Virginia Administrative Code (Last Updated: January 10, 2017) |
Title 20. Public Utilities and Telecommunications |
Agency 5. State Corporation Commission |
Chapter 301. Rules Governing the Use of Bidding Programs to Purchase Electricity from Otherpower Suppliers |
Section 110. Utility reporting requirements
Latest version.
-
An electric utility conducting a competitive bid solicitation must submit a written report to the Commission staff within 45 days of the completion of its evaluation of bids. This report shall describe in detail the evaluation of bids and the company's comparison of the bids received to its own construction options. A second report, similar to the report submitted to the staff but without information considered to be proprietary, must be prepared as a public document. The company shall cooperate fully with the staff in its review of the solicitation and evaluation process.
Historical Notes
Derived from Case No. PUE900029, eff. November 28, 1990.