A. If the interconnection request is for an increase in capacity for an existing small generating facility, the interconnection request shall be evaluated on the basis of the new total capacity of the SGF.
B. If the interconnection request is for a SGF that includes multiple energy production devices at a site for which the interconnection customer seeks a single point of interconnection, the interconnection request shall be evaluated on the basis of the aggregate capacity of the multiple devices.
C. The interconnection request shall be evaluated using the maximum rated capacity of the SGF.
Historical Notes
Derived from Volume 25, Issue 20, eff. May 21, 2009.