Section 240. Issuance of the construction permit  


Latest version.
  • A construction permit shall be issued to the owner by the commissioner no later than 60 days after receipt of a complete and approvable application submitted under 12VAC5-630-230. If applicable, the applicant shall comply with 12VAC5-630-340 prior to issuance of the permit.

Historical Notes

Derived from VR355-34-100 § 2.14, eff. April 1, 1992.

Statutory Authority

§§ 32.1-12 and 32.1-176 of the Code of Virginia.