are monitored on a daily basis and as dictated by the emergency action plan;

    5. The impounding structure is inspected at least annually by a professional engineer and all observed deficiencies are addressed within 120 days of such inspection. Such inspection reports shall be completed in accordance with 4VAC50-20-105 E and be submitted to the department with the owner's certification;

    6. The owner has a dam break inundation zone map developed in accordance with the regulations that is acceptable to the department;

    7. The owner is insured in an amount that will substantially cover the costs of downstream property losses to others that may result from a dam failure; and

    8. The owner has the impounding structure's emergency action plan posted on his website, or upon the request of the owner, the department or another state agency responsible for providing emergency management services to citizens agrees to post the plan on its website. If the department or another state agency agrees to post the plan on its website, the owner shall provide the plan in a format suitable for posting.

    A dam owner who meets the conditions of subdivisions 1 through 8 of this subsection, but has not provided record drawings to the department for his impounding structure, shall submit a complete record report developed in accordance with 4VAC50-20-70 J, excluding the required submittal of the record drawings.

    B. The dam owner must retain documents for a six-year period that supports the certification of the elements set out in subsection A.

Historical Notes

Derived from Volume 27, Issue 06, eff. December 22, 2010.

Statutory Authority

§10.1-605 of the Code of Virginia.