Section 270. Inspection and correction  


Latest version.
  • A. Within 30 days after placing a new or modified waterworks or water supply into operation, the owner shall test the water produced in a manner acceptable to the division. The field office will be notified of the time and place of the tests. Results of the tests will be sent to the field office.

    B. The commissioner, a member of the board, or a member of the division has a right to inspect any waterworks or water supply and to be present for any testing in accordance with Title 32.1 of the Code of Virginia.

Historical Notes

Derived from VR355-18-003.22 § 1.28, eff. August 1, 1991; amended, Volume 09, Issue 17, eff. June 23, 1993.

Statutory Authority

§§ 32.1-12 and 32.1-170 of the Code of Virginia.