Section 170. Schedules for Chapter 314


Latest version.
  • The following schedules shall be used in the administration of this chapter.

    Schedule 1

    LEVEL 1 INTERCONNECTION REQUEST FORM FOR SMALL GENERATING FACILITY NOT EXCEEDING 500 kW

    PURSUANT TO 20VAC5-314-40 OF THE COMMISSION'S REGULATIONS GOVERNING INTERCONNECTION OF SMALL ELECTRICAL GENERATORS, APPLICANT HEREBY GIVES NOTICE OF INTENT TO OPERATE A GENERATING FACILITY.

    Section 1. Interconnection Customer Information

    Name:____________________________________________________________

    Mailing Address:____________________________________________________

    City, State, Zip:_____________________________________________________

    Street Address:_____________________________________________________

    City, State, Zip:_____________________________________________________

    Phone Number(s):___________________________________________________

    Fax Number:______________________ Email:____________________________

    Utility:_____________________________________________________________

    Utility Account Number:______________________________

    Competitive Service Provider:__________________________________________

    CSP Account Number:______________________________

    Proposed Interconnection Date:_______________________

    Section 2. Processing Fee

    The nonrefundable processing fee payable to the utility is $100.

    Section 3. Small Generating Facility Information

    SGF owner:_______________________________________________________

    SGF operator:_____________________________________________________

    Business relationship to applicant:______________________________________

    Mailing address:___________________________________________________

    City, State, Zip:____________________________________________________

    SGF Address:_____________________________________________________

    City, State, Zip:____________________________________________________

    Phone Number(s):__________________________________________________

    Fax Number:______________________ Email:__________________________

    Fuel Type:_______________________________________________________

    Generator Manufacturer and Model:____________________________________

    Rated Capacity in kilowatts: AC:_________________________ DC:__________

    Inverter Manufacturer and Model:______________________________________

    Battery Backup: Yes_____ No_____

    Facility schematic and equipment layout must be attached to this form.

    Section 4. Information for Generators with an AC capacity in excess of 25 kW

    Is the proposed generator inverter based? Yes_____ No_____

    Generator Type: Inverter

    Induction

    Synchronous

    Frequency:_____________ Hz; Number of phases: One___

    Three___

    Rated Capacity: DC _______ kW; AC apparent _________ kVA; AC real _______ kW;

    Power factor ____________%; AC voltage _________; AC amperage___________

    Facility schematic and equipment layout must be attached to this form.

    Section 5. Vendor Certification

    The SGF equipment is listed by Underwriters Laboratories to be in compliance with UL1741.

    Signed (Vendor):_____________________________________ Date:____________

    Name (printed):_______________________________________________________

    Company:___________________________________________________________

    Phone Number:_______________________________________________________

    Mailing Address:______________________________________________________

    City, State, Zip:_______________________________________________________

    Section 6. Electrician Certification

    The generator equipment has been installed in accordance with the manufacturer's specifications as well as all applicable provisions of the National Electrical Code.

    Signed (Licensed Electrician):__________________________ Date:__________

    Name (printed):____________________________________________________

    License Number:_______________________ Phone Number:_______________

    Mailing Address:___________________________________________________

    City, State, Zip:____________________________________________________

    Section 7. Applicant Signature

    I hereby certify that, to the best of my knowledge, all of the information provided in this Request Form is true and correct.

    Signature of Applicant:_____________________________________________

    Date:________________________

    Section 8. Utility Acknowledgement of Receipt

    Signed:_______________________________________________________

    Title:_________________________________________________________

    Utility:________________________________________________________

    Date:_________________________

    Utility signature signifies only receipt of this form, in compliance with 20VAC5-314-40, the State Corporation Commission's Regulations Governing Interconnection of Small Electrical Generators.

    Schedule 2

    Certification of Small Generator Equipment Packages

    Small generating facility equipment proposed for use separately or packaged with other equipment in an interconnection system shall be considered certified for interconnected operation if (i) it has been tested in accordance with industry standards for continuous utility interactive operation in compliance with the appropriate codes and standards referenced below by any Nationally Recognized Testing Laboratory (NRTL) recognized by the United States Occupational Safety and Health Administration to test and certify interconnection equipment pursuant to the relevant codes and standards listed in SGIP Schedule 3, (ii) it has been labeled and is publicly listed by such NRTL at the time of the interconnection application, and (iii) such NRTL makes readily available for verification all test standards and procedures it utilized in performing such equipment certification, and, with consumer approval, the test data itself. The NRTL may make such information available on its website and by encouraging such information to be included in the manufacturer's literature accompanying the equipment.

    The interconnection customer must verify that the intended use of the equipment falls within the use or uses for which the equipment was tested, labeled, and listed by the NRTL.

    Certified equipment shall not require further type-test review, testing, or additional equipment to meet the requirements of this interconnection procedure; however, nothing herein shall preclude the need for an on-site commissioning test by the parties to the interconnection nor follow up production testing by the NRTL.

    If the certified equipment package includes only interface components (switchgear, inverters, or other interface devices), then an IC must show that the generator or other electric source being utilized with the equipment package is compatible with the equipment package and is consistent with the testing and listing specified for this type of interconnection equipment.

    Provided the generator or electric source, when combined with the equipment package, is within the range of capabilities for which it was tested by the NRTL, and does not violate the interface components' labeling and listing performed by the NRTL, no further design review, testing or additional equipment on the customer side of the point of interconnection shall be required to meet the requirements of this interconnection procedure.

    An equipment package does not include equipment provided by the utility.

    Schedule 3

    Certification Codes and Standards

    IEEE Std 1547 Standard for Interconnecting Distributed Resources with Electric Power Systems (including use of IEEE Std 1547.1 testing protocols to establish conformity)

    UL 1741 Inverters, Converters, and Controllers for Use in Independent Power Systems

    IEEE Std 929-2000 IEEE Recommended Practice for Utility Interface of Photovoltaic (PV) Systems

    NFPA 70 (2005), National Electrical Code

    IEEE Std C37.90.1-1989 (R1994), IEEE Standard Surge Withstand Capability (SWC) Tests for Protective Relays and Relay Systems

    IEEE Std C37.90.2 (1995), IEEE Standard Withstand Capability of Relay Systems to Radiated Electromagnetic Interference from Transceivers

    IEEE Std C37.108-1989 (R2002), IEEE Guide for the Protection of Network Transformers

    IEEE Std C57.12.44-2000, IEEE Standard Requirements for Secondary Network Protectors

    IEEE Std C62.41.2-2002, IEEE Recommended Practice on Characterization of Surges in Low Voltage (1000V and Less) AC Power Circuits

    IEEE Std C62.45-1992 (R2002), IEEE Recommended Practice on Surge Testing for Equipment Connected to Low-Voltage (1000V and Less) AC Power Circuits

    ANSI C84.1-1995 Electric Power Systems and Equipment – Voltage Ratings (60 Hertz)

    IEEE Std 100-2000, IEEE Standard Dictionary of Electrical and Electronic Terms

    NEMA MG 1-1998, Motors and Small Resources, Revision 3

    IEEE Std 519-1992, IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems

    NEMA MG 1-2003 (Rev 2004), Motors and Generators, Revision 1

    Schedule 4

    LEVELS 2 AND 3 INTERCONNECTION REQUEST FORM SMALL GENERATING FACILITY LESS THAN 20 MW

    Section 1. Interconnection Customer Information

    Name:_________________________________________________________

    Contact person:__________________________________________________

    Mailing address:_________________________________________________

    City, State, Zip:__________________________________________________

    Utility and account number:_________________________________________

    Energy Service Provider and account number:__________________________

    Facility address:_________________________________________________

    Telephone (Day):________________ (Evening):________________________

    Fax:__________________________ E-Mail:__________________________

    Alternative contact information

    Contact Name:__________________________________________________

    Title:_________________________________________________________

    Mailing Address:________________________________________________

    City, State, Zip:__________________________________________________

    Telephone (Day):________________ (Evening):________________________

    Fax:__________________________ E-Mail:__________________________

    Application is for: New Small Generating Facility______ Capacity addition____

    If capacity addition to existing facility, please describe:
    ______________________________________________________________

    The Small Generating Facility will supply: Interconnection Customer __ others __

    Point of Interconnection:___________________________________________

    Interconnection Customer's requested in-service date:____________________

    Section 2. Processing Fee or Deposit

    If the Interconnection Request is submitted as Level 2, the nonrefundable processing fee payable to the utility is $500.

    If the Interconnection Request is submitted as Level 3, the Interconnection Customer shall submit to the Utility the deposit is $1,000, or 50% of the estimated cost of the Feasibility Study, whichever is less.

    Section 3. Small Generating Facility Information

    Data apply only to the small generating facility, not the interconnection facilities.

    Energy Source:___ Solar___ Wind___ Hydro___ Hydro Type:______________

    Diesel___ Natural Gas___ Fuel Oil___ Other (describe)___________________

    Prime Mover: Fuel Cell____ Recip Engine____ Gas Turb____ Steam Turb____ Microturbine____ PV____ Other (describe)_____________________________

    Type of Generator: Synchronous_____ Induction_____ Inverter_____

    Generator Nameplate Rating:________ kW ___ Generator Nameplate kVAR:______

    Interconnection customer or customer-site load:__________kW

    Typical reactive load:_________________

    Maximum physical export capability requested:______________ kW

    List components of the small generating facility equipment package that are currently certified:

    Equipment

    Certifying Entity

    1.____________________________

    1.____________________________

    2.____________________________

    2.____________________________

    3.____________________________

    3.____________________________

    4.____________________________

    4.____________________________

    5.____________________________

    5.____________________________

    Is the prime mover compatible with the certified protective relay package?
    Yes____No____

    Generator (or solar collector)

    Manufacturer, model name & number:_________________________________

    Version Number:_________________________________________________

    Nameplate Output Power Rating in kW: (Summer)_________ (Winter)______

    Nameplate Output Power Rating in kVA: (Summer)________ (Winter)______

    Individual Generator Power Factor

    Rated Power Factor: Leading:_____________ Lagging:________________

    Total number of generators in wind farm to be interconnected pursuant to this Interconnection Request: Elevation:_______ Single phase___ Three phase___

    Inverter manufacturer, model name & number:__________________________

    List of adjustable set points for the protective equipment or software:_________

    Note: A completed power systems load flow data sheet must be supplied with the Interconnection Request.

    Small Generating Facility Characteristic Data (for inverter-based machines)

    Max design fault contribution current:______ Instantaneous___ or RMS_______

    Harmonics characteristics:__________________________________________

    Start-up requirements:_____________________________________________

    Small Generating Facility Characteristic Data (for rotating machines)

    RPM Frequency:_______________________________________________

    Neutral Grounding Resistor (If Applicable):____________

    Synchronous Generators:

    Direct Axis Synchronous Reactance, Xd:_______ P.U.

    Direct Axis Transient Reactance, X'd:___________ P.U.

    Direct Axis Subtransient Reactance, X"d:______________ P.U.

    Negative Sequence Reactance, X2:_________ P.U.

    Zero Sequence Reactance, X0:____________ P.U.

    KVA Base:___________________________

    Field Volts:______________

    Field Amperes:___________

    Induction Generators:

    Motoring Power (kW):______________

    I2t or K (Heating Time Constant):______________

    Rotor Resistance, Rr:______________

    Stator Resistance, Rs:______________

    Stator Reactance, Xs:______________

    Rotor Reactance, Xr:______________

    Magnetizing Reactance, Xm:_____________

    Short Circuit Reactance, Xd"':______________

    Exciting Current:______________

    Temperature Rise:______________

    Frame Size:______________

    Design Letter:______________

    Reactive Power Required In Vars (No Load):______________

    Reactive Power Required In Vars (Full Load):______________

    Total Rotating Inertia, H:_____________ Per Unit on kVA base

    Excitation and Governor System Data for Synchronous Generators Only:

    Provide appropriate IEEE model block diagram of excitation system, governor system and power system stabilizer (PSS) in accordance with the regional reliability council criteria. A PSS may be determined to be required by applicable studies. A copy of the manufacturer's block diagram may not be substituted.

    Section 4. Customer's Interconnection Facilities Information

    Will a transformer be used between the generator and the point of interconnection ? Yes ____No ____

    Will the transformer be provided by the interconnection customer? Yes ____No ____

    Transformer Data (If applicable, for interconnection customer-owned transformer):

    Is the transformer: single phase_____ three phase____ Size: kVA_____

    Transformer Impedance:_______% on __________kVA base

    If Three Phase:

    Transformer Primary:_____ Volts _____ Delta _____ Wye _____ Wye Grounded

    Transformer Secondary:___ Volts _____ Delta _____ Wye _____ Wye Grounded

    Transformer Tertiary:_____ Volts _____ Delta _____ Wye _____ Wye Grounded

    Transformer Fuse Data (If applicable, for interconnection customer-owned fuse):

    (Attach copy of fuse manufacturer's minimum melt and total clearing time-current curves)

    Manufacturer:____________ Type:__________ Size:______ Speed:_______

    Interconnecting Circuit Breaker (if applicable):

    Manufacturer:____________________________ Type:__________

    Load Rating (Amps):___ Interrupting Rating (Amps):___ Trip Speed (Cycles):___

    Interconnection Protective Relays (If Applicable):

    If microprocessor-controlled:

    Manufacturer:__________________________ Type:____________________

    Model No. ___________ Firmware ID:_______ Instruction Book No. _________

    List of functions and adjustable setpoints for the protective equipment or software:

    Setpoint Function

    Minimum

    Maximum

    1.________________________________

    ____________

    __________

    2.________________________________

    ____________

    __________

    3.________________________________

    ____________

    __________

    4.________________________________

    ____________

    __________

    5.________________________________

    ____________

    __________

    6.________________________________

    ____________

    __________

    If Discrete Components:

    (Enclose copy of any proposed time-overcurrent coordination curves)

    Manufacturer:___________ Type:_______ Style/Catalog No.:______ Proposed Setting:______

    Manufacturer:___________ Type:_______ Style/Catalog No.:______ Proposed Setting:______

    Manufacturer:___________ Type:_______ Style/Catalog No.:______ Proposed Setting:______

    Manufacturer:___________ Type:_______ Style/Catalog No.:______ Proposed Setting:______

    Manufacturer:___________ Type:_______ Style/Catalog No.:______ Proposed Setting:______

    Current Transformer Data (If applicable):

    (Enclose copy of manufacturer's excitation and ratio correction curves)

    Manufacturer:_________________________________________________

    Type:_______ Accuracy Class:________ Proposed Ratio Connection:_____

    Manufacturer:_________________________________________________

    Type:_______ Accuracy Class:________ Proposed Ratio Connection:_____

    Potential Transformer Data (If applicable):

    Manufacturer:_________________________________________________

    Type:________ Accuracy Class:_______ Proposed Ratio Connection:_____

    Manufacturer:_________________________________________________

    Type:________ Accuracy Class:_______ Proposed Ratio Connection:_____

    Section 5. General Information

    Enclose a copy of the site electrical one-line diagram showing the configuration of the small generating facility equipment, current and potential circuits, and protection and control schemes.

    Enclose a copy of any site documentation that indicates the precise physical location of the proposed SGF (e.g., United States Geological Survey () topographic map or other diagram or documentation).

    Describe the proposed location of the protective interface equipment on the property:____________________________________________________

    Enclose a copy of any site documentation that describes and details the operation of the protection and control schemes. Is available documentation enclosed? Yes____ No____

    Enclose copies of schematic drawings for all protection and control circuits, relay current circuits, relay potential circuits, and alarm/monitoring circuits (if applicable).

    Are schematic drawings enclosed? Yes____ No____

    Section 6. Interconnection Customer Signature

    I hereby certify that, to the best of my knowledge, all the information provided in this Interconnection Request is true and correct.

    Signature:_____________________________ Date:________________

    Section 7. Utility Acknowledgement of Receipt

    Signed:_____________________________________

    Title:_______________________________________

    Utility:______________________________________

    Date:______________________________________

    Utility signature signifies only receipt of this form, in compliance with 20VAC5-314-50 of the State Corporation Commission's Regulations Governing Interconnection of Small Electrical Generators.

    Schedule 5

    LEVELS 2 AND 3 FACILITIES STUDY INFORMATION FORM FOR SMALL GENERATING FACILITIES LESS THAN 20 MW

    1. Provide a location plan and simplified one-line diagram of the plant and station facilities. For staged projects, indicate future generation, future transmission circuits, and other major future facilities. On the one-line diagram, show (i) each generator, its electric connection configuration, and its generation capacity, (ii) the location and capacity of auxiliary power, and (iii) minimum load on CT/PT.

    2. One set of metering is required for each generation connection to the new ring bus or existing utility station. Indicate the number of generation connections requiring a metering set:_____________________

    3. Indicate whether an alternate source of auxiliary power will be available during CT/PT maintenance. Yes_______ No_______

    4. Indicate whether a transfer bus on the generation side of the metering will require that each meter set be designed for the total plant generation. Indicate such on the one-line diagram.

    5. State the type of control system or Programmable Logic Controller (PLC) that will be located at the small generating facility.

    ________________________________________________________________________________________________________________

    6. State the protocol used by the control system or PLC. _____________________________________________________________________

    7. Describe the operation sequence and timing of the protection scheme during disconnection and reconnection to the utility by the SGF.

    8. Provide a 7.5-minute quadrangle map of the site. Indicate the plant, station, transmission line, and property lines.

    9. State the physical dimensions of the proposed interconnection station.

    ________________________________________________________________________________________________________________

    10. State the bus length from generation to interconnection station.

    ________________________________________________________________________________________________________________

    11. Provide a diagram or description of the point of interconnection desired by the IC that is to be the point of interconnection in the system impact study report.

    12. State the line length from interconnection station to utility system.

    ________________________________________________________________________________________________________________

    13. State the pole or tower number observed in the field affixed to the pole or tower leg. _____________________________________________

    14. State the number of third party easements required for distribution or transmission lines.

    ________________________________________________________________________________________________________________

    15. Provide the following proposed schedule dates:

    a. Date IC to begin construction:_________________________________________________

    b. Date generator step-up transformers to receive back feed power:______________________

    c. Date IC will test SGF:_______________________________________________________

    d. Date IC will place SGF into commercial operation:_________________________________

    Schedule 6

    SMALL GENERATOR INTERCONNECTION AGREEMENT (SGIA)

    This Small Generator Interconnection Agreement ("Agreement") is made and entered into this ______ day of ____________, 20__, by __________________ (" Utility"), and _________________________________ ("Interconnection Customer") each hereinafter sometimes referred to individually as "Party" or both referred to collectively as the "Parties."

    Utility Information

    Utility:_________________________________________

    Attention:______________________________________________

    Address:______________________________________________

    City, State, Zip:_________________________________________

    Phone:_____________________ Fax:_______________________

    Interconnection Customer Information

    Interconnection Customer:__________________________________

    Attention:_______________________________________________

    Address:_______________________________________________

    City, State, Zip:__________________________________________

    Phone:_______________________ Fax:______________________

    Interconnection Customer Application No:________________

    In consideration of the mutual covenants set forth herein, the Parties agree as follows:

    Article 1. Scope and Limitations of Agreement

    1.1 This Agreement shall be used for all Interconnection Requests for generators in excess of 500 kW submitted pursuant to the Commission's Regulations Governing Interconnection of Small Electrical Generators, Chapter 314 of the Virginia Administrative Code.

    1.2 This Agreement governs the terms and conditions under which the Interconnection Customer's ("IC") Small Generating Facility ("SGF") will interconnect with, and operate in parallel with, the utility system.

    1.3 This Agreement does not constitute an agreement to purchase or deliver the Interconnection Customer's power. The purchase or delivery of power and other services, including station service or backup power, that the IC may require will be covered under separate agreements, possibly with other parties. The IC will be responsible for separately making all necessary arrangements (including scheduling) for delivery of electricity with the applicable utility and provider of transmission service.

    1.4 Nothing in this Agreement is intended to affect any other agreement between the utility and the IC.

    1.5 Responsibilities of the Parties

    1.5.1 The Parties shall perform all obligations of this Agreement in accordance with all applicable laws and regulations, operating requirements, and Good Utility Practice.

    1.5.2 The IC shall construct, interconnect, operate and maintain its SGF and construct, operate, and maintain its Customer's Interconnection Facilities in accordance with the applicable manufacturer's recommended maintenance schedule, in accordance with this Agreement, and with Good Utility Practice.

    1.5.3 The utility shall construct, operate, and maintain its distribution and transmission system and attachment facilities in accordance with this Agreement, and with Good Utility Practice.

    1.5.4 The IC agrees to construct its facilities in accordance with applicable specifications that meet or exceed those provided by the National Electrical Safety Code, the American National Standards Institute, IEEE, Underwriter's Laboratory, and operating requirements in effect at the time of construction and other applicable national and state codes and standards. The IC agrees to design, install, maintain, and operate its SGF so as to reasonably minimize the likelihood of a disturbance adversely affecting or impairing the system or equipment of the utility or affected systems and to otherwise maintain and operate its SGF in accordance with the specifications and certifications under which the SGF was initially installed and interconnected.

    1.5.5 Each Party shall operate, maintain, repair, and inspect, and shall be fully responsible for the facilities that it now or subsequently may own unless otherwise specified in the Attachments to this Agreement. Each Party shall be responsible for the safe installation, maintenance, repair and condition of their respective lines and appurtenances on their respective sides of the point of change of ownership. The utility and the IC, as appropriate, shall provide Attachment Facilities and Customer's Interconnection Facilities that adequately protect the utility's personnel, and other persons from damage and injury. The allocation of responsibility for the design, installation, operation, maintenance and ownership of Attachment Facilities and Customer's Interconnection Facilities shall be delineated in the Attachments to this Agreement. The design, installation, operation, and maintenance of such facilities shall be the responsibility of the owner except as otherwise provided for in this Agreement.

    1.5.6 The utility shall coordinate with all affected systems to support the interconnection.

    1.6 Parallel operation obligations

    Once the SGF has been authorized to commence parallel operation, the IC shall abide by all rules and procedures pertaining to the parallel operation of the SGF including, but not limited to the rules and procedures concerning the operation of generation set forth in the tariff.

    1.7 Metering

    The IC shall be responsible for the utility's reasonable and necessary cost for the purchase, installation, operation, maintenance, testing, repair, and replacement of metering and data acquisition equipment specified in Attachments 2 and 3 of this Agreement. The IC's metering (and data acquisition, as required) equipment shall conform to applicable industry rules and operating requirements.

    1.8 Reactive power

    1.8.1 The IC shall design its SGF to maintain a composite power delivery at continuous rated power output at the point of interconnection at a power factor within the range of 0.95 leading to 0.95 lagging, unless the utility has established different requirements that apply to all similarly situated generators in the control area on a comparable basis. The requirements of this paragraph shall not apply to wind generators.

    1.8.2 The utility is required to pay the Interconnection Customer for reactive power that the IC provides or absorbs from the SGF when the utility requests the IC to operate its SGF outside the range specified in article 1.8.1. In addition, if the utility pays its own or affiliated generators for reactive power service within the specified range, it must similarly pay the IC.

    1.8.3 Payments shall be in accordance with the IC's applicable rate schedule as may be in effect and accepted by the appropriate government authority. To the extent that no rate schedule is in effect at the time the Interconnection Customer is required to provide or absorb reactive power under this Agreement, the IC may expeditiously file such rate schedule with the appropriate government authority, and the utility agrees to support any request for waiver of any prior notice requirement of such authority in order to permit compensation to the IC from the time service commenced.

    1.9 Capitalized terms used herein shall have the meanings specified in the definitions in Attachment 1 to Schedule 6 or in the body of this Agreement.

    Article 2. Inspection, Testing, Authorization, and Right of Access

    2.1 Equipment testing and inspection

    2.1.1 The Interconnection Customer shall test and inspect its small generating facility and interconnection facilities prior to interconnection. The IC shall notify the utility of such activities no fewer than five business days (or as may be agreed to by the Parties) prior to such testing and inspection. Testing and inspection shall occur on a business day. The utility may, at its own expense, send qualified personnel to the SGF site to inspect the interconnection and observe the testing. The IC shall provide the utility a written test report when such testing and inspection is completed.

    2.1.2 The utility shall provide the IC written acknowledgment that it has received the IC's written test report. Such written acknowledgment shall not be deemed to be or construed as any representation, assurance, guarantee, or warranty by the utility of the safety, durability, suitability, or reliability of the SGF or any associated control, protective, and safety devices owned or controlled by the IC or the quality of power produced by the SGF.

    2.2 Authorization required prior to parallel operation

    2.2.1 The utility shall use reasonable efforts to list applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, the utility shall notify the Interconnection Customer of any changes to these requirements as soon as they are known. The utility shall make reasonable efforts to cooperate with the IC in meeting requirements necessary for the IC to commence parallel operations by the in-service date.

    2.2.2 The IC shall not operate its SGF in parallel with the utility's system without prior written authorization of the utility. The utility will provide such authorization once the utility receives notification that the IC has complied with all applicable parallel operation requirements. Such authorization shall not be unreasonably withheld, conditioned, or delayed.

    2.3 Right of access

    2.3.1 Upon reasonable notice, the utility may send a qualified person to the premises of the Interconnection Customer at or immediately before the time the SGF first produces energy to inspect the interconnection, and observe the commissioning of the SGF (including any required testing), startup, and operation for a period of up to three business days after initial start-up of the unit. In addition, the IC shall notify the utility at least five business days prior to conducting any on-site verification testing of the SGF.

    2.3.2 Following the initial inspection process described above, at reasonable hours, and upon reasonable notice, or at any time without notice in the event of an emergency or hazardous condition, the utility shall have access to the Interconnection Customer's premises for any reasonable purpose in connection with the performance of the obligations imposed on it by this Agreement or if necessary to meet its legal obligation to provide service to its customers.

    2.3.3 Each Party shall be responsible for its own costs associated with this article.

    Article 3. Effective Date, Term, Termination, and Disconnection

    3.1 Effective date

    This Agreement shall become effective upon execution by the Parties. The utility shall promptly file this Agreement with the Commission's Division of Energy Regulation upon execution.

    3.2 Term of Agreement

    This Agreement shall remain in effect for a period of 10 years from the effective date or such other longer period as the Interconnection Customer may request and shall be automatically renewed for each successive one-year period thereafter, unless terminated earlier in accordance with article 3.3 of this Agreement.

    3.3 Termination

    No termination shall become effective until the Parties have complied with all applicable laws and regulations applicable to such termination, including the filing with the Commission's Division of Energy Regulation of a notice of termination of this Agreement.

    3.3.1 The Interconnection Customer may terminate this Agreement at any time by giving the utility 20 business days written notice.

    3.3.2 Either Party may terminate this Agreement after default pursuant to article 7.6.

    3.3.3 Upon termination of this Agreement, the Small Generating Facility will be disconnected from the utility system. The termination of this Agreement shall not relieve either Party of its liabilities and obligations, owed or continuing at the time of the termination.

    3.4 Temporary disconnection

    Temporary disconnection shall continue only for so long as reasonably necessary under Good Utility Practice.

    3.4.1 Emergency Conditions -- "Emergency Condition" shall mean a condition or situation: (i) that in the judgment of the Party making the claim is imminently likely to endanger life or property; or (ii) that, in the case of the utility, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to the utility system, the Attachment Facilities or the electrical facilities of others to which the utility system is directly connected; or (iii) that, in the case of the Interconnection Customer, is imminently likely (as determined in a non-discriminatory manner) to cause a material adverse effect on the security of, or damage to, the Small Generating Facility or the Customer's Interconnection Facilities. Under emergency conditions, the utility may immediately suspend interconnection service and temporarily disconnect the SGF. The utility shall notify the IC promptly when it becomes aware of an emergency condition that may reasonably be expected to affect the IC's operation of the SGF. The IC shall notify the utility promptly when it becomes aware of an emergency condition that may reasonably be expected to affect the utility system or other affected systems. To the extent information is known, the notification shall describe the emergency condition, the extent of the damage or deficiency, the expected effect on the operation of both Parties' facilities and operations, its anticipated duration, and the necessary corrective action.

    3.4.2 Routine maintenance, construction, and repair

    The utility may interrupt interconnection service or curtail the output of the SGF and temporarily disconnect the SGF from the utility's system when necessary for routine maintenance, construction, and repairs on the utility system. The utility shall provide the IC with at least five business days notice prior to such interruption unless circumstances require shorter notice. The utility shall use reasonable efforts to coordinate such reduction or temporary disconnection with the IC.

    3.4.3 Forced outages

    During any forced outage, the utility may suspend interconnection service to effect immediate repairs on the utility system. The utility shall use reasonable efforts to provide the IC with prior notice. If prior notice is not given, the utility shall, upon request, provide the IC written documentation after the fact explaining the circumstances of the disconnection.

    3.4.4 Adverse operating effects

    The utility shall notify the IC as soon as practicable if, based on Good Utility Practice, operation of the SGF may cause disruption or deterioration of service to other customers served from the utility system or affected systems, or if operating the SGF could cause damage to the utility system or affected systems. Supporting documentation used to reach the decision to disconnect shall be provided to the IC upon request. If, after notice, the IC fails to remedy the adverse operating effect within a reasonable time, the utility may disconnect the SGF. The utility shall provide the IC with a five business day notice of such disconnection, unless the provisions of article 3.4.1 apply.

    3.4.5 Modification of the Small Generating Facility

    The Interconnection Customer must receive written authorization from the utility before making changes to the SGF or mode of operations that may have a material impact on the safety or reliability of the utility system or affected system. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the IC makes such modifications without the utility's prior written authorization, the latter shall have the right to temporarily disconnect the SGF.

    3.4.6 Reconnection

    The Parties shall cooperate with each other to restore the SGF, interconnection facilities, and the utility system to their normal operating state as soon as reasonably practicable following a temporary disconnection.

    Article 4. Cost Responsibility for Customer's Interconnection Facilities, Attachment Facilities, and Distribution Upgrades

    4.1 Customer's Interconnection Facilities

    The IC shall be responsible for the costs associated with owning, operating, maintaining, repairing, and replacing the Customer's Interconnection Facilities.

    4.2 Attachment Facilities

    The IC shall pay for one-time and ongoing costs of installing, owning, operating, maintaining and replacing the attachment facilities itemized in Attachment 2 of this Agreement. The utility shall provide an estimated costfor the purchase and construction of the attachment facilities and provide a detailed itemization of such costs. Costs associated with attachment facilities may be shared with other entities that may benefit from such facilities by agreement of the IC, such other entities, and the utility.

    4.3 Distribution upgrades

    The utility shall design, procure, construct, install, and own the distribution upgrades described in Attachment 6 of this Agreement. The actual cost of the distribution upgrades shall be directly assigned to the IC. If the utility and the IC agree, the IC may construct distribution upgrades that are located on land owned by the IC.

    Article 5. Transmission System

    5.1 Transmission system upgrades

    5.1.1 No portion of section 5.1 of this article 5 shall apply unless the interconnection of the Small Generating Facility requires transmission system upgrades.

    5.1.2 The utility shall design, procure, construct, install, and own the transmission system upgrades described in Attachment 6 of this Agreement. If the utility and the Interconnection Customer agree, the IC may construct transmission system upgrades that are located on land owned by the IC. The costs of the transmission system upgrades shall be borne by the IC.

    5.1.3 Notwithstanding any other provision of section 5.1 of article 5, in the event and to the extent an RTE has rules, tariffs, agreements, or procedures properly applying to transmission system upgrades, the provisions of section 5.2 of article 5 shall apply to such upgrades.

    5.2 Regional Transmission Entities

    Notwithstanding any other provision of this Agreement, if the utility's transmission system is under the control of an RTE and the RTE has rules, tariffs, agreements or procedures properly governing operation of the SGF, transmission of the output of the SGF, sale of the output of the SGF, system upgrades required for interconnection of the SGF, or other aspects of the interconnection and operation of the SGF, the IC and the utility shall comply with the applicable of such agreements, rules, tariffs, or procedures.

    5.3 Rights under other agreements

    Notwithstanding any other provision of this Agreement, nothing herein shall be construed as relinquishing or foreclosing any rights, including but not limited to firm transmission rights, capacity rights, transmission congestion rights, or transmission credits, that the IC shall be entitled to, now or in the future, under any other agreement or tariff as a result of, or otherwise associated with system upgrades, including the right to obtain cash reimbursements or transmission credits for transmission service that is not associated with the SGF.

    Article 6. Billing, Payment, Milestones, and Financial Security

    6.1 Billing and payment procedures and final accounting

    6.1.1 The utility shall bill the IC for the design, engineering, construction, and procurement costs of attachment facilities and upgrades contemplated by this Agreement on a monthly basis, or as otherwise agreed by the Parties. The IC shall pay each bill within 30 calendar days of receipt, or as otherwise agreed to by the Parties.

    6.1.2 Within 120 calendar days of completing the construction and installation of the attachment facilities and/or distribution upgrades described in the Attachments to this Agreement, the utility shall provide the IC with a final accounting report of any difference between (i) the IC's cost responsibility for the actual cost of such facilities or upgrades, and (ii) the IC's previous aggregate payments to the utility for such facilities or upgrades. If the IC's cost responsibility exceeds its previous aggregate payments, the utility shall invoice the IC for the amount due and the IC shall make payment to the utility within 30 calendar days. If the IC's previous aggregate payments exceed its cost responsibility under this Agreement, the utility shall refund to the IC an amount equal to the difference within 30 calendar days of the final accounting report.

    6.2 Milestones

    The Parties shall agree on milestones for which each Party is responsible and such milestone shall be listed in Attachment 4 of this Agreement. A Party's milestones obligations under this provision may be modified by agreement. If a Party anticipates that it will be unable to meet a milestone for any reason other than a Force Majeure event, it shall immediately (i) notify the other Party of the reason(s) for not meeting the milestone, and (ii) propose the earliest reasonable alternate date by which it can attain this and future milestones, and (iii) request appropriate amendments to Attachment 4. The Party affected by the failure to meet a milestone shall not withhold agreement to such an amendment unless it will suffer uncompensated economic or operational harm from the delay, attainment of the same milestone has previously been delayed, or it has reason to believe that the delay in meeting the milestone is intentional or unwarranted notwithstanding the circumstances explained by the Party proposing the amendment.

    6.3 Financial security arrangements

    At least 20 business days prior to the commencement of the design, procurement, installation, or construction of a discrete portion of the attachment facilities and distribution upgrades, the Interconnection Customer shall provide the utility, at the IC's option, a guarantee, a surety bond, letter of credit or other form of security that is reasonably acceptable to the utility and is consistent with the Uniform Commercial Code of the jurisdiction where the point of interconnection is located. Such security for payment shall be in an amount sufficient to cover the costs for designing, procuring, installing, and constructing the applicable portion of the attachment facilities and distribution upgrades and shall be reduced on a dollar-for-dollar basis for payments made to the utility under this Agreement during its term. In addition:

    6.3.1 The guarantee must be made by an entity that meets the creditworthiness requirements of the utility, and contain terms and conditions that guarantee payment of any amount that may be due from the IC, up to an agreed-to maximum amount.

    6.3.2 The letter of credit or surety bond must be issued by a financial institution or insured reasonably acceptable to the utility and must specify a reasonable expiration date.

    Article 7. Assignment, Liability, Indemnity, Force Majeure, Consequential Damages, and Default

    7.1 Assignment

    This Agreement may be assigned by either Party upon 15 business days prior written notice and opportunity to object by the other Party; provided that:

    7.1.1 Either Party may assign this Agreement without the consent of the other Party to any affiliate of the assigning Party with an equal or greater credit rating and with the legal authority and operational ability to satisfy the obligations of the assigning Party under this Agreement;

    7.1.2 The Interconnection Customer shall have the right to assign this Agreement, without the consent of the utility, for collateral security purposes to aid in providing financing for the SGF, provided that the IC will promptly notify the utility of any such assignment.

    7.1.3 Any attempted assignment that violates this article is void and ineffective.

    Assignment shall not relieve a Party of its obligations, nor shall a Party's obligations be enlarged, in whole or in part, by reason thereof. An assignee is responsible for meeting the same financial, credit, and insurance obligations as the IC. Where required, consent to assignment will not be unreasonably withheld, conditioned or delayed.

    7.2 Limitation of liability

    Each Party's liability to the other Party for any loss, cost, claim, injury, liability, or expense, including reasonable attorney's fees, relating to or arising from any act or omission in its performance of this Agreement, shall be limited to the amount of direct damage actually incurred. In no event shall either Party be liable to the other Party for any indirect, special, consequential, or punitive damages, except as authorized by this Agreement.

    7.3 Indemnity

    7.3.1 This provision protects each Party from liability incurred to third parties as a result of carrying out the provisions of this Agreement. Liability under this provision is exempt from the general limitations on liability found in article 7.2.

    7.3.2 The Parties shall at all times indemnify, defend, and hold the other Party harmless from, any and all damages, losses, claims, including claims and actions relating to injury to or death of any person or damage to property, demand, suits, recoveries, costs and expenses, court costs, attorney fees, and all other obligations by or to third parties, arising out of or resulting from the other Party's action or failure to meet its obligations under this Agreement on behalf of the indemnifying Party, except in cases of gross negligence or intentional wrongdoing by the indemnified Party.

    7.3.3 If an indemnified Party is entitled to indemnification under this article as a result of a claim by a third party, and the indemnifying Party fails, after notice and reasonable opportunity to proceed under this article, to assume the defense of such claim, such indemnified person may at the expense of the indemnifying Party contest, settle or consent to the entry of any judgment with respect to, or pay in full, such claim.

    7.3.4 If an indemnifying Party is obligated to indemnify and hold any indemnified person harmless under this article, the amount owing to the indemnified person shall be the amount of such indemnified person's actual loss, net of any insurance or other recovery.

    7.3.5 Promptly after receipt by an indemnified person of any claim or notice of the commencement of any action or administrative or legal proceeding or small generator investigation as to which the indemnity provided for in this article may apply, the indemnified person shall notify the indemnifying Party of such fact. Any failure of or delay in such notification shall not affect a Party's indemnification obligation unless such failure or delay is materially prejudicial to the indemnifying party.

    7.4 Consequential damages

    Other than as expressly provided for in this Agreement, neither Party shall be liable under any provision of this Agreement for any losses, damages, costs or expenses for any special, indirect, incidental, consequential, or punitive damages, including but not limited to loss of profit or revenue, loss of the use of equipment, cost of capital, cost of temporary equipment or services, whether based in whole or in part in contract, in tort, including negligence, strict liability, or any other theory of liability; provided that damages for which a Party may be liable to the other Party under another agreement will not be considered to be special, indirect, incidental, or consequential damages hereunder.

    7.5 Force Majeure

    7.5.1 As used in this article, a Force Majeure event means "any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, any order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities, or any other cause beyond a Party's control. A Force Majeure event does not include an act of negligence or intentional wrongdoing."

    7.5.2 If a Force Majeure event prevents a Party from fulfilling any obligations under this Agreement, the Party affected by the Force Majeure event ("Affected Party") shall promptly notify the other Party, either in writing or via the telephone, of the existence of the Force Majeure event. The notification must specify in reasonable detail the circumstances of the Force Majeure event, its expected duration, and the steps that the Affected Party is taking to mitigate the effects of the event on its performance. The Affected Party shall keep the other Party informed on a continuing basis of developments relating to the Force Majeure event until the event ends. The Affected Party will be entitled to suspend or modify its performance of obligations under this Agreement (other than the obligation to make payments) only to the extent that the effect of the Force Majeure event cannot be mitigated by the use of reasonable efforts. The Affected Party will use reasonable efforts to resume its performance as soon as possible.

    7.6 Default

    7.6.1 No default shall exist where such failure to discharge an obligation (other than the payment of money) is the result of a Force Majeure event as defined in this Small Generator Interconnection Agreement or the result of an act or omission of the other Party. Upon a default, the Nondefaulting Party shall give written notice of such default to the Defaulting Party. Except as provided in article 7.6.2, the Defaulting Party shall have 60 calendar days from receipt of the default notice within which to cure the default; however, if the default is not capable of cure within 60 calendar days, the Defaulting Party shall commence the cure within 20 calendar days after notice and continuously and diligently complete the cure within six months from receipt of the default notice; and, if cured within such time, the default specified in such notice shall cease to exist.

    7.6.2 If a default is not cured as provided in this article, or if a default is not capable of being cured within the period provided for herein, the Nondefaulting Party shall have the right to terminate this Agreement by written notice at any time until cure occurs, and be relieved of any further obligation hereunder and, whether or not that Party terminates this Agreement, to recover from the Defaulting Party all amounts due hereunder, plus all other damages and remedies to which it is entitled at law or in equity. The provisions of this article will survive termination of this Agreement.

    Article 8. Insurance

    8.1 The Interconnection Customer shall, at its own expense, maintain in force general liability insurance without any exclusion for liabilities related to the interconnection undertaken pursuant to this Agreement. The amount of such insurance shall be in accordance with 20VAC5-314-160 of the Commission's Regulations Governing the Interconnection of Small Electrical Generators. The IC shall obtain additional insurance only if necessary as a function of owning and operating a generating facility. Insurance shall be obtained from an insurance provider authorized to do business in the State of Virginia. Certification that such insurance is in effect shall be provided upon request of the utility, except that the IC shall show proof of insurance to the utility no later than 10 business days prior to the anticipated commercial operation date of the SGF. An IC of sufficient creditworthiness may propose to self-insure for such liabilities, and such a proposal shall not be unreasonably rejected.

    8.2 The utility agrees to maintain general liability insurance or self insurance consistent with the utility's commercial practice. Such insurance or self-insurance shall not exclude coverage for the utility's liabilities undertaken pursuant to this Agreement.

    8.3 The Parties further agree to notify each other whenever an accident or incident occurs resulting in any injuries or damages that are included within the scope of coverage of such insurance, whether or not such coverage is sought.

    Article 9. Confidentiality

    9.1 Confidential information shall mean any confidential and/or proprietary information provided by one Party to the other Party that is clearly marked or otherwise designated "Confidential." For purposes of this Agreement all design, operating specifications, and metering data provided by the Interconnection Customer shall be deemed confidential information regardless of whether it is clearly marked or otherwise designated as such.

    9.2 Confidential information does not include information previously in the public domain, required to be publicly submitted or divulged by governmental authorities (after notice to the other Party and after exhausting any opportunity to oppose such publication or release), or necessary to be divulged in an action to enforce this Agreement. Each Party receiving confidential information shall hold such information in confidence and shall not disclose it to any third party nor to the public without the prior written authorization from the Party providing that information, except to fulfill obligations under this Agreement, or to fulfill legal or regulatory requirements.

    9.2.1 Each Party shall employ at least the same standard of care to protect confidential information obtained from the other Party as it employs to protect its own confidential information.

    9.2.2 Each Party is entitled to equitable relief, by injunction or otherwise, to enforce its rights under this provision to prevent the release of confidential information without bond or proof of damages, and may seek other remedies available at law or in equity for breach of this provision.

    9.3 Notwithstanding anything in this Agreement to the contrary, if the Virginia State Corporation Commission ("Commission"), during the course of an investigation or otherwise, requests information from one of the Parties that is otherwise required to be maintained in confidence, the Party shall provide the requested information to the Commission, within the time provided for in the request for information. In providing the information to the Commission, the Party may request that the information be treated as confidential and nonpublic by the Commission and that the information be withheld from public disclosure. Parties are prohibited from notifying the other Party prior to the release of the confidential information to the Commission. A Party shall notify the other Party when it is notified by the Commission that a request to release confidential information has been received by the Commission, at which time either Party may respond to the Commission before such information would be made public.

    Article 10. Disputes

    10.1 The Parties agree to attempt to resolve all disputes arising out of the interconnection process according to the provisions of this article.

    10.2 In the event of a dispute, either Party shall provide the other Party with a written Notice of Dispute. Such Notice shall describe in detail the nature of the dispute. The Parties shall make a good faith effort to resolve the dispute informally within 10 business days.

    10.3 If the dispute has not been resolved within 10 business days after receipt of the Notice, either Party may seek resolution assistance from the Commission's Division of Energy Regulation where the matter will be handled as an informal complaint.

    Alternatively, either Party may, upon mutual agreement, seek resolution through the assistance of a dispute resolution service. The dispute resolution service will assist the Parties in either resolving the dispute or in selecting an appropriate dispute resolution venue (e.g., mediation, settlement judge, early neutral evaluation, or technical expert) to assist the Parties in resolving their dispute. Each Party shall conduct all negotiations in good faith and shall be responsible for one-half of any costs paid to neutral third parties.

    10.4 If the dispute remains unresolved either Party may petition the Commission to handle the dispute as a formal complaint or may exercise whatever rights and remedies it may have in equity or law consistent with the terms of this Agreement.

    Article 11. Taxes

    11.1 The Parties agree to follow all applicable tax laws and regulations

    11.2 Each Party shall cooperate with the other to maintain the other Party's tax status. Nothing in this Agreement is intended to adversely affect the utility's tax exempt status with respect to the issuance of bonds including, but not limited to, local furnishing bonds.

    Article 12. Miscellaneous

    12.1 Governing law, regulatory authority, and rules

    The validity, interpretation and enforcement of this Agreement and each of its provisions shall be governed by the laws of the State of Virginia without regard to its conflicts of law principles. This Agreement is subject to all applicable laws and regulations. Each Party expressly reserves the right to seek changes in, appeal, or otherwise contest any laws, orders, or regulations of a governmental authority.

    12.2 Amendment

    The Parties may amend this Agreement by a written instrument duly executed by both Parties.

    12.3 No third-party beneficiaries

    This Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and where permitted, their assigns.

    12.4 Waiver

    12.4.1 The failure of a Party to this Agreement to insist, on any occasion, upon strict performance of any provision of this Agreement will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party.

    12.4.2 Any waiver at any time by either Party of its rights with respect to this Agreement shall not be deemed to be a continuing waiver or a waiver with respect to any other failure to comply with any other obligation, right, or duty of this Agreement. Termination or default of this Agreement for any reason by the Interconnection Customer shall not constitute a waiver of the IC's legal rights to obtain an interconnection from the utility. Any waiver of this Agreement shall, if requested, be provided in writing.

    12.5 Entire Agreement

    This Agreement, including all Attachments, constitutes the entire agreement between the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between the Parties with respect to the subject matter of this Agreement. There are no other agreements, representations, warranties, or covenants which constitute any part of the consideration for, or any condition to, either Party's compliance with its obligations under this Agreement.

    12.6 Multiple counterparts

    This Agreement may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument.

    12.7 No partnership

    This Agreement shall not be interpreted or construed to create an association, joint venture, agency relationship, or partnership between the Parties or to impose any partnership obligation or partnership liability upon either Party. Neither Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, the other Party.

    12.8 Severability

    If any provision or portion of this Agreement shall for any reason be held or adjudged to be invalid or illegal or unenforceable by any court of competent jurisdiction or other governmental authority, (i) such portion or provision shall be deemed separate and independent, (ii) the Parties shall negotiate in good faith to restore insofar as practicable the benefits to each Party that were affected by such ruling, and (iii) the remainder of this Agreement shall remain in full force and effect.

    12.9 Environmental releases

    Each Party shall notify the other Party, first orally and then in writing, of the release of any hazardous substances, any asbestos or lead abatement activities, or any type of remediation activities related to the Small Generating Facility, the customer's interconnection facilities, or attachment facilities, each of which may reasonably be expected to affect the other Party. The notifying Party shall (i) provide the notice as soon as practicable, provided such Party makes a good faith effort to provide the notice no later than 24 hours after such Party becomes aware of the occurrence, and (ii) promptly furnish to the other Party copies of any publicly available reports filed with any governmental authorities addressing such events.

    12.10 Subcontractors

    Nothing in this Agreement shall prevent a Party from utilizing the services of any subcontractor as it deems appropriate to perform its obligations under this Agreement; however, each Party shall require its subcontractors to comply with all applicable terms and conditions of this Agreement in providing such services and each Party shall remain primarily liable to the other Party for the performance of such subcontractor.

    12.10.1 The creation of any subcontract relationship shall not relieve the hiring Party of any of its obligations under this Agreement. The hiring Party shall be fully responsible to the other Party for the acts or omissions of any subcontractor the hiring Party hires as if no subcontract had been made; however, in no event shall the utility be liable for the actions or inactions of the IC or its subcontractors with respect to obligations of the IC under this Agreement. Any applicable obligation imposed by this Agreement upon the hiring Party shall be equally binding upon, and shall be construed as having application to, any subcontractor of such Party.

    12.10.2 The obligations under this article will not be limited in any way by any limitation of subcontractor's insurance.

    12.11 Reservation of rights

    The utility shall have the right to make a unilateral filing with the Commission to modify this Agreement with respect to any rates, terms and conditions, charges, classifications of service, rule or regulation.

    Article 13. Notices

    13.1 General

    Unless otherwise provided in this Agreement, any written notice, demand, or request required or authorized in connection with this Agreement ("Notice") shall be deemed properly given if delivered in person, delivered by recognized national courier service, or sent by first class mail, postage prepaid, to the person specified below:

    If to the Interconnection Customer:

    Interconnection Customer:____________________________________

    Attention:_________________________________________________

    Address:_________________________________________________

    City, State, Zip:____________________________________________

    Phone:___________________________ Fax:____________________

    If to the Utility:

    Utility:___________________________________________

    Attention:_________________________________________________

    Address:_________________________________________________

    City, State, Zip:____________________________________________

    Phone:___________________________ Fax:____________________

    13.2 Billing and payment

    Billings and payments shall be sent to the addresses set out below:

    If to the Interconnection Customer:

    Interconnection Customer:_____________________________________

    Attention:__________________________________________________

    Address:__________________________________________________

    City, State, Zip:______________________________________________

    If to the Utility:

    Utility:___________________________________________

    Attention:__________________________________________________

    Address:__________________________________________________

    City, State, Zip:_____________________________________________

    13.3 Alternative forms of notice

    Any notice or request required or permitted to be given by either Party to the other and not required by this Agreement to be given in writing may be so given by telephone, facsimile or e-mail to the telephone numbers and email addresses set out below:

    If to the Interconnection Customer:

    Interconnection Customer:_______________________________________

    Attention:____________________________________________________

    Address:____________________________________________________

    City, State, Zip:_______________________________________________

    Phone:___________________________ Fax:_______________________

    If to the Utility:

    Utility:___________________________________________

    Attention:____________________________________________________

    Address:____________________________________________________

    City, State, Zip:_______________________________________________

    Phone:___________________________ Fax:_______________________

    13.4 Designated operating representative

    The Parties may also designate operating representatives to conduct the communications which may be necessary or convenient for the administration of this Agreement. This person will also serve as the point of contact with respect to operations and maintenance of the Party's facilities.

    Interconnection Customer's Operating Representative:

    Interconnection Customer:_______________________________________

    Attention:____________________________________________________

    Address:____________________________________________________

    City, State, Zip:_______________________________________________

    Phone:___________________________ Fax:_______________________

    Utility's Operating Representative:

    Utility:___________________________________________

    Attention:____________________________________________________

    Address:____________________________________________________

    City, State, Zip:_______________________________________________

    Phone:___________________________ Fax:_______________________

    13.5 Changes to the notice information

    Either Party may change this information by giving five business days written notice prior to the effective date of the change.

    Article 14. Signatures

    IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by their respective duly authorized representatives.

    For the Utility

    Name:_______________________________________________________

    Title:________________________________________________________

    Date:_____________________

    For the Interconnection Customer

    Name:______________________________________________________

    Title:________________________________________________________

    Date:_____________________

    Attachment 1 to

    Schedule 6

    Glossary of Terms

    "Affected system" means an electric utility system other than that of the utility that may be affected by the proposed interconnection.

    "Affected system operator" means an entity that operates an affected system or, if the affected system is under the operational control of an independent system operator or a Regional Transmission Entity, such independent entity.

    "Applicable laws and regulations" means all duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or administrative orders, permits and other duly authorized actions of any governmental authority.

    "Attachment facilities" means the facilities and equipment owned, operated, and maintained by the utility that are built new in order to physically connect the customer's interconnection facilities to the utility system. Attachment facilities shall not include distribution upgrades or previously existing distribution and transmission facilities.

    "Business day" means Monday through Friday, excluding federal holidays.

    "Certified" has the meaning ascribed to it in Schedule 2 of Chapter 314 (20VAC5-314) of the Virginia Administrative Code.

    "Commission" means the Virginia State Corporation Commission.

    "Competitive service provider" means any entity, other than the utility, supplying electric energy service to the Interconnection Customer.

    "Customer's interconnection facilities" means all the facilities and equipment owned, operated and maintained by the Interconnection Customer, between the Small Generating Facility and the point of interconnection necessary to physically and electrically interconnect the Small Generating Facility to the utility system.

    "Default" means the failure of a breaching Party to cure its breach under the Small Generator Interconnection Agreement.

    "Distribution system" means the utility's facilities and equipment generally delivering electricity to ultimate customers from substations supplied by higher voltages (usually at transmission level). For purposes of this Agreement, all portions of the utility's transmission system regulated by the Commission for which interconnections are not within Federal Energy Regulatory Commission jurisdiction are considered also to be subject to Commission regulations.

    "Distribution upgrades" means the additions, modifications, and upgrades to the utility's distribution system at or beyond the point of interconnection necessary to abate problems on the utility's distribution system caused by the interconnection of the Small Generating Facility. Distribution upgrades do not include customer's interconnection facilities or attachment facilities.

    "Facilities study" has the meaning ascribed to it in the commission's regulations governing the interconnection of small generating facilities at 20VAC5-314-70 E.

    "Feasibility study" has the meaning ascribed to it in the commission's regulations governing the interconnection of small generating facilities at 20VAC5-314-70 C.

    "FERC" means the Federal Energy Regulatory Commission.

    "Good Utility Practice" means any of the practices, methods and acts engaged in or approved by a significant portion of the electric industry during the relevant time period, or any of the practices, methods and acts which, in the exercise of reasonable judgment in light of the facts known at the time the decision was made, could have been expected to accomplish the desired result at a reasonable cost consistent with good business practices, reliability, safety and expedition. Good Utility Practice is not intended to be limited to the optimum practice, method, or act to the exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted in the region.

    "Governmental authority" means any federal, state, local or other governmental regulatory or administrative agency, court, commission, department, board, or other governmental subdivision, legislature, rulemaking board, tribunal, or other governmental authority having jurisdiction over the Parties, their respective facilities, or the respective services they provide, and exercising or entitled to exercise any administrative, executive, police, or taxing authority or power; provided that such term does not include the Interconnection Customer, the utility, or a utility affiliate.

    "Interconnection Customer" or "IC" means any entity proposing to interconnect a new Small Generating Facility with the utility system.

    "Interconnection request" means the IC's request, in accordance with Chapter 314 (20VAC5-314) of the Virginia Administrative Code, to interconnect a new Small Generating Facility, or to increase the capacity of, or make a material modification to the operating characteristics of, an existing Small Generating Facility that is interconnected with the utility system.

    "Interconnection studies" means the studies conducted by the utility, or a third party agreed to by the utility and the Interconnection Customer, in order to determine the interaction of the Small Generating Facility with the utility system and the affected systems in order to specify any modifications to the Small Generating Facility or the electric systems studied to ensure safe and reliable operation of the Small Generating Facility in parallel with the utility system.

    "Material modification" means a modification that has a material impact on the cost or timing of any Interconnection Request with a later queue priority date.

    "Operating requirements" means any operating and technical requirements that may be applicable due to regional transmission entity, independent system operator, control area, or the utility's requirements, including those set forth in the Small Generator Interconnection Agreement.

    "Party" or "Parties" means the utility, the Interconnection Customer or both.

    "Point of interconnection" means the point where the customer's interconnection facilities connect to the utility system.

    "Regional Transmission Entity" or "RTE" shall refer to an entity having the management and control of a utility's transmission system as further set forth in § 56-579 of the Code of Virginia.

    "Small Generating Facility" or "generator" or "SGF" means the Interconnection Customer's equipment for the production of electricity identified in the Interconnection Request.

    "Small Generator Interconnection Agreement" or "SGIA" means the agreement between the utility and the Interconnection Customer as set forth in Schedule 6 of Chapter 314 (20VAC5-314) of the Virginia Administrative Code.

    "Supplemental review" has the meaning ascribed to it in the Commission's regulations governing the interconnection of small generating facilities at 20VAC5-314-70 I.

    "System" or "utility system" means the distribution and transmission facilities owned, controlled, or operated by the utility that are used to deliver electricity.

    "System impact study" has the meaning ascribed to it in the Commission's regulations governing the interconnection of small generating facilities at 20VAC5-314-70 D.

    "Tariff" means the rates, terms and conditions filed by the utility with the Commission for the purpose of providing Commission-regulated electric service to retail customers.

    "Transmission system" means the utility's facilities and equipment delivering electric energy to the distribution system, such facilities usually being operated at voltages above the utility's typical distribution system voltages.

    "Utility" means the public utility company subject to regulation by the Commission pursuant to Chapter 10 (§ 56-232 et seq.) of Title 56 of the Code of Virginia with regard to rates and/or service quality to which the Interconnection Customer proposes to interconnect a Small Generating Facility.

    Attachment 2 to

    Schedule 6

    Description and Costs of the Small Generating Facility, Customer's Interconnection Facilities, Attachment Facilities and Metering Equipment

    The following shall be provided in this exhibit:

    1. An itemization of the major equipment components owned by the Interconnection Customer and the utility, including components of the Small Generating Facility, the customer's interconnection facilities, attachment facilities, and metering equipment. Such itemization shall identify the owner of each item listed.

    2. The utility's estimated itemized cost of its attachment facilities and its metering equipment.

    3. The utility's estimated cost of its annual operation and maintenance expenses associated with attachment facilities and metering equipment to be charged to the Interconnection Customer.

    Attachment 3 to

    Schedule 6

    One-line Diagram Depicting the Small Generating Facility, Customer's Interconnection Facilities, Attachment Facilities, Metering Equipment, and Distribution Upgrades

    (Diagram and description to be provided by Interconnection Customer unless the utility elects to prepare this schedule. If this schedule is prepared by the utility, the IC shall provide a one-line diagram of the SGF and IC's interconnection facilities for the utility to use as a data source for preparing this schedule.)

    Attachment 4 to

    Schedule 6

    Milestones

    In-Service Date:___________________

    Critical milestones and responsibility as agreed to by the Parties:

    Milestone/Date

    Responsible Party

    (1)___________________________

    ___________________________

    (2)___________________________

    ___________________________

    (3)___________________________

    ___________________________

    (4)___________________________

    ___________________________

    (5)___________________________

    ___________________________

    (6)___________________________

    ___________________________

    (7)___________________________

    ___________________________

    (8)___________________________

    ___________________________

    (9)___________________________

    ___________________________

    (10)__________________________

    ___________________________

    Agreed to by:

    For the Utility__________________ Date__________

    For the Transmission Owner (If Applicable)_____________ Date__________

    For the Interconnection Customer____________________ Date__________

    Attachment 5 to

    Schedule 6

    Additional Operating Requirements for the Utility System and Affected Systems Needed to Support the Interconnection Customer's Needs

    The utility shall provide requirements that must be met by the Interconnection Customer prior to initiating parallel operation with the utility system.

    Attachment 6 to

    Schedule 6

    Utility's Description of its Distribution and Transmission Upgrades and Estimate of Upgrade Costs

    The utility shall provide the following in this attachment:

    1. An itemized list of the upgrades required to be constructed by the utility prior to interconnection of the Small Generating Facility, with transmission and distribution related upgrades shown separately.

    2. An estimate of the cost of each item listed pursuant to item 1.

    3. An estimate of annual operation and maintenance expenses associated with such upgrades that are to be charged to the Interconnection Customer, shown separately for transmission and distribution related items.