Virginia Administrative Code (Last Updated: January 10, 2017) |
Title 12. Health |
Agency 5. Department of Health |
Chapter 590. Waterworks Regulations |
Section 300. Procedure for obtaining a general permit for distribution mains
-
In lieu of obtaining a permit for each distribution main project, an owner may elect to obtain a general permit for distribution mains. These general permits are issued by the commissioner, but all requests for a general permit are directed initially to the field office. The following procedure for obtaining the general permit shall be used:
1. The owner shall develop, adopt, and have division approval of general specifications and plan details covering water main design and construction.
2. The owner shall enter into a memorandum of understanding (MOU) with the division which outlines the following system-specific requirements, and the owner's method of compliance with such requirements:
a. The maximum size of pipe to be covered by the general permit;
b. The means for modifying the division approved general specifications and plan details;
c. The maintenance of engineering capabilities satisfactory to the division, either on-staff or through contractual arrangements;
d. The preparation of engineering plans and specifications for individual projects;
e. The maintenance of up-to-date distribution system maps and other appropriate records; and
f. The submission by the owner to the division of appropriate reports, including an annual report, concerning all projects constructed under the terms of the general permit and information concerning changes to the distribution system.
Historical Notes
Derived from VR355-18-003.25 § 1.31, eff. August 1, 1991; amended, Volume 09, Issue 17, eff. June 23, 1993.