Section 90. Commissioning tests  


Latest version.
  • Commissioning tests of the interconnection customer's installed equipment shall be performed pursuant to applicable codes and standards, including IEEE 1547.1 2005 "IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems." The utility shall be given at least five business days written notice, or notice as otherwise mutually agreed to by the parties, of the tests and the utility shall be allowed to be present to witness the commissioning tests. The utility shall not be compensated by the IC for witnessing commissioning tests.

Historical Notes

Derived from Volume 25, Issue 20, eff. May 21, 2009.

Statutory Authority

§§ 12.1-13 and 56-578 of the Code of Virginia.