Section 20. Cost/benefit measures  


Latest version.
  • Utility applicants shall analyze a proposed program from a multi-perspective approach using, at a minimum, the Participants Test, the Utility Cost Test, the Ratepayer Impact Measure Test, and the Total Resource Cost Test. Utilities may file for approval of programs individually or as a package. However, any application which includes a package of DSM programs shall also provide an analysis of the cost/benefit of each program individually.

Historical Notes

Derived from Case No. PUE900070 § 2, eff. June 28, 1993.

Statutory Authority

§§ 56-234, 56-235.1, 56-235.2, 56-247 and 56-249 of the Code of Virginia.